1PLANNING LOGISTICS CENTRES IN OPOLE THE PORTS
OF GDYNIA AND GDANSK - A CASE STUDY
Wojciech Piotrowicz Maritime Institute in Gdansk
2RESULTS OF THE WORK PACKAGE 1 PLANNING OF
LOGISTICS CENTRES
- NeLoC Work Package 1 Leader - Prof. Dr Ludwik
Kondratowicz - Lead Partner - Maritime Institute in Gdansk
- Partners
- Institute of Logistics and Warehousing, Poznan
- Port of Gdynia
- Port of Gdansk
3Agenda
- Time of the presentation 20 minutes
- Logistic Centres Opole, Gdansk and Gdynia
- Goals of the simulation modelling
- Creation of the model
- Results
4Logistic Centre Location
5Opole Logistic Centre
- Industrial zone situated in southern side of
Opole, 8 km from the city centre and 10 km from
motorway A4 (Germany - Russia) - Manufacturing halls - 14200 m2
- Railway siding
- Internal road network
- Utilities
- Pre-investment analysis
6Opole LC main services
- Multimodal transportation
- Logistics services related to warehousing
- Transport and forwarding services
- Distribution
- Logistics support services
7Gdansk and Gdynia Logistic Centres
- Located close or in the ports
- Close to agglomeration of Gdansk, Gdynia and
Sopot population 800,000 - During the pre-investment planning stage
- Located in VI Transport corridor (North-South)
8Logistic Centre Gdynia
- Create the Logistic Centre mostly based on
existing port infrastructure and terminals
(ro-ro, container, cars) - To provide value-added services
- Warehousing and storage
- Consolidation
- Quality control
9Logistic Centre Gdynia
10Logistic Centre in Gdansk Pomeranian Logistic
Center
- Support efficient cargo distribution from three
port terminals - Provide comprehensive services to cargo flows
- Provide empty containers servicing
- Additional services
11Pomeranian Logistic Centre
12Creation of the simulation model
- Defining the simulation goals
- Gathering the data, description of the processes
- Building a model, by means of specialized
software - Model verification
- Presentation of the simulation results
13Logistic Centre Opole
- Main goals of the simulation modelling
- Estimating the infrastructure sufficiency
- Identifying the influence of cargo stream
structure on utilization of resources (warehouses
and employment) - Support area development plan
14Logistic Centre Gdynia
Main goals of the simulation modelling, to answer
the questions
- What is the current utilization level of the
existing and used storage areas (yards,
warehouses, stores)? - Is it possible to shot down warehouse no 20
without negative influence on logistics
processes?
15Pomeranian Logistic Centre
- Main goals of the simulation modelling
- Analyse numerous possible scenarios
- How to arrange planned LC space the best?
- What will be warehouses capacity?
- What and how many of cargo handling equipment is
needed?
16Data collection, processing and verification
17Logistic Centre Opole
- Data of forecast cargo flows - the period of
2004-2007 - Analysis of the volume and structure of cargo
flows (national and international) - Level of employment and technical equipment- same
as in the assumptions of the centres project - Connection with macro and microeconomics data
18Logistic Centre Gdynia
- Historical and present data
- Separately from three terminals
- Some of them already existed in ports documents
- Other had to be collected during processes
observation - Consulting with managers and workers
19Pomeranian Logistic Centre
- Analyses and reports
- Internal (prepared by port)
- External (prepared by other bodies)
- Experts opinions
- Existing logistic centres analyses
- Connection with macro and microeconomics data
20Process Map Gdynia
21The Awesim! simulation model of Gdynia Logistic
Centre
22Taylor ED simulation model of Opole Logistic
Centre
23Simulation reports
24Yards and warehouses utilisation - Gdansk
25Recommended availability of equipment and
transportation means Gdansk
26Yards and warehouses utilisation - Gdynia LC
27Storage and warehouse utilisation average in
28Utilization of warehouse workers labour Opole
LC
100
Utilisation
Months
29Simulation results
30Opole Logistic Centre
- Indicated some bottlenecks during peak seasons
- The need to engage additional resources to fulfil
efficient functioning of LC - Number of workers is not optimal
31Pomeranian Logistic Centre
- Basis for LC spatial arrangement
- Warehouses capacity
- Handling equipment requirements
- Internal transport organisation system
- Optimal utilisation
- lower cost
- flexibility
32Logistic Centre Gdynia
- Present utilisation about 53
- Possibility for development
- No need to build more warehouses
- There is still margin for improvement
33Logistic Centre Gdynia
- To shot down warehouse no 20 will have negative
impact on processes - Warehouses will be build for particular customer
34Simulation modelling
- Help to plan LC development
- Resources (incl. labour)
- Area arrangement
- Give information about resources utilisation
- Tool to optimise logistics processes
- Scenarios analysis
35- Case Study details
- Final report planning of Logistics Centres,
International Project NeLoC - vol. 2
36Thank you!
- Wojciech Piotrowicz
- wojtekp_at_gnu.univ.gda.pl