Title: Panel Session:
1Panel Session NASA Supplier Assessments
Processes, Results and Lessons Learned
GSFCs Supplier Assessments Mike Kelly,
Chief Institutional Support Office Supply Chain
2008 Conference October 28, 2008
2Todays Presentation
- Organization / Team
- Purpose and Scope
- Process Overview
- Approach
- Reporting
- Other Highlights
3Safety Mission Assurance Directorate Goddard
Space Flight Center
Supply Chain Management Team
4Supply Chain Management Team
- Mike Kelly (michael.p.kelly_at_nasa.gov)
- Charles Kim (charles.k.kim_at_nasa.gov)
- Jonathan Root (jonathan.root_at_nasa.gov)
- Louis Thomas (louis.a.thomas_at_nasa.gov)
- Vic DiMarco (victor.v.dimarco_at_nasa.gov)
- Plus assessors from GSFC and the NASA Contract
Assurance Services contract!
5Supplier AssessmentsPurpose and Scope
- Purpose
- Assess conformance with requirements and monitor
improvements to better enable the realization of
quality products and services for NASA mission
projects - Scope includes the Suppliers implementation of
- NASA contractual requirements, including risk
management and systems safety - Quality Management Standards (IS0 90012000 or
AS9100,Rev.B) - Internal processes / procedures supporting the
fulfillment of requirements - Government-Industry Data Exchange Program (GIDEP)
Alerts - Industrial Safety
- Each assessment is tailored (per Assessment Plan)
to address applicable requirements, past findings
and any NASA project management concerns
6Process OverviewGSFC Supplier Assessments
- Plan Assessment
- Selection Factors
- Scheduling and Coordination
- Tailored Assessment Plan
- Assessment Follow-up
- Corrective / Preventive Actions
- On-site Verification
- Reporting
- Knowledge Sharing
- Assessment Database
- Conduct Assessment
- GSFC-led expert team
- Strengths and Areas for Improvement
- Reporting
- NASA Projects
- NASA Acquisition Processes
- Other NASA Centers / Agencies
7Assessment Approach Highlights
- Assessments conducted by an expert team under
GSFC Supply Chain Management leadership - Open communication and coordination before,
during and after - Assessment Plan provided in advance for feedback
/ revision - Daily debriefs and Assessment Out-Brief
- Open door for communication of concerns
throughout the assessment process - Feedback welcomed! -- Supplier Assessment Team
Evaluation Form - Focused on conformance with requirements,
strengths (positive comments and commendations),
and areas for improvement (non-compliances and
observations)
8Assessment Approach Highlights - continued
- Assessment method employs sampling, objective
evidence and professional judgment - Coordination / collaboration with GSFC project
management, other NASA centers and agencies
(e.g., DCMA) and with companys customers as
appropriate - GSFC works closely with suppliers to address
assessment results and close Corrective Actions - Assessment Report with documented findings
provided for comment/response - Corrective action responses reviewed
- Onsite (eyes-on) verification usually conducted
NASA / Industry Teamwork Mission Success!
9Assessment Reporting
- Assessment team documents non-compliances,
observations and commendations during the course
of the assessment - Critical Noncompliance Failure to fulfill or
comply with requirements that could have serious
safety and mission consequences (e.g., loss of
life, serious injury to personnel, damage to
high-value property, defective mission-critical
product) - Noncompliance Failure to fulfill or comply with
requirements - Observation A condition or process that
conforms with requirements, but warrants
improvement based on industry practices - Commendation A condition or process that is
considered an industry benchmark - Daily debrief with informal discussion of the
days activities and plans for the next day - Out-Brief with any draft non-compliances,
observations or commendations presented at the
conclusion of the assessment - Assessment Report provided for Supplier
comment/response - Corrective Action responses and verification
reported/shared within NASA
10Other Highlights
- Assessments support the portfolio of mission
projects managed by GSFC, examining suppliers at
multiple tiers of the projects supply chains - Conducted 38 assessments (full follow-up) in
2007 39 assessments completed/scheduled in 2008 - In 2009 . ramping-up assessments to include more
lower tier suppliers - Summary trend data from assessments available to
suppliers for benchmarking analysis.
11Discussion
Questions?