Title: Recent developments in auditing Public Private Partnerships (PPPs)
1Recent developments in auditing Public Private
Partnerships (PPPs)
- Richard Wade
- National Audit Office
- EUROSAI
- Prague, November 2006
2Three main topics
- UK experience to date
- Major audit issues financial performance
- A comprehensive audit approach
3Desired benefits are unchanged
- Private Finance Initiative (PFI) model should
offer - Modern Facilities built with Whole Life Approach
- Delivered to Time and Budget
- Increased Efficiency in Service Provision
- Reduced Cost and/or Better Quality of Service
4PFI schemes some examples
Bridges Schools
Tramways Hospitals
Roads Prisons
5UK PPP experience to date
- 670 signed deals, 430 operational
- Over 50 published NAO reports onPPP/PFI since
1997 - Individual deals and thematic/cross cutting
reports - Construction perfomance
- Financial analysis and financing issues
- Operational performance of prisons
6Traditional procurement cost profile
Capex
Operating Maintenance Costs
t
7Traditional procurement cost profile
8Improved delivery to time and budget
- PFI experience Prior record
- (2002 NAO census) (1999 survey)
- Exceeds price (1) 22 73
- Late delivery 24 70
- Over 2 months late 8
- Note (1) Price agreed at contract (changes in
the PFI case are linked to public sector scope
changes).
9What is the accounting issue for the public
sector?
- Should the fixed asset and the associated finance
be On or Off Balance Sheet? - Macro considerations public expenditure and
borrowing statistics -
-
- (e.g. in the UK Maastricht criteria and the
Sustainable
Investment
rule) - Micro considerations - departmental cash and
capital budgets (affordability) -
10The dangers of Off Balance Sheet Accounting
- Government liabilities are understated
- Payment burdens are shifted onto future
generations - will the debt repayment be
manageable? - Risks associated with the service provision may
be overlooked - Value for Money may be compromised
11Financial Audit based on FRS 5
- Reporting the Substance of Transactions
- The risks inherent in the benefits provided by
an asset determine which entity has the asset - Does the (private) Operator or (public) Service
Purchaser have the highest Net Present Value
exposure to variations in property profits?
12FRS 5 two key risks
- Demand risk that demand for the property will
be greater or less than predicted or expected. - Where demand risk is significant, it
will normally give the clearest evidence of who
should record an asset of the property. - Residual value risk that the actual value of
the property at the end of the contract will
vary. - Where it is significant, residual value risk
will normally give clear evidence of who should
record an asset of the property.
13Some UK projects and their accounting future
treatment
Central govt Local govt and health Whole of Govt Accounts Private sector
Road improvements On Off On Off
New toll roads Off Off On
Schools Off On Off
Prisons On Off (Scotland) On Off
Gov offices etc which revert to public sector On Off On Off
14Continuing Financial Audit confusion
- Prisons usually on balance sheet
- Many schools hospitals off balance sheet
- Issue of the disappearing asset - both parties
claim that the majority of risks are with the
other party and no one puts the asset on their
balance sheet. - Survey of 27 Health and Local government deals
found 24 on neither the public sector nor the
special purpose companys balance sheet.
15Traditional Value for Money audit- applying 4
Pillars Approach
16Time to update the audit approach
- Published methodology looks at the deal as closed
- There is little published guidance once deals are
operational - The value for money assessment can change over
the contract period
17A new approach May 2006
- Two dimensional matrix
- Chronological approach based on key stages
- Key performance themes/indicators, supported by
detailed audit questions - what you would expect to find if a project
delivers value for money at every stage
18Life cycle of PFI deals
STRATEGIC ANALYSIS
TENDERING
MATURE OPERATIONAL
EARLY OPERATIONAL
CONTRACT COMPLETION
ASSET CONSTRUCTION
19Key life cycle themes
- Suitability to business needs
- Whether it is the best alternative
- Whether stakeholders get what they contracted for
- Quality of delivery of project
- Whether it offers optimum mix of scope, cost and
quality - Quality of risk management
20ILLUSTRATIVE MATRIX
Strategic analysis Tendering Contract completion Asset construction Early operational Mature operational
Fit with business needs Good OBC Clear deliverables Robust output specification Clear cut contract Delivery to specification Contract being met Service meeting requirement
Appropriate delivery mechanism Results of options analysis Baseline of service performance Review of evaluation Delivery to specification Review of performance Review of performance
Stakeholder support Review of consultation Review of stakeholder buy in Key stakeholder support Stakeholders informed of progress Review of stakeholder satisfaction Analysis of stakeholder benefits
Quality of project management Design of project management Effective team in place Contract management arrangement Problem solving arrangement Post deal evaluation Effective internal controls
Balance of cost, quality and finance Affordable based on market soundings Good quality bids received Analysis of financing terms Changes made are vfm Deal remains affordable Benchmarking of price and quality
Quality of risk management Analysis of scope for risk transfer Risk management procedures Appropriate risk transfer agreed Management of risk Risk transfer sticks Procedures updated
21Example 1 Theme Fit with the business
requirements of the Public Authority
- Has the best form of project to pursue been
selected? - Have top level output specifications for the
required services been drawn up? - Further test questions such as
- Have clear objectives for the project been set?
- Have the projects wider socio-economic benefits
been quantified? - Does the proposed solution clearly meet business
requirements?
22Example 2 Theme PFI is the appropriatedelivery
mechanism
- Has the project been assessed as part of a
suitable investment programme for PFI? - Has a good outline business case justifying a PFI
procurement route been produced? - Are the qualitative reasons for proceeding with
PFI clearly justified?
23HOW THE APPROACH CAN BE USED
- As a guide to VFM of individual deals
- At a programme level
- As a traffic light system to highlight main
risks
24More recent PFI issues
- Does EU competitive dialogue imply fully funded
bids with duplication of costs? - Early UK deals are now reaching the stage of
periodic market testing for the cost of service
delivery. What are the issues for auditors?