Approval Process
2
Planning process took 26 mths
20 mths with An Bord Pleanala
Announced project November 2000
Lodged Planning Application January 2001
Revised Planning Permission July 2001
Planning Permission upheld by An Bord Pleanala
March 2003
Appeals to An Bord Pleanala August 2001
An Bord Pleanala Oral Hearing October
2002
Revised Planning Application
6 Planning Permission upheld by An
Bord Pleanala October 2007
5 An Bord Pleanala hold Oral Hearing
of Appeals March 2006
4 Meath County Council grants
planning permission August 2006
3 Indaver provides response to Meath
County Council July 2006
2 Meath County Council Requested
additional information April 2006
1 Revised Planning Application lodged Feb 06
3
(No Transcript)
4
Meath Project Progress to Date
Fire Certification
4 Fire Certificate must be issued by Meath County
Council Fire Deptdecision within 2 months of the
date of receipt of the application, unless an
extension of time is agreed
5 The decision may be appealed to An Bord
Pleanala within one month of the date of the
decision
1 Pre-planning consultation with Meath County
Council Fire Dept to discuss main aspects of
project
2 Fire Certificate Application will be lodged
with MeathCounty Council Fire Dept prior to
construction
3 Meath County Council Fire Dept may request
additional information regarding the project
CER Application
1 An Application for Authorisation to Construct a
Generating Station must be submitted to the
Commission for Energy Regulation (CER)
2 The CER may request additional information
prior to or during its assessment of the
Application
3 Once the CER is satisfied all relevant
information has been supplied it will complete
its assessment of the application and issue
Authorisation