Title: Hazardous Liquid Pipelines
1Hazardous Liquid Pipelines
- ABC Company
- ABC Chemical Complex
- Engineering Specification
2Hazardous Liquid Pipelines
- 1.0 SCOPE
- Covers the design, materials, fabrication,
construction, inspection, testing, operations,
maintenance, and safety aspects of hazardous
liquid pipeline systems - Also covers the components including, but not
limited to, pipe, relief devices, valves,
fittings, flanges, bolting, gaskets, hangars, and
supports.
3Hazardous Liquid Pipelines
- EXCLUSIONS
- Auxiliary piping such as water, air, steam,
lubricating oil, gas, and fuel - Pressure vessels, heat exchangers, pumps, meters,
and other equipment not in scope - Petroleum refinery, natural gasoline, gas
processing, ammonia, carbon dioxide processing,
and bulk plant piping covered in the scope of
ASME/ANSI B31.3, Plant Piping.
4Hazardous Liquid Pipelines
- Exclusions (Continued)
- Gas transmission and distribution piping systems
covered under ASME/ANSI B31.8 - Piping at or below 15 psi
- Piping above 15 psi if design temperature is
below -20oF or above 250oF - Design and fabrication of proprietary items of
equipment, apparatus, or equipment
5Hazardous Liquid Pipelines
- INTENT
- Provide engineering specifications for safe
construction, operation, maintenance, and
inspection of ABC hazardous liquid pipelines - Shall meet or exceed the requirements in
ASME/ANSI B31.4 and DOT 49CFR195 - Not retroactive for existing pipelines which
shall be inspected and tested to the Code used in
original design and construction.
6Hazardous Liquid Pipelines
- 3.0 PIPING SYSTEMS DEFINITIONS
- General Terms (14)
- Piping Systems (20)
- Pressure Relief Stations and Regulators (3)
- Valves (2)
- Pipe and Piping Terms (2)
- Dimensional Terms (3)
- Mechanical Properties (5)
- Steel Pipe (3)
7Hazardous Liquid Pipelines
- 4.0 DESIGN, FABRICATION, OPERATION, AND TESTING
TERMS - Uprating (1)
- Pressure Terms (8)
- Temperature Terms (3)
- Stress Terms (5)
8Hazardous Liquid Pipelines
- 5.0 MATERIALS AND EQUIPMENT
- Acceptable Materials and Specifications
- Marking
- Material Specifications
- Steel Pipe
- Fittings
- Transportation of Line Pipe
- Conditions for Reuse of Line Pipe
9Hazardous Liquid Pipelines
- 6.0 WELDING
- Welding Terms
- Preparation for Welding
- Safe Practices in Cutting and Welding
- Welding Processes and Filler Metal
- Welding Qualifications
- Qualification Records
- Material Limitations
- Welder Requalification Requirements
- Qualification Records (WPS, PQR, Welder)
10Hazardous Liquid Pipelines
- 7.0 Design Conditions
- Provides a set of standards covering
- Specifications for, and selection of, equipment
and piping components - Acceptable methods of making branch connections
- Provisions for temperature changes
- Approved methods for support and anchorage of
exposed and buried piping systems.
11Hazardous Liquid Pipelines
- Design Conditions (Continued)
- Exclusions
- Pipe Materials (Section 5)
- Welding Procedures (Section 6)
- Installation and Testing of Piping Systems
- Special Engineering Stresses Not Specifically
Covered in Specification - River crossings, inland coastal water areas,
bridges, areas of heavy traffic, long
self-supported spans, unstable ground, vibration,
earthquake, thermal, etc.
12Hazardous Liquid Pipelines
- Allowable Stress Values
- S 0.72 x E x SMYS, psi (MPa)
- where 0.72 design factor
- E weld joint factor, normally 1
- Allowable stress values shall be determined for
- Used pipe or new/used pipe of unknown or ASTM 120
specifications - Pipe which is cold worked to meet SMYS and
reheated to 600oF or higher shall be 75 of
applicable stress value
13Hazardous Liquid Pipelines
- Allowable Stress Values (Continued)
- In shear shall not exceed 45 SMYS
- In bearing shall not exceed 90 SMYS
- Structural supports and restraints shall not
exceed 66 SMYS - Structural supports and restraints of unknown
piping specifications shall be assigned an SMYS
of 24,000 psi or less
14Hazardous Liquid Pipelines
- Limits of Calculated Stresses Due to Sustained
Loads and Thermal Expansion - Internal Pressure Stresses
- External Pressure Stresses
- Allowable Expansion Stresses
- Additive Longitudinal Stresses
- Additive Circumferential Stresses Due to
Occasional Loads
15Hazardous Liquid Pipelines
- Limits of Calculated Stresses Due to Occasional
Loads - Operation
- Sum of longitudinal stresses produced by
pressure, live and dead loads, and occasional
loads, i.e. wind and earthquake shall not exceed
80 SMYS - Test
- Stress due to test conditions are not subject to
above limitations
16Hazardous Liquid Pipelines
- Limitations on Design Pressure, P
- Shall not exceed 85 of mill test pressure
- Alternatively, shall not exceed 85 of field test
pressure if mill tests are not available - Limitations on SMYS
- Used pipe from Company stock with known
specifications may be assigned full S value - An S value 24,000 psi shall be assigned to pipe
with unknown specifications
17Hazardous Liquid Pipelines
- Additional Requirements for Nominal Wall
Thickness, t - Shall not be reduced to less than 90 of the
design thickness under any circumstances - Allowances
- Corrosion (Not required if corrosion controlled)
- Threading and Grooving
- Weld Joint Factors
- Wall Thickness and Defect Tolerances
18Hazardous Liquid Pipelines
- Straight Pipe Under Internal Pressure
- Design wall thickness of steel pipe shall be
calculated by the following equation - t PiD/2S
- where Piinternal design gage pressure
- Doutside diameter of pipe, in.
- Sapplicable allowable stress value, psi
-
19Hazardous Liquid Pipelines
- Additional Pressure Design Considerations
- Flanges, Reducers, Fittings, Elbows, Bends, and
Intersections - Closures
- Quick Opening Closures
- Closure Fittings
- Closure Heads
- Fabricated Closures
- Bolted Blind Flange Connections
20Hazardous Liquid Pipelines
- Expansion and Flexibility
- Means of Providing Flexibility
- Amount of Expansion
- Properties
- Coefficient of Thermal Expansion
- (6.5x10-6in./in./oF)
- Modulus of Elasticity (29x106 psi)
- Poissons Ratio (0.3 for steel)
21Hazardous Liquid Pipelines
- Design of Pipe Supporting Elements
- Combined Stress Calculations
- Restrained Pipelines
- Unrestrained Pipelines
- Analysis
- Basic Assumptions and Requirements
22Hazardous Liquid Pipelines
- 8.0 CONSTRUCTION
- Construction Specifications
- Inspection Provisions
- Right-of-Way
- Handling, Hauling, Stringing, and Storing
- Damage to Fabricated Items and Pipe
- Ditching
- Welding
- Tie In
23Hazardous Liquid Pipelines
- CONSTRUCTION (Continued)
- Installation of Pipe in Ditch
- Backfilling
- Hot Taps
- Restoration of Right-of-Way and Cleanup
- Special Crossings
- Block and Isolating Valves
- Mainline Valves
- Scraper Traps
24Hazardous Liquid Pipelines
- CONSTRUCTION (Continued)
- Line Markers
- Corrosion Control
- Pump Station, Tank Farm, and Terminal
Construction - Storage and Working Tankage
- Electrical Installations
- Liquid Metering
- Liquid Strainers and Filters
25Hazardous Liquid Pipelines
- 9.0 INSPECTION
- General
- Shall assure compliance with material,
construction, welding, assembly, and testing
requirements of ABC Specifications, ASME/ANSI
B31.4 and DOT 49CFR 195 - Qualification of Inspectors
- Inspection personnel shall be qualified by
training and experience to the criteria in API 570
26Hazardous Liquid Pipelines
- Inspection Services
- Right-of-way and grading
- Ditching
- Line up and pipe surface inspection
- Welding
- Coating
- Cathodic protection
- Tie-in and lowering
- Backfilling cleanup
- Pressure testing
- Station construction
- River crossings
- Electrical installation
- Radiography
- Corrosion control
- external
- internal
27Hazardous Liquid Pipelines
- Inspection Services
- Backfilling cleanup
- Pressure testing
- Station construction
- River crossings
- Electrical installation
- Radiography
- Corrosion control
- external
- internal
28Hazardous Liquid Pipelines
- Type and Extent of Examination Required
- Visual
- Material-mechanical damage
- Permanent records Location of pipe, wall
thickness, type, specification, and manufacturer - Construction
- Surface defects before coating operation and
during lowering-in and backfilling operations - Pipe swabbing operation
29Hazardous Liquid Pipelines
- Proper alignment and condition of weld joint
surface before welding - Inspect stringer bead for cracks
- Remove irregularities on weld cap to prevent
coating damage - Inspect all repairs, changes, or replacements
prior to backfilling operation - Inspect fit of pipe to ditch prior to backfilling
- Inspect backfilling operations for quality and
compaction of backfill, placement of material for
erosion control, and possible coating damage
30Hazardous Liquid Pipelines
- Inspect cased crossings during installation to
assure that the carrier pipe is supported,
sealed, and insulated from the casing - Inspect piping components other than pipe to
insure damage-free condition and proper
installation
31Hazardous Liquid Pipelines
- Supplementary Types of Examination
- Weld inspection and testing
- Complete in accordance with ABC Specs and
ASME/ANSI B31.4 - Weld defect and repair
- Complete in accordance with ABC Specs and
ASME/ANSI B31.4 - Coatings
- Use ABC Specs and ASME/ANSI B31.4
32Hazardous Liquid Pipelines
- 9.2 TESTING
- Testing of Fabricated Items
- Testing After New Construction
- Systems or Parts of Systems
- Testing Tie-Ins
- Testing Controls and Protective Equipment
- Hydrostatic Testing of Internal Pressure Piping
- Hydrotest to 1.25 times the internal design
pressure for at least four (4) hours - Use API 1110 for guidance in hydrostatic tests
33Hazardous Liquid Pipelines
- Treat hydrotest water with a bactericide and
corrosion inhibitor - Relieve excess pressure during the test as
required - Hydrotesting with gas or nonvolatile hydrocarbons
is not permitted on ABC projects without written
permission from Company management - Leak Testing
- Reduce hydrotest pressure to design pressure and
hold for an additional eight (8) hours
34Hazardous Liquid Pipelines
- Qualification Tests for Pipe
- Visual Examination
- Bending Properties
- Determination of Wall Thickness
- Determination of Weld Joint Factor
- Weldability
- Determination of Yield Strength
- Minimum Yield Strength Value
- Records
35Hazardous Liquid Pipelines
- 10.0 Operation and Maintenance Plans and
Procedures - Written detailed plans and training programs for
employees - Plan for external and internal corrosion control
- Written emergency plan
- Plan for reviewing changes in conditions
affecting the integrity and safety of the piping
system.
36Hazardous Liquid Pipelines
- Liaison with local authorities and other pipeline
operators to prevent excavation accidents. - Procedures to analyze all failures and accidents
to determine the cause and prevent recurrence. - Record system to administer the plans and
procedures. - Procedures for abandoning pipelines
- Procedures to assure public safety in pipeline
operation and maintenance
37Hazardous Liquid Pipelines
- Operation and maintenance of piping systems in
conformance with ABC Specifications, ASME/ANSI
B31.4, and DOT 49CFR195. - Plan and procedure modifications as required
38Hazardous Liquid Pipelines
- 10.2 PIPELINE OPERATIONS AND MAINTENANCE
- Operating Pressure
- The internal design pressure and pressure rating
for all components shall not be exceeded in
steady state operations. - Pressure rise due to surges shall not exceed the
internal design pressure at any point in the
piping system by more than 10.
39Hazardous Liquid Pipelines
- Requalification of a piping system is required if
a higher operating pressure produces a hoop
stress more than 20 SMYS. Requirements in
paragraph 456, ASME/ANSI B31.4 shall be followed
without exception. - Derating of a pipeline to a lower operating
pressure in lieu of repair or replacement may be
completed with the maximum operating pressure
determined by paragraph 10.2.7, ABC
Specification. - Codes in effect during original construction
shall be consulted for allowable stress and
design criteria.
40Hazardous Liquid Pipelines
- Communications
- Markers
- Right-of-Way Maintenance
- Patrolling
- Pipeline Repairs
- Repairs shall be completed in accordance with ABC
Specification, Repair of Pipelines. - Allowable pipeline repairs and repair methods are
summarized in B31.4 and ABC specifications.
41Hazardous Liquid Pipelines
- Railroads and Highways Crossing Existing
Pipelines - Use API 1102 to determine the total stress caused
by internal pressure and external loads. If new
external pipe loading exceeds 0.72SMYS, Company
will install mechanical reinforcement, suitable
protection, or increased pipe thickness. - Installation of uncased carrier pipe is preferred.
42Hazardous Liquid Pipelines
- 10.3 PUMP STATION, TERMINAL, AND TANK FARM
OPERATION AND MAINTENANCE - Pressure limiting devices, regulators, flow
controllers, relief valves, and other safety
devices shall be inspected annually to determine
condition and functionality. - Inspect storage tanks in accordance with API 653.
43Hazardous Liquid Pipelines
- CORROSION CONTROL
- EMERGENCY PLAN
- RECORDS
- Necessary operational data
- Pipeline patrol records
- Corrosion records as required by B31.4
- Records for routine and/or unusual inspections
- Pipeline repair records
44Hazardous Liquid Pipelines
- 10.7 QUALIFYING A PIPING SYSTEM FOR A HIGHER
OPERATING PRESSURE - Review initial design and previous testing
- Determine present condition by leak surveys and
other field inspections, examination of
maintenance and corrosion control records, or
other suitable means. - Complete necessary repairs, replacements, or
alterations.
45Hazardous Liquid Pipelines
- Maximum steady state operating pressure may be
increased after compliance with the previous
slide and one of the following provisions - If the condition of the pipeline is consistent
with the design and hydrotesting has been
completed to a test pressure equal to or higher
than required for the new steady state operating
pressure, the system is approved for the higher
operating pressure. - The system is successfully hydrotested to a test
pressure required for the higher operating
pressure.
46Hazardous Liquid Pipelines
- 10.8 Abandoning a Piping System
- Disconnect all facilities to be abandoned from
all transported sources, i.e., other pipelines,
meter stations, control lines, and other
equipment. - Purge all facilities to be abandoned to replace
the transported liquid and vapor with an inert
material. - Seal the ends of the piping system.
47Hazardous Liquid Pipelines
- 11.0 CORROSION CONTROL
- Scope
- External Corrosion Control
- Internal Corrosion Control
- Pipelines in High Temperature Service
- Stress Corrosion and Other Phenomena
- Records