NASA Operations - PowerPoint PPT Presentation

1 / 17
About This Presentation
Title:

NASA Operations

Description:

Protecting the Public, Astronauts and Pilots, the NASA Workforce, and ... Lack of Fire Alarm Pull Stations at all Exits in violation of NFPA and NASA requirements ... – PowerPoint PPT presentation

Number of Views:75
Avg rating:3.0/5.0
Slides: 18
Provided by: waynerf7
Learn more at: https://sma.nasa.gov
Category:

less

Transcript and Presenter's Notes

Title: NASA Operations


1
NASA Operations Engineering Board (OEB)
FY01 Safety Health (SH) Assessment
Jon Mullin/HQ/QS Art Lee/HQ/QS
Dr. Bill Barry/KSC/QA March 7,
2002
(1)
2
Operations Engineering Board (OEB)
FY01 Assessments
  • OEB Activities for FY01
  • OEB Reviews Performed
  • Ames Research Center (March 6-8, 2001)
  • Unitary Plan Wind Tunnel (UPWT)
  • Langley Research Center (August 28-31, 2001)
  • National Transonic Facility (NTF)
  • OEB Participants
  • NASA Headquarters
  • Safety Mission Assurance Office
  • Chief Health Medical Office
  • Facilities Engineering Division
  • Environmental Management Division
  • Institutional Program Offices
  • NASA Centers

3
Operations Engineering Board (OEB)
FY01 SH Assessments
  • Ames Research Center Review, March 6-8, 2001
  • Reviewed Unitary Plan Wind Tunnel (UPWT)
  • Areas of Concern Include Safety Fire
    Protection Lifting Devices and Equipment
    Emergency Preparedness Security Occupational
    Health Operations Maintenance
  • Safety
  • Conduct a complete Safety Walk-down of UPWT by
    experienced Safety, Fire, and Health Team
  • Include all Collateral Equipment (Drives,
    Auxiliaries, etc.) in required Facility Condition
    Assessment IAW NPD 8831.1B
  • Evaluate potential risks from a seismic event
    since unmodified portion of UPWT not meeting
    current seismic standard
  • Evaluate risks from potential Failure of
    Compressed Gas Containers in event of an
    Earthquake

4
Operations Engineering Board (OEB)
FY01 SH Assessments
  • Ames Research Center Review, March 6-8, 2001
  • Reviewed Unitary Plan Wind Tunnel (UPWT)
    (Contd.)
  • Safety (Contd.)
  • Recommend ARC Code Q update Hazard Risk
    Identification Control Documentation to include
    System Safety Hazard Reports
  • What are the Root Causes from the extensive
    number of Contractor Failures during UPWT Project
    Upgrade
  • Evaluate Customer Requirements to insure against
    Facility Failure
  • Explain the Process assuring Document changes are
    flowed down to all related Documents
  • Lack of Knowledge Concerning Agencys
    Lessons-Learned Information System (LLIS)
  • Implement the GIDEP process and provide user
    training

5
Operations Engineering Board (OEB)
FY01 SH Assessments
  • Ames Research Center Review, March 6-8, 2001
  • Reviewed Unitary Plan Wind Tunnel (UPWT)
    (Contd.)
  • Safety (Contd.)
  • Review Uninterruptible Power Supply (UPS)
    Configuration and consider tying in model homing
    system in case of Power loss
  • Confirm how Probabilistic Risk Assessments (PRAs)
    have been satisfied for UPWT
  • Confirm Risk Based Acquisition Management (RBAM)
    was conducted for UPWT contracts
  • Performance Evaluation Profile (PEP) results
    should be utilized to improve UPWT Safety
    Health Program
  • Review Reliance on Unassisted Voice
    Communications in Test Environment and evaluate
    Recording of Voice Loops in UPWT Control Rooms,
    if Communication Systems installed

6
Operations Engineering Board (OEB)
FY01 SH Assessments
  • Ames Research Center Review, March 6-8, 2001
  • Reviewed Unitary Plan Wind Tunnel (UPWT)
    (Contd.)
  • Fire Protection
  • Improper Storage of Chemicals and Flammable
    Materials in violation of NFPA and NASA
    requirements
  • Lack of Fire Alarm Pull Stations at all Exits in
    violation of NFPA and NASA requirements
  • Placement of Fire Extinguishers is extremely
    dense potentially causing unnecessary costs (ref.
    NFPA 10)
  • Define and document Approval Process for
    transporting Hazardous Materials to UPWT in the
    Test Planning Guide WT Operations Division
    H.S.T.P.
  • Add Fire Safety Information to the Test Planning
    Guide WT Operations Division H.S.T.P.

7
Operations Engineering Board (OEB)
FY01 SH Assessments
  • Ames Research Center Review, March 6-8, 2001
  • Reviewed Unitary Plan Wind Tunnel (UPWT)
    (Contd.)
  • Lifting Devices and Equipment (LDE)
  • Verify that Lifting Devices and Slings are
    properly tested IAW NSS/GO 1740.9B for LDE
  • Confirm that required Hazard Analyses and Failure
    Modes Effects Analyses (FMEAs) were done prior
    to conducting Critical Lifts
  • Emergency Preparedness Security
  • Evacuation Routes from the UPWT Control Rooms and
    Other Intensive Work Areas need to be clearly
    marked
  • All UPWT Workers need to be frequently trained
    and updated on the proper Emergency Egress with
    documentation of Training as required by OSHA
  • Conduct Human Factors Study to Evaluate
    Standardized Emergency Shutdown Procedures for
    all WTs

8
Operations Engineering Board (OEB)
FY01 SH Assessments
  • Ames Research Center Review, March 6-8, 2001
  • Reviewed Unitary Plan Wind Tunnel (UPWT)
    (Contd.)
  • Emergency Preparedness Security (Contd.)
  • Add Emergency Information to the Test Planning
    Guide WT Operations Division H.S.T.P.
  • Provide ARC Policy on Background Investigations
    for New Employees, especially unescorted access
    to Critical Facilities
  • Occupational Health
  • WT Guide for ARC requires an Eye Exam every 4
    years, but Center Medical Office unaware of the
    requirement - need resolution
  • Concern with the Noise-levels in the UPWT
    Control Rooms

9
Operations Engineering Board (OEB)
FY01 SH Assessments
  • Ames Research Center Review, March 6-8, 2001
  • Reviewed Unitary Plan Wind Tunnel (UPWT)
  • Observations
  • ARC should consider using SOLAR Web-based
    Training for improving Training opportunities
    Center-wide
  • Lessons-Learned for ARC Wind Tunnels should be
    better shared between Code R (Office of Aerospace
    Technology) Centers
  • Revisiting Hazard Risk Analysis on a Regular and
    Periodic Basis by UPWT is fundamental to a Good
    Risk Management Program

10
Operations Engineering Board (OEB)
FY01 SH
Assessments
  • Langley Research Center Review, August 28-31,
    2001
  • Reviewed National Transonic Facility (NTF)
  • Areas of Concern Include Safety Emergency
    Preparedness Fire Protection Lifting Devices
    and Equipment and Operations Maintenance
  • Safety
  • Assure Operational Staffing Levels are maintained
    and Corporate Knowledge is being transferred and
    captured
  • Explain how the Center Director is made aware of
    the Risk Acceptance decisions made for the
    Center
  • Establish and communicate a strong and formal
    Timeout Policy Center-wide
  • NTF Management should become more familiar with
    Johnson Controls (JCI) Safety Health Plan

11
Operations Engineering Board (OEB)
FY01 SH Assessments
  • Langley Research Center Review, August 28-31,
    2001
  • Reviewed National Transonic Facility (NTF)
    (Contd.)
  • Safety (Contd.)
  • Determine what Collateral Damage may occur should
    the NTF as a Pressure Vessel and System (PV/S)
    rupture during a Test and who updates the Hazard
    Analysis as part of the Facility System Safety
    Program
  • A complete Inventory of Flexible Hoses for PV/S
    is required IAW NPD 8710.5
  • Evaluate a Facility Closed Circuit TV System to
    improve Safety and Security
  • Improve Confined Space Entry Management at the
    NTF
  • Management should advocate Funding to Upgrade
    Software/Hardware for Reliable WT Control Data
    Acquisition System

12
Operations Engineering Board (OEB)
FY01 SH Assessments
  • Langley Research Center Review, August 28-31,
    2001
  • Reviewed National Transonic Facility (NTF)
    (Contd.)
  • Safety (Contd.)
  • Evaluate use of UPS in the NTF Control Room to
    protect Oxygen Monitoring Systems, Computers,
    Data Acquisition Systems
  • Explain why the Oxygen Monitoring System is on a
    12- month Calibration Cycle
  • Recognize LaRCs VPP Star Status however,
    Lock-Out/ Tag-Out (LO/TO) Program is less
    stringent than at many other Centers and should
    be re-evaluated independently
  • Utilize the Agencys Lessons-Learned Information
    System (LLIS) Database
  • Reconsider Philosophy on displaying NSRS Agency
    Safety Initiative (ASI) Information (Displays
    currently limited), especially in High Traffic
    Areas Center-wide

13
Operations Engineering Board (OEB)
FY01 SH Assessments
  • Langley Research Center Review, August 28-31,
    2001
  • Reviewed National Transonic Facility (NTF)
    (Contd.)
  • Safety (Contd.)
  • Project INFUSE should utilize the Agencys
    Risk Assessment Training (sponsored by HQ/Code
    QE)
  • Confirm Data Retention (5 Years) complies with
    NPG 1441
  • Review all Procedures or Actions to achieve
    orderly or Emergency Shut-down and generate or
    revise Procedures, where appropriate
  • As changes are made in Safety Emergency
    Procedures, assure Personnel are properly trained
    and training is documented

14
Operations Engineering Board (OEB)
FY01 SH Assessments
  • Langley Research Center Review, August 28-31,
    2001
  • Reviewed National Transonic Facility (NTF)
    (Contd.)
  • Fire Protection
  • Many Emergency Lights were either partially or
    totally burned out along with a need to improve
    Egress Identification
  • Evaluate Fire Extinguisher placement and Training
    in the NTF
  • Review Under-floor Wet Fire Sprinkler System to
    determine if Gaseous Suppression may be better
  • Lifting Devices and Equipment (LDE)
  • Verify that LDE Program is consistent with NSS/GO
    1740.9B
  • Ensure Compliance of Certifying and Tagging of
    Slings IAW NSS/GO 1740.9B
  • Develop Center-wide Policy defining Critical
    Lifts

15
Operations Engineering Board (OEB)
FY01 SH Assessments
  • Langley Research Center Review, August 28-31,
    2001
  • Reviewed National Transonic Facility (NTF)
    (Contd.)
  • Operations Maintenance
  • How is NTF Maintenance Data, including Roles
    Responsibilities and reporting of Facility
    Health, communicated to Center Management
  • Explain Value to be derived from Third Party
    (Plexus Scientific) review of Maintenance Program
  • NTF Facility Safety Head should be included and
    utilized as Critical input to Project INFUSE
    Reliability Centered Maintenance (RCM) Plan
  • Use Incident Reporting Information System (IRIS)
    as a source of information for developing Project
    INFUSE RCM Plan
  • Include Construction of Facilities (CoF) in
    Backlog of Maintenance Repairs (BMAR) reduction
    planning

16
Operations Engineering Board (OEB)
FY01 SH Assessments
  • Langley Research Center Review, August 28-31,
    2001
  • Reviewed National Transonic Facility (NTF)
  • Observations
  • Suggest using Third Party to conduct Facility
    Condition Assessment rather than the current
    Maintenance Contractor
  • LaRC needs to continue their Program of replacing
    the recalled Omega Fire Sprinklers Heads and
    identifying recently recalled Central Sprinkler
    Heads
  • Recommend installing Sound Discs for effective
    repeatable Vibration Analysis Data collection
  • Suggest linking Customer satisfaction feedback
    data to a set goal to trigger corrective/preventiv
    e action part of ISO Program

17
Operations Engineering Board (OEB)
Statistics
Write a Comment
User Comments (0)
About PowerShow.com