Title: International Space Station Status To the Biological
1International Space Station StatusTo the
Biological Physical Research Advisory
CommitteeJune 14, 2001
W. Michael Hawes Deputy Associate Administrator
for Space Station Office of Space Flight
2International Space Station Status
Table of Contents I. Overview II. Budget
Status III. Plan of Action IV. Backup
3Overview
- Key Contributions of 3 Partners now in orbit
- Service Module Zvezda July 00
- US Lab Destiny on orbit since January 01
- Remote Manipulator System Canadarm 2 launched
April 01 - Rapid successes 12 ISS Missions since July 2000
- Russia has initiated re-supply responsibility
- 4 Progress Vehicles already flown to ISS
- Numerous other Progress vehicles in flow
- Expedition 1 enabled ISS subsystems in
preparation for lab outfitting -
- Expedition 2 is continuing systems outfitting
and expanding on orbit research - On Orbit assembly continues to be an exhibition
of technical preparation and teamwork - Currently working issues with the Canadam2 and
the Command and Control Computers -
Permanent Human Presence Achieved
4Assembly Milestones to CompleteISS Phase II
(Early Research Capability)
5ISS Research
- Delivery of the U.S. Laboratory Destiny in
February set the stage to begin - significant levels of ISS research
- Expedition 1 focus was outfitting, but conducted
some U.S. research activities - Earth observations, Educations (SEEDS experiment,
EarthKam), biological - crystal growth, technology development, and
human research data collection - Expedition 2 crew has begun a more robust
program of scientific research - eighteen experiments primarily focused on
biomedical research in the - areas of radiation environment, bone loss,
changes in reflexes - Lab outfitting began with delivery of the Human
Research Facility in - March and continues with delivery of the first
two Express Racks in April - Continuing to prepare for on-orbit research
through fabrication and test of - seven additional research racks, ongoing
payload crew training and - development of the ground support
infrastructure including the Payload - Operations Center
HgI Crystal Grown in Microgravity
Research Being conducted during Assembly
6ISS Expedition Crews
A New Era of Permanent Operations in Space
- Expedition 2 Crew
- Launched on Flight 5A.1 (STS-102)
- Yuri Usachev, Commander/Rosaviakosmos
- Jim Voss, Susan Helms
- Return on Flight 7A.1 (STS-105)
- Expedition 3 Crew
- Flight 7A.1 - STS-105
- Frank Culbertson, Commander/NASA Vladimir
Dezhurov, Mikhail Turin
- Expedition 4 Crew
- Flight 8A - STS-109, Yuri Onufrienko,
Commander/Rosaviakosmos - Carl Walz, Dan Bursch
7Assembly Status
- Approximately 3/4 of U.S. flight hardware is at
KSC - Cargo Elements 7A 7A.1 are preparing for
Shuttle launch - Truss elements in acceptance and Multi-Element
Integrated Testing
Science Power Platform
Docking Compartment
Universal Docking Module
Solar Alpha Rotary Joint
Research Module
P3 Truss Segment
Research Module
Docking and Stowage Module
Soyuz
Express Pallet
S3 Truss Segment
S6 Truss Segment
S5 Truss Segment
P4 Truss Segment
S4 Truss Segment
Cupola
Kibo (Hope) JEM Experiment Logistics
Module--Pressurized Section
Starboard Photovoltaic Arrays
Kibo (Hope) JEM Remote Manipulator System
Solar Alpha Rotary Joint
Kibo (Hope) JEM Experiment Logistics
Module --Exposed Section
Node 3
Kibo (Hope) JEM Exposed Facility
Crew Return Vehicle
Habitation Module
Kibo (Hope) JEM Pressurized Module
European Lab Columbus Orbital Facility
8Budget Status
- The FY 2002 Presidents Budget supports ISS
assembly schedule milestones through early 2005,
including the following high priorities - Permanent human presence in space
- World class research
- Accommodation of IP elements
- Projected cost growth and resulting actions for
fiscal restraint modify Program - U.S. Core Complete defined as readiness to
accept International elements - Funding for certain projects has been redirected
to meet high priority needs - Crew Return Vehicle, Prop Module, Habitation
Module, Node 3 - ISS capabilities have been reduced to support a
crew size of 3 - Research activities are being aligned with on
orbit capabilities - Completion of remaining U.S. hardware will be
considered based on affordability and confidence
in our ability to safely and efficiently operate
and utilize the station - Will continue to increase ISS capabilities within
the context of its operations budget
9Summary ofFY02 Presidents Budget
- Principal aspects of the FY 2002 ISS Budget
- Live within the Human Space Flight (HSF) budget
- ISS Assembly through U.S. Core Complete plus
International Partner contributions - Funding for high risk new starts and 40 of
the Research budget redirected - to accommodate U.S. Core Complete within the
HSF budget - Research effort realigned to on-orbit
capabilities during assembly - Management plan to restore cost-estimating
credibility, temporarily transfer - program management reporting to HQs, and
open-up program for competition
10Budget Assessments
- After the Service Module launch in July 2000,
spending rates started to increase - Schedule was no longer shifting to the right
- Several make work changes had to be initiated
(i.e. CMGs) - The previous pattern of undercosting liens
started to reverse - The ISS Program manager called for a new
assessment of the liens and threats - Nov-Dec 00 quick-look assessments indicated a 5
year problem in excess of 2B - Rapid bottoms up assessment completed Jan 30
indicated estimates as high as 4B - Excluded research budget
11Plan of Action
- Agency Strategy for the FY 2002 Presidents
Budget - Redirected Funding
- Propulsion Module (Canceled) 549M
- Habitat Module 421M
- Node 3/Hab Outfitting/ECLSS TBD (Under
Assessment) - CRV Phase 2 1,015M
- Prime Avionics Sys Lab (ASIL) 106M
- S6 Truss/PV TBD (Savings Minimal)
- Realign ISS Research 981M
- Total 3,072M
- Refocus Agency work force to build ISS
- Incorporate Management Reforms
- Identify path to achieving increased crew
- Seek additional Partner contributions to
increase crew time and research resources - Prioritize science and rebalance research
budgets accordingly
12Accommodating Redirected ContentIncreased Crew
Time
- Habitation Module deferred with funding applied
to meet high priority needs. - Eventual growth to a larger crew will require
- Additional life support equipment
- Current capability will handle 3-4 long term crew
- US regenerative ECLSS provides capacity and
redundancy for a crew of 6/7 - Habitation Capability
- NASA will work with IPs on options to enhance
habitation - Redistribute Habitation functions in US core
complete - MPLM based Habitation Module
- Framework for Cooperation signed 4/19/01 between
NASA/ASI - Docking and Stowage Module (SpaceHab Enterprise)
concept - Crew Return Capability
- Soyuz provides 3 person crew return
- Additional Soyuz (purchased, bartered,
commercial) can provide safe return for 6 crew
13International Space Station Status
IV. Backup
14International Space StationRev F Assembly
Sequence
Jan-06
Notes (a) 3-Person Permanent Human Presence
Capability, (b) Microgravity Capability, (c)
Phase 2 Complete, (d) Rack traffic assumes
transition to 7-person crew on 19A
15International Partner Status Russia
- Zvezda Service Module launched and docked July
2000 - First ISS crew successfully launched on Soyuz
rocket, docked to ISS November 2000 - On orbit operations are generally nominal.
Energia and Khrunichev flight operations teams at
MCC-Moscow are integrated with MCC-Houston - First 4 Progress vehicles successfully delivered
propellant and dry cargo to ISS (1P Aug 00, 2P
Nov 00 and 3P Feb 01, 4P May 01) - Docking Compartment 1 (4R) launch delayed from
March to August 2001. No impact to U.S. elements - Russian funding is steady, but remains fragile
- Russia successfully deorbited Mir in March 01
16International Partner Status Canada
- Providing the Mobile Servicing System (MSS),
which consists of the Space Station Remote
Manipulator System (SSRMS), the Mobile Remote
Servicer Base System (MBS) and the Special
Purpose Dexterous Manipulator (SPDM). - SSRMS or Canadarm-2 launched in April
(STS-100/ISS 6A) - Activation still in work
- MBS shipped to KSC August 2000 for April '02
launch (STS-111/ISS UF2) - SPDM Flight Support Equipment CDR completed in
1999, Acceptance Review planned for Fall, 2001
17International Partner Status ESA
- Providing the Columbus Orbital Facility (COF) and
the Automated Transfer Vehicle (ATV), a logistics
resupply vehicle and fuel carrier - Offset contributions include
- Nodes 2, 3 (built by ASI), the Cryogenic Freezer
and the crew R/FRs - Minus Eighty degree Freezer, Microgravity
Sciences Glovebox and Hexapod pointing - Cupola
- COF Final Design Board conducted January 2001.
Pressure hull complete secondary structure in
work - ATV Preliminary Design Review, Final Board
completed December 2000 - Development of hardware provided to NASA through
offsets proceeding on schedule - ESA participating in X-38 program NASA and ESA
have initiated technical discussions regarding
increased ESA participation in CRV
18International Partner Status Japan
- Japan is providing the Japanese Experiment Module
(JEM), which includes - JEM Pressurized Module (PM), JEM Remote
Manipulator System (RMS), - JEM Experiment Logistics Modules (ELM-PS and
ELM-ES), JEM Exposed Facility (EF) - H-II Transfer Vehicle (HTV), a logistics resupply
vehicle. - Offset contributions include
- Centrifuge Accommodations Module(CAM), Centrifuge
Rotor(CR) Life Sciences Glovebox (LSG) - JEM Proto Flight Model (PFM) System and subsystem
integrated testing underway - JEM Overall System Test scheduled to begin at
Tsukuba Space Center, August 2001. - JEM shipment to KSC is scheduled in stages
- JEM PM (1J) and ELM-PS (1J/A) Fall 2002
- JEM RMS (1J) Spring 2003
- JEM EF and ELM-ES (2J/A) Early 2004
- HTV Delta Preliminary Design Review to be
completed in May 2001. - First Flight Demonstration Test of H-IIA launch
vehicle scheduled for Summer 2001 - HTV Demonstration flight to ISS scheduled for
2005 - CAM and LSG PDRs completed in 1999 CR PDR
completed in August 2000, - CR PDR 2 scheduled for October 2001
- Integration Issues threaten launch schedule
- Centrifuge Rotor physical integration and
post-installation verification
19International Participant Status
- Italy
- Through a bilateral arrangement with the United
States, Italy has provided three Multi-Purpose
Logistics Modules which are part of the US
contribution to ISS. Through a trilateral
arrangement between ESA, ASI and NASA, Italy will
provide two Nodes. These will also be part of
the US contribution to the ISS. - All three MPLM Flight Modules delivered to KSC,
and two have completed their initial flights to
the ISS Leonardo in March, 2001 (5A.1) and
Raffaello in April, 2001 (6A) - Node 2 Design Review 2 completed March 2001
- Node 3 Design Review 2 scheduled for November
2001 -
- Brazil
- Brazil will provide the Unpressurized Logistics
Carrier (ULC), EXPRESS Pallet, Z1 Attachment
Site, Cargo Handling Interface Assemblies (CHIA),
Window Observation Research Facility (WORF) and
the Technology Experiment Facility (TEF), which
are part of the US contribution to ISS. - Flight hardware development impeded by continuing
funding uncertainty. Some funding became
available in late 1999, allowing technical work
to continue through summer 2000. Funding remains
a significant issue.