Title: Q3 INFRASTRUCTURE AND CONDITIONAL GRANTS PRESENTATION
1- Q3 INFRASTRUCTURE AND CONDITIONAL GRANTS
PRESENTATION
National Council of
Provinces
4th February 2008
2PURPOSE
- To provide the National Council of Provinces
(NCOP) with an overview of Conditional Grant
and Capital Expenditure performance for Gauteng
Province during the Third Quarter of 2007/08 - Snapshot of detailed Q3 financial and
non-financial performance report
3 CONSOLIDATED VIEW OF GPG INFRASTRUCTURE PAYMENTS
4CONSOLIDATED REVIEW OF GPG INFRASTRUCTURE
- The adjusted 2007/08 infrastructure appropriation
for the Province is an amount of approximately R
5.7 billion which equates to approximately 13.8
of the total Provincial budget (R 41,4 billion).
This amount excludes an appropriation for
Gautrain of which R2,8 billion has been spent - The infrastructure allocation is made up of
capital and maintenance. Of the total R5.7
billion infrastructure appropriation, R4.98
billion, (87) is allocated for capital projects
and R752 million, (13) is allocated towards
maintenance projects - As at the end of Quarter 3, R4,1 billion was
expended on infrastructure projects in the
Province by provincial departments. Of which
R3,61 billion was spent on capital projects and
R442 million was spent on maintenance projects.
5GPG INFRASTRUCTURE BUDGETS 2007/08
6INFRASTRUCTURE EXPENDITURE ANALYSIS CAPITAL
PROJECTS
7INFRASTRUCTURE EXPENDITURE ANALYSIS CAPITAL
PROJECTS
- As at the end of Q3, R3.61 billion (73) has been
expended by GPG Departments on Capital projects
in line with the projections - Of the R 752 million allocated to Maintenance
projects by the end of Q3, an amount of R
422,05million (58.8) was actually expended. The
largest contributors to this under expenditure
are Social Development and Public Works - The Province projects to spend R1,453 billion in
the remaining segment of the 2007/08 financial
year, which if achieved will result in an
under-expenditure of R223 million (3.9) of the
infrastructure budget
8CAPITAL PROJECTS
- The highest expenditure in capital projects is
reported by Housing at R1,79 billion, and Health
at R 716 million. Low rates of spending are
reported by Agriculture, (R1,2 billion) and
Social Development, (R 14,1 million) - The under expenditure by Agriculture(20,5) can
be attributed to poor project planning. The
budget has been reduced to R6,6 million during
the adjustment process - The depart of Social Development may under spend
by R17,4 million. Low spending is also due to
poor project planning which has resulted to
surrender of funds - Significant over-expenditure on capital projects
is anticipated from the departs of Education and
Health. This is due to the fact the department of
Education has submitted incorrect projections.
The over-expenditure for the DoH is owing to
increased costs of the Departments
Revitalisation strategy being rolled out this
year
9INFRASTRUCTURE EXPENDITURE ANALYSIS MAINTENANCE
PROJECTS
10MAINTENANCE PROJECTS
- Of the R441,24 million (58,7) projected to be
spent for Q3, actual spending on maintenance
projects undertaken in the Province is reported
at R442,05 million (58,8) - The highest expenditure is reported by the
Department of Health -
- The Departments of Agriculture(12,3), Public
Works(16,7) and Social Development(19,8)
reported the low maintenance expenditure as at
the end of Q3 - The projected spend for the rest of the year is
25.23 of the overall maintenance budget, which
would result in an 16 under expenditure for the
2007/08 year on maintenance projects - The Department of Health projects an
over-expenditure of R512 million due to
shortfalls in maintenance allocation, however the
department has been advised to scale down in
order to stay within budget
11SECTORAL INFRASTRUCTURE ANALYSIS
- Department of Health
- A province wide programme of modernising,
rationalising, and transforming health
infrastructure and technology in line with
national policy objectives is being rolled out by
the depart of Health - At least 15 capital projects new, and existing,
have been completed up to the end of Q3, and 23
new projects that have commenced as part of the
Revitalization strategy of the Department - Numerous upgrading and rehabilitation projects
are ongoing throughout the Province. However only
statutory, day-to day maintenance is being
undertaken as the need arises. This is due to
only 23.3 of the DOH infrastructure budget being
allocated to maintenance - Large CAPEX projects completed are
- Ann Latsky Nursing College New Admin and
Student Facility - Bristlecone Clinic New Facility
- John Doe Clinic New Facility
- The rollout of new projects in terms of the
Revitalization strategy, could result in the
Department reporting a year end over expenditure
of at least R29,2 million
12 SECTORAL INFRASTRUCTURE ANALYSIS
- Department of Education
- In terms of the objectives of the Department of
Education, the infrastructure delivery programme
seeks to address the current backlogs and lack of
basic learner facilities in the various
under-serviced areas of the Province - The amount of R628 million has predominantly been
expended on rehabilitation and maintenance works
for 152 schools, the construction of 162 new
projects, including fencing projects for
improving school security and to ensure
maintenance works where necessary in existing
educational facilities and institutions - Department of Public Transport, Roads and Works
- The major portion of the amount expended by the
Department has been expended on projects that
are geared towards the - Tarring of existing gravel roads
- Upgrading and maintenance of earmarked roads for
improvement - Provision of lighting on certain routes
- Operational and expansion works on the major
routes, M1, R24, R21, N12,N1 to ensure traffic
efficiencies for the 2010 event - Project Managers have been appointed to fast
track development and construction on 20
Townships Roads projects - Overall challenges have been experienced in the
overall maintenance programme, resulting in the
backlogs for routes in need of urgent maintenance
- Delayed procurement processes has slowed the
construction of roads in the 20 townships and
contracts were awarded late.
13SECTORAL INFRASTRUCTURE ANALYSIS
- Department of Social Development
- Department is in the process of completing
construction of a secure rehabilitation facility
for delinquent youth at the Jabulani Place of
Safety, scheduled for completion in 2008/09 - ECD Infrastructure Delays experienced during
the planning stages with the new implementing
agents (municipalities) - Department of Agriculture, Conservation and
Environment - Department has been undertaking ongoing upgrading
and maintenance works at existing facilities at
provincial nature reserves - Department of Sport, Arts, Culture and Recreation
- Phase 1 in four stadia has been completed
- Department is currently involved in the second
phase of construction at two provincial stadia,
HM Pitje and Sinaba - Completion is scheduled for the 2008/09 financial
year
14KEY OBSERVATIONS
- It is evident that that weaknesses in
infrastructure delivery result from misalignment
between budget, planning and cash flow
requirements for projects. Departments are
struggling to undertake forward planning - Departments delay to finalise lists of projects,
some lists are changed during the year as new
priorities are identified. Late awarding of
contracts to contractors is among other reasons
for projected high expenditure in Q4 - GT is currently rolling out the Infrastructure
Delivery Improvement Programme (IDIP) to departs
of SACR and Social Development. IDIP seeks to
align the project delivery cycle with the budget
cycle - GT noted with concern that whilst some projects
are moving at an acceptable pace, other large
scale capex projects, are moving at a sluggish
pace and are being plagued by operational,
procurement and reporting difficulties - GPG notes that well-maintained infrastructure
underpins quality of life and economic
development. If maintenance is inadequate, social
and economic growth in Gauteng will be impeded
15KEY OBSERVATIONS
- It is clear that there are numerous factors that
impact on the expenditure levels of departments
during the final stages of the financial year. A
pure data analysis on its own cannot identify
specific factors influencing spending behaviour
and a more detailed analysis of such factors are
reviewed monthly at PW-GT-Client meetings - It is instructive to note that an increase in
spending during the final stages of the financial
year can be expected because payment patterns for
capital projects are generally high based on
completion of project milestones. Departments
would use the first few months of the financial
year to initiate the project - GPG departments continue to build and be
supported in their efforts by Treasury to build
infrastructure capacity to ensure improved
monitoring and reporting as they are faced with
capacity constraints - Treasury continue its pursuit of ensuring that
Departments meet their infrastructure goals and
objectives, and assist strengthen thin structures
and tighten budgetary leaks
16CONDITIONAL GRANTS ANALYSIS
17CONDITIONAL GRANTS ANALYSIS
18CONDITIONAL GRANTS ANALYSIS
- Department Of Health
- Comprehensive HIV/AIDS
- An amount of R301,890 million (75,5 per cent) was
spent as at the end of Q3, as compared to total
transfers of R299,700 million by National
Treasury - Forensic Pathology Grant
- As at the end of December, R55,476 million (68
per cent) had been spent - 3 884 post-morterm operations carried out to the
end of Q3 - 257 576 km covered by the 73 FPS vehicles
available for transporting bodies in Gauteng - FPS operating with a 90 per cent staff complement
(including Forensic Pathologists and Medical
Officers) - Hospital Revitalisation Grant
- Hospital Revitalisation had an allocation of
R503,3 million for 2007/08, as well as R63,768
million rolled over from the 2006/07 fiscal year - By the end of Q3, R339,706 million had been
expended, representing 66,6 per cent of the total
amount available - This grant faces undue budgetary pressures, and
besides requiring that expenditure be contained
within acceptable limits - Department Of Sport, Arts, Culture and Recreation
- Community Library Services
- The Community Library Services Grant had spent
R13, 3 million (70.5) of the allocated budget of
R18,8 million by the end of the third quarter of
2007/08, with R5,5million expected to be spent
during the fourth quarter. - About 60 per cent of the unspent funds are
committed, and 4 per cent to be left unspent at
the end of Q4. - Community Library Services
- The MSPP Grant had spent R13, 7 million (49) of
the allocated budget of R28,809 million by the
end of the third quarter of 2007/08, with R15, 5
million expected to be spent during the fourth
quarter
19CONDITIONAL GRANTS ANALYSIS
- Department of Education
- FET Recapitalisation Grant
- The FET Recapitalisation Grant for 2007/08
amounted to R140,5 million, and this was
increased by rollovers from the 2006/07 financial
year amounting to R21,056 million - By the end of Q3, R119,382 million (73,9 per
cent) had been expended out of total budget of
R161,565 million - While it is anticipated that the entire amount
shall be spent by the end of the 2007/08 fiscal
year, challenges faced include - Speeding up of the procurement processes and
conversion of commitments to actual expenditure - Increasing the frequency of monitoring per
college especially those that are behind in their
spending and - Implementation of monthly cash flow projections
- GDE and GT undertake thorough scrutiny of College
monthly reports as well as quotations, invoices
and financial statements and follow up visits to
verify progress as indicated in monthly reports - HIV/AIDS (Life Skill)
- The HIV/AIDS Conditional Grant, amounting to
R22,416 million for the 2007/08 fiscal year, had
spent R17,603 million, against total transfers of
R16,812 million, approximately 75 per cent of the
total 2007/08 allocation - GDE has indicated that measures were instituted
to ensure that districts use 45 per cent of their
budgets before the actual budget allocation - The early start to the programme will also ensure
minimal disruptions in delivering the programme
20CONDITIONAL GRANT ANALYSIS
- National School Nutrition Programme
- With an allocation for 2007/08 of R114,574
million, NSNP had by December 31 spent R85,641
million, representing 75 per cent of the total
2007/08 allocation - GDE anticipates that the full amount shall be
spent - Presently 450 310 learners are beneficiaries of
this scheme - Department of Public Transport, Roads, Works
- Gautrain
- The actual expenditure on the Gautrain grant
amounted to R2,829 billion against the budget of
R3,029 billion - The low expenditure is attributable to the R1,5
billion in foreign transfer payments that does
not reflect in the December IYM ( due to strict
reporting requirements for the Gautrain
payments). Taking this payments into account the
actual expenditure could have been at 83,7 per
cent. These payments will be visible in the
January 2008 expenditure and thus the expenditure
is expected to be high during the remaining
quarter - DACE
- The CASP program had spent R13,8 million (70,1)
of the allocated budget of R19,7million by the
end of the third quarter of 2007/08, with
R5,9million expected to be spent during the
fourth quarter - LandCare Programme spent R2,3 million during the
first three quarters and projects to spend R3,3
million during the fourth quarter. - The Land Care Program transferred R2,3 million
towards the eradication of alien vegetation in
Elandsfontein and Mogale City. - The CASP program has so far cleared 6479 hectares
of alien vegetation against the target of 20 000
ha, the progress has been affected by persistent
rains - 1,191 farmers were trained against an annual
target of 2,150 - 19 mentorship programs undertaken against the
annual target of 25 - Over 400 emerging farmers were given advisory
support
21 END OF PRESENTATION
Thank you!