Alpha Magnetic Spectrometer 02 Phase II Flight Safety Review Mission Operations CERN TIM April 25, 2 - PowerPoint PPT Presentation

1 / 94
About This Presentation
Title:

Alpha Magnetic Spectrometer 02 Phase II Flight Safety Review Mission Operations CERN TIM April 25, 2

Description:

Alpha Magnetic Spectrometer 02 Phase II Flight Safety Review Mission Operations CERN TIM April 25, 2 – PowerPoint PPT presentation

Number of Views:48
Avg rating:3.0/5.0
Slides: 95
Provided by: Urba1
Category:

less

Transcript and Presenter's Notes

Title: Alpha Magnetic Spectrometer 02 Phase II Flight Safety Review Mission Operations CERN TIM April 25, 2


1
Alpha Magnetic Spectrometer 02Phase II Flight
Safety Review Mission OperationsCERN TIM
April 25, 2007Timothy J. Urban / ESCG /
Barrios Technology
2
Alpha Magnetic Spectrometer 02Mission
Operations
  • Outline
  • Timeline
  • Pre-Launch Operations
  • Ascent Operations
  • On-Orbit Operations
  • STS
  • SRMS to SSRMS Hand-off
  • ISS
  • EVA Compatibility
  • Contingency Operations

3
Alpha Magnetic Spectrometer 02Mission
Operations
  • Overall Milestone Timeline

4
Alpha Magnetic Spectrometer 02Mission
Operations
PRE-LAUNCH OPERATIONS
5
Alpha Magnetic Spectrometer 02Mission
Operations Pre-Launch
  • Outline
  • KSC Flow
  • Pre-Launch Operations
  • T0 Umbilical Interfaces
  • Standard Switch Panel Configuration
  • Payload Data Interface Panel 2 (PDIP2)
    Configuration
  • Timeline
  • Launch Commit Criteria

6
Alpha Magnetic Spectrometer 02Mission
Operations Pre-Launch
  • KSC Flow
  • Arrive at Space Station Processing Facility
    (SSPF)
  • Integrate remainder of AMS-02 hardware
  • Top-off SFHe and Warm He Gas Supply
  • Power up/checkout Avionics and charge Magnet
  • Discharge Magnet and power off all systems
  • Functional Interface Test (FIT)
  • Power up/checkout avionics, no Magnet Charge

7
Alpha Magnetic Spectrometer 02Mission
Operations Pre-Launch
  • KSC Flow (continued)
  • Load into canister and transport to Canister
    Rotation Facility (CRF)
  • Rotate canister in CRF (may require use of small,
    payload-mounted vent pump)
  • Transport to Pad for Vertical Installation in
    Payload Change-out Room (PCR)
  • Interface Verification Test (IVT)
  • End to End Tests in STS
  • Continued payload servicing until L-88 hours
  • Continued payload monitoring until L-9 minutes

8
Alpha Magnetic Spectrometer 02Mission
Operations Initial Operations
9
Alpha Magnetic Spectrometer 02Mission
Operations Pre-Launch
10
Alpha Magnetic Spectrometer 02Mission
Operations Pre-Launch
  • PRE-LAUNCH OPERATIONS
  • Activate/checkout AMS-02 avionics subsystems and
    thermally condition payload
  • Approximately 1000 1500 W for J-Crate,
    Cryo-valves, Cryo-coolers, CAB critical
    functions, and SFHe Tank Vent Pump
  • Maximum of 2 kW (peak) for calibration and
    contingency based upon thermal load in purged PLB
  • No magnet charging possible on STS APCU power
    supplied to prime PDS side B has no
    connectivity to the CAB
  • Final cryogenic servicing
  • Cryosystems monitoring

11
Alpha Magnetic Spectrometer 02Mission
Operations
PRE-LAUNCH OPERATIONS Cryogenic Ground Support
Equipment Layout in PCR
12
Alpha Magnetic Spectrometer 02Mission
Operations Pre-Launch
  • Pre-Launch Safety
  • PCR / PLB payload operations are being evaluated
    for ground and vehicle safety hazards.
  • Cryogenic temperature evaluation
  • Vent Pump operations (110 VAC) Pre-Launch only
  • He venting exhausted out PCR
  • Payload servicing and check-out in vertical
    orientation
  • Will be tested prior to arrival at KSC
  • PLB thermal loads analysis in work

13
Alpha Magnetic Spectrometer 02Mission
Operations Pre-Launch
  • SFHe Tank Vent Pump
  • Pre-Launch only
  • T0 110 VAC interface and ground safety being
    worked with STS Program and KSC
  • Rotating parts analysis to be performed

14
Alpha Magnetic Spectrometer 02Mission
Operations Pre-Launch
  • T0 Umbilical Interfaces
  • T0 Interfaces via ROEU PDA Vent Pump,
    Cryocoolers, valves, CAB critical monitoring
    functions, and J-Crate
  • Power (120 VDC) to PDS
  • Direct feed to Vent Pump (110 VAC) Pre-Launch
    Only
  • 1553 for command/telemetry requirements
  • High Rate Data via RS422
  • Continuous data using both paths (redundancy)
    until L-9 min to monitor health status of Cryo
    systems (Vacuum Case pressure and SFHe
    pressure/temp), supporting GO / NO GO Call from
    AMS-02 See Page 15

15
Alpha Magnetic Spectrometer 02Mission
Operations Pre-Launch
  • Pre-Launch Configuration
  • Payload Data Interface Panel 2 (PDIP2)
  • Low rate data (1553) is routed through T0
    umbilical to MLP GSE computers from Shuttle PDIP2
    with the AMS-02 1553 switch in the T0
    position, and program provided jumper installed
    on PDIP2 front panel J4 connector
  • High rate data (RS422) is routed through T0
    umbilical to MLP GSE computers from Shuttle PDIP2
    via payload provided cable installed between
    PDIP2 front panel J103 and J105 connectors.

16
Alpha Magnetic Spectrometer 02Mission
Operations Pre-Launch
  • Pre-Launch Standard Switch Panel Configuration

17
Alpha Magnetic Spectrometer 02Mission
Operations Pre-Launch
  • Pre-launch Timeline
  • Installation at L-32 days through L-30 minutes
    operations
  • L-88 hours complete Top-off SFHe activities
  • L-80 hours payload disconnect, PLB door close
  • At L-30 minutes
  • Close SFHe Tank Vent Valve and deactivate Vent
    Pump
  • Deactivate Cryo-coolers
  • Power down all equipment with the exception of
    J-Crate and necessary CAB functions to monitor of
    cryogenics system health (limited to 120W)
  • Monitor health status of cryogenic systems until
    L-9 min GO / NO GO Call from AMS-02 based on
    Cryogenic System Health
  • At L-9 minutes Complete Payload Power-Down

18
Alpha Magnetic Spectrometer 02Mission
Operations Pre-Launch Activity
19
Alpha Magnetic Spectrometer 02Mission
Operations Pre-Launch
  • Safety Launch Commit Criteria
  • Loss of vacuum case seal immediately prior to
    launch results in over-pressurization of the SFHe
    Tank during ascent, over-pressurizing the PLB and
    possibly damaging the Aft Bulkhead
  • Worst case leak in VC requires 23 minutes to
    generate sufficient He to burst disks, releasing
    gas into PLB
  • PLB over-pressurization must occur between L30
    seconds and L1 minute to result safety hazard
  • Monitor VC health / status until L-9 minutes
  • Compared to trend data established over the
    lifetime of the experiment to indicate
    occurrence, and make the GO / NO GO Call
  • Minimum of three measurements of temperature and
    pressure within the SFHe Tank will provide this
    data on redundant paths
  • For operational scenarios that involve the burst
    disks rupturing at any other time, no hazard has
    been identified

20
Alpha Magnetic Spectrometer 02Mission
Operations Pre-Launch
  • Payload Launch Commit Criteria
  • The only payload LCC that has been defined
    relates to the operability of ISS Bus A prior to
    payload bay closure. Because this Bus is
    required for magnet charging, verification that
    this Bus is operational must be made, or possibly
    corrected, prior to launch.

21
LAUNCH
Alpha Magnetic Spectrometer 02Mission
Operations
22
Alpha Magnetic Spectrometer 02Mission
Operations
ASCENT OPERATIONS
23
Alpha Magnetic Spectrometer 02Mission
Operations Ascent
  • SFHe Tank Nominal Vent Valve Operation
  • He Vapor pressure in SFHe tank must be maintained
    at a pressure to keep LHe temperature superfluid
  • Endurance Mission Success
  • Vent valve to open when PLB pressure is less than
    the SFHe vapor pressure (lt 20 millibars)
  • Must occur during Powered Flight
  • Porous plug, which allows He vapor vent while
    containing the liquid within the tank
  • When the valve is opened, liquid must not be in
    contact with the porous plug, which could act as
    a pump to drain the SFHe liquid from the tank
  • Not a safety issue, due the rate of pumping that
    would occur
  • Endurance Mission Success
  • Porous plug is designed to be parallel to the
    acceleration vector during ascent. G-forces
    during powered flight will ensure only vapors are
    in contact with the plug at vent opening.

24
Alpha Magnetic Spectrometer 02Mission
Operations Ascent
  • SFHe Tank Nominal Vent Valve Operation
    (continued)
  • Avionics Baroswitch Electronics (BSE) will open
    the vent valve
  • Barometric switch to trigger the BSE when PLB
    pressure is less than the SFHe (15 20
    millibars)
  • Time-tagged Discrete Output Low (DOL) command via
    Backup Flight System (BFS) General Purpose
    Computer (GPC) to trigger BSE as a backup _at_ LTBD
    minutes
  • In the event of an STS abort, the barometric
    switch will trigger BSE to close the vent valve
    during descent (non-hazard)
  • Any potential ignition sources will be compliant
    with NSTS/ISS 18978B, NS2/81-M082

25
(No Transcript)
26
Alpha Magnetic Spectrometer 02Mission
Operations
STS ON-ORBIT OPERATIONS
27
Alpha Magnetic Spectrometer 02Mission
Operations STS On-Orbit
  • Outline
  • STS On-Orbit Interfaces
  • Re-configure / Set-up AFD Equipment
  • PDIP1 and PDIP2
  • Digital Data Recording System-02 (DDRS-02)
  • Payload Check-out
  • Payload Deploy

28
Alpha Magnetic Spectrometer 02Mission
Operations STS On-Orbit
  • Configure AFD Equipment
  • Configure PDIP1 and PDIP2
  • Unstow and activate Digital Data Recorder
    System-02 (DDRS-02)
  • Operated on Next Generation Laptop System (NGLS)
    computer
  • Serves as a back-up recording device for payload
    data that is down-linked via the Ku-Band
  • Single hard disk in the NGLS computer will
    provide recording capability for 40 hours worth
    of check-out data
  • Back-up hard-disks flown (contingency)
  • Activate Assembly Power Converter Units (APCUs)
  • Powers AMS-02 Payload

29
Alpha Magnetic Spectrometer 02Mission
Operations STS On-Orbit
  • Configure PDIP1

30
Alpha Magnetic Spectrometer 02Mission
Operations STS On-Orbit
  • Configure PDIP2

31
Alpha Magnetic Spectrometer 02Mission
Operations STS On-Orbit
  • Digital Data Recorder System-02 (DDRS-02)

32
Alpha Magnetic Spectrometer 02Mission
Operations STS On-Orbit
  • Payload Power-up and Check-out
  • Cryo-coolers and housekeeping data at MET 2 hr
    30 minutes
  • Activate/checkout AMS-02 avionics subsystems and
    thermally condition payload
  • Peak power draw on shuttle 2 kW based upon
    thermal loads in PLB
  • No magnet charging possible on STS APCU power
    supplied to prime PDS side B has no
    connectivity to the CAB.
  • Dock with ISS (MET Day 3)
  • Make GO / NO GO Call prior to transfer on MET Day
    4
  • Power down AMS-02 prior to transfer operations

33
Alpha Magnetic Spectrometer 02Mission
Operations ISS
  • Simplified Payload Power-Up Sequence

34
Alpha Magnetic Spectrometer 02Mission
Operations STS On-Orbit
  • Payload Deploy
  • Grapple Flight Releasable Grapple Fixture (FRGF)
    with Shuttle Remote Manipulator System (SRMS)
  • Disconnect Remotely Operated Electrical Umbilical
    (ROEU) and operate Payload Retention Latch
    Actuators (PRLAs)
  • AMS-02 removed from PLB by SRMS

35
SRMS TO SSRMS HAND-OFF OPERATIONS
Alpha Magnetic Spectrometer 02Mission
Operations
36
Alpha Magnetic Spectrometer 02Mission
Operations Hand-Off
  • Payload Hand-Off
  • Grapple Power and Video Grapple Fixture (PVGF)
    with Space Station RMS (SSRMS) located on MT
  • External Berthing Cues System (EBCS) utilized to
    verify final approach to Attach Site (Power and
    Video functions routed through SSRMS)
  • SSRMS supplies power for AMS-02 Heaters during
    Transfer Ops
  • Magnet charging on SSRMS Operationally Controlled
  • SSRMS Nominal power bus is connected to PDS side
    B, which has no connectivity to the CAB
  • Magnet charge initiation requires a series of
    up-linked commands, none of which are stored
    on-board the computer
  • The payload has no communications via the PVGF to
    receive these commands

37
Alpha Magnetic Spectrometer 02Mission
Operations Hand-Off
  • Payload Hand-Off (continued)
  • SRMS release of AMS
  • Transfer to S3 attach site
  • Attach AMS-02 to S3 upper inboard site
    mechanical/ electrical (via PAS)
  • Deactivate power via PVGF
  • Connect UMA
  • Activate payload power via UMA
  • Power up Avionics, perform abbreviated avionics
    checkout to verify payload power and
    communications
  • SSRMS Ungrapple

38
Alpha Magnetic Spectrometer 02Mission
Operations Hand-Off
  • Transfer to ISS

1
2
3
4
39
Alpha Magnetic Spectrometer 02Mission
Operations Hand-Off
  • Berthing to ISS S3 Upper / Inboard

40
Alpha Magnetic Spectrometer 02Mission
Operations
ISS ON-ORBIT OPERATIONS
41
Alpha Magnetic Spectrometer 02Mission
Operations ISS
  • On-Orbit ISS Operations
  • Power-up and complete systems check-out
  • Thermal monitor and condition cryosystems
  • Power-down all subsystems except those integral
    to magnet charging
  • Begin magnet charging operations
  • Post-magnet charge systems power-up and check-out

42
Alpha Magnetic Spectrometer 02Mission
Operations ISS
  • On-Orbit ISS Operations (continued)
  • Experiment Science
  • 3 years operation with magnet
  • After LHe depletion and magnet is no longer
    functional, the payload will continue with
    further physics goals
  • Nominal End of Mission
  • No STS flights for return of AMS-02 Payload.
  • Will remain on ISS for duration of ISS mission
    life, and re-enter with ISS vehicle

43
Alpha Magnetic Spectrometer 02Mission
Operations ISS
  • On-Orbit ISS Operations (continued)
  • Primary control of AMS-02 is from ground
  • Only safety related operation is Cryomagnet
    charge
  • Only safety hazard when EVA/EVR operations on
    AMS-02
  • Requires a series of up-linked commands (not
    stored on-board)
  • Data down-linked via ISS Ku-Band
  • Proposed to use S-Band to downlink minimal health
    data
  • In case of loss of power and/or communications,
    payload is safe without services

44
Alpha Magnetic Spectrometer 02Mission
Operations ISS
  • Simplified Payload Power-Up Sequence

45
EVA Compatibility
Alpha Magnetic Spectrometer 02Mission
Operations
46
Alpha Magnetic Spectrometer 02Mission
Operations EVA
  • Translation Paths
  • Translation paths were evaluated by Worksite
    Analysis and in NBL
  • EVA translation in proximity to and in contact
    with AMS-02 payload approved for both STS and ISS
    EVA
  • For ISS EVA when magnet charge is possible, suit
    certification for operations in magnetic field
  • EMU 300 Gauss
  • Orlon 175 Gauss
  • Hazard avoided by magnet discharge prior to EVA
    or limiting EVA exposure via Keep Out Zones
  • Translation allowed between attach sites on truss
    and up USS to access PVGF
  • Translation path for foldable ROEU to be
    validated in NBL

47
Alpha Magnetic Spectrometer 02Mission
Operations EVA
  • PVGF Translation Path

48
Alpha Magnetic Spectrometer 02Mission
Operations EVA
  • S3 Truss Translation Paths

49
Alpha Magnetic Spectrometer 02Mission
Operations EVA
  • Translation Path

50
Alpha Magnetic Spectrometer 02Mission
Operations EVA
  • EVA Keep Out-Zones
  • The AMS-02 Vacuum Case ribs are not designed to
    withstand EVA Kick-loads
  • Worked with the EVA Projects Office
  • Reviewed during NBL operation
  • Not deemed a concern
  • VC is classified as an EVA Keep Out Zone
  • Additionally, the Star Tracker Baffles are also
    considered EVA Keep Out Zones (sharp edges)
  • Detailed thermal analysis shall be performed to
    determine if any additional areas of concern are
    identified due to EVA touch temp violations

51
CONTINGENCY OPERATIONS
Alpha Magnetic Spectrometer 02Mission
Operations
52
Alpha Magnetic Spectrometer 02Outline
  • EVA Operation
  • STS
  • ROEU Release
  • PRLA Release
  • FRGF Release
  • ISS
  • EVA Interface Panel Operations
  • PAS Release
  • PVGF Release
  • ROEU Folding Bracket
  • NBL Testing
  • Completed Testing
  • Forward Work
  • EVR Operation
  • Mission Abort

53
Alpha Magnetic Spectrometer 02Contingency
Operations STS EVA
  • AMS-02 designed to be compatible with
  • Manual ROEU disconnect
  • Access issue only
  • Can be performed from Orbiter Sill
  • Manual Payload Retention Latch Actuators (PRLA)
    operation
  • Access issue only
  • Can be performed from Orbiter Sill
  • Flight Releasable Grapple Fixture (FRGF) Release
  • Access issue only
  • Can be performed from Orbiter Sill or post-deploy

54
Alpha Magnetic Spectrometer 02Contingency
Operations STS EVA
  • AMS-02 in PLB (ROEU and PRLA Access)

55
Alpha Magnetic Spectrometer 02Contingency
Operations STS EVA
  • FRGF Release

56
Alpha Magnetic Spectrometer 02Contingency
Operations ISS EVA
  • EVA Interface Panel
  • Passive UMA Removal contingency operation as
    required by SSP-57003
  • Capture Bar Unloading and Release contingency
    operation as required by SSP-57003
  • PVGF Contingency Release
  • PVGF Grapple Release
  • Latching End Effector (LEE) Release
  • Foldable ROEU

57
Alpha Magnetic Spectrometer 02Contingency
Operations ISS EVA
  • EVA Interface Panel
  • EVA Interface Panel allows for redundant avionics
    interfaces in contingency scenario
  • Connectors will meet the mating/demating
    requirements identified in letter MA2-99-170, and
    comply with (SSQ 21654)
  • Connections are swapped to effect changing A
    (prime) / B (redundant) channels in the event
    that prime capability is lost
  • Data Payload Redundancy Only
  • Power Payload and ISS Redundancy
  • Cryomagnet charge can be performed on UMA powered
    PDS A-side (prime) bus only.

58
Alpha Magnetic Spectrometer 02Contingency
Operations ISS EVA
  • EVA Interface Panel and UMA Operations

59
Alpha Magnetic Spectrometer 02Contingency
Operations ISS EVA
  • Capture Bar Unload/Release
  • WIF/PFR location identified on Truss for this
    operation (as necessary)
  • Handrails on Keel accessible during operation,
    Keel available for additional handhold location
  • Capture Bar Load Release Screws are captive and
    can be loosened with PGT/extension
  • Once unloaded capture bar handle must be lifted
    and pulled to release
  • Procedure/access verified by NBL Test

60
Alpha Magnetic Spectrometer 02Capture Bar
With Removal Handle
PAS Platform Passive Half
61
Alpha Magnetic Spectrometer 02Contingency
Operations ISS EVA
  • Capture Bar Unload

Approximately 80 turns Alternating for
balanced load release
62
Alpha Magnetic Spectrometer 02Contingency
Operations ISS EVA
  • Capture Bar Release

63
Alpha Magnetic Spectrometer 02Contingency
Operations ISS EVA
  • Capture Bar Handle Release Handrail Locations

64
Alpha Magnetic Spectrometer 02Contingency
Operations ISS EVA
  • PVGF Release
  • PVGF can be released by releasing Grapple Pin or
    by releasing LEE (ISS EVA standard procedure)
  • Handrail placement on USS provides translation
    path
  • WIF location on USS Sill Beam for PFR Access w/
    nearby handrails for installation of PFR
  • Both Grapple Pin release and LEE release
    accessible from same location, operation
    performed with PGT/extension
  • Access verified by NBL Test

65
Alpha Magnetic Spectrometer 02Contingency
Operations ISS EVA
  • PVGF Release

66
Alpha Magnetic Spectrometer 02Contingency
Operations ISS EVA
  • PVGF Handrails/WIF

67
Alpha Magnetic Spectrometer 02Contingency
Operations ISS EVA
  • PVGF Related Handrails

68
Alpha Magnetic Spectrometer 02Contingency
Operations ISS EVA
  • Foldable ROEU PDA
  • Designed to be compatible with folding in STS or
    on ISS
  • Designed as contingency to limit protrusion
    outside of standard Attach Payload Envelope,
    bracket holding Passive Disconnect Assembly (PDA)
    for Remotely Operated Electrical Umbilical can be
    folded down.
  • Working with EVA Project Office to define
    additional requirements (if applicable) for
  • Handrails
  • WIF
  • Actuation force measurement test
  • Additional hardware to be developed to
    demonstrate access on existing NBL mockup
  • EVA approved MSWG approved Push-In-Place (PIP)
    Pins used for locking feature in both positions

69
Alpha Magnetic Spectrometer 02Contingency
Operations ISS EVA
  • Foldable ROEU (extended)

70
Alpha Magnetic Spectrometer 02Contingency
Operations ISS EVA
  • Foldable ROEU (extended)

71
Alpha Magnetic Spectrometer 02Contingency
Operations ISS EVA
  • Foldable ROEU (folded)

72
Alpha Magnetic Spectrometer 02Contingency
Operations ISS EVA
  • Foldable ROEU (folded)

73
NBL Testing
Alpha Magnetic Spectrometer 02Mission
Operations - EVA
74
Alpha Magnetic Spectrometer 02Mission
Operations - EVA
  • NBL Testing
  • First access test in NBL completed in March 2002
    with low fidelity mockup (only Passive PAS)
  • Second NBL access test (with higher fidelity
    mockup, full experiment envelope) performed in
    November 2002
  • No mission specific NBL testing required
  • No specific EVA training requirements

75
Alpha Magnetic Spectrometer 02Mission
Operations - EVA
  • NBL Testing (continued)
  • Testing to evaluate AMS-02 Contingency EVA
    interfaces was performed November 12th thru 15th,
    2002 (five astronauts performed tasks)
  • Testing included
  • PVGF Contingency Release
  • PVGF Grapple Release
  • LEE Release
  • Capture Bar Unloading and Release
  • Connector Panel Access/Evaluation
  • Passive Umbilical Mating Assembly (UMA) bolt
    access
  • And, crew translation path evaluation

76
(No Transcript)
77
(No Transcript)
78
(No Transcript)
79
(No Transcript)
80
(No Transcript)
81
(No Transcript)
82
Alpha Magnetic Spectrometer 02Mission
Operations - EVA
  • NBL Test Results
  • All tested tasks were deemed acceptable as
    documented in Crew Consensus Report (reference
    letter CB-02-129)
  • Only minor issues identified with
  • Labeling (updates completed and approved)
  • Fit-checks (verified with flight hardware at
    Lockheed Martin)
  • Connector clocking (updated and approved)
  • Potential future work for Foldable ROEU

83
Alpha Magnetic Spectrometer 02Phase II Flight
Safety Review
  • Contingency EVR Operations
  • Single operation considered for EVR relocation of
    AMS-02
  • SSRMS operation in magnetic field is not
    certified
  • Hazard avoided by magnet discharge prior to EVR

84
Alpha Magnetic Spectrometer 02Mission
Operations - Contingency
  • Mission Abort
  • In the event of an abort (e.g. RTLS, TAL, or any
    other return with AMS-02 still in STS 4 PRLAs
    engaged)
  • Close vent valve when PLB pressure exceeds 15
    20 millibars
  • SSP supplied 28 VDC only
  • APCU supplied 120 VDC to payload PDS powered off
  • Upon landing, services should be applied via the
    T0 Umbilical, to perform the following
  • Allow internal Electronics to Monitor He tank
    pressure
  • Operate vent valve and vent pump
  • Not a safety concern, but rather a refurbishment
    concern (dont want to rupture burst disks)
  • Initial projection from KSC for nominal landing
    indicates 10 hrs.
  • Endurance Mission Success for turn-around

85
Backup Slides
Alpha Magnetic Spectrometer 02Mission
Operations
86
Alpha Magnetic Spectrometer 02Phase II Flight
Safety Review
87
Alpha Magnetic Spectrometer 02Payload Avionics
Universal Interface Diagram
88
Alpha Magnetic Spectrometer 02Payload
Interface Diagram STS Pre-Launch
89
Alpha Magnetic Spectrometer 02Payload
Interface Diagram STS Ascent
90
Alpha Magnetic Spectrometer 02Payload
Interface Diagram STS On-Orbit
91
Alpha Magnetic Spectrometer 02Payload
Interface Diagram Hand-Off
92
Alpha Magnetic Spectrometer 02Avionics Systems
Interface Diagram ISS
93
Alpha Magnetic Spectrometer 02Mission
Operations Scrub Launch Activity
  • Scrub Turnaround Scenario

94
Alpha Magnetic Spectrometer 02Mission
Operations Scrub Launch Activity
  • Scrub Recycle Turnaround Scenario
Write a Comment
User Comments (0)
About PowerShow.com