MRP - PowerPoint PPT Presentation

1 / 35
About This Presentation
Title:

MRP

Description:

MRP Master Production Schedule (MPS) Time-phased plan specifying how many and when the firm plans to build each end item MPS Example Maine Woods Toy Co. Dependent ... – PowerPoint PPT presentation

Number of Views:101
Avg rating:3.0/5.0
Slides: 36
Provided by: prismGat
Category:
Tags: mrp

less

Transcript and Presenter's Notes

Title: MRP


1
MRP
2
Question how do firms actually organize things
to turn materials into finished products?
3
Master Production Schedule (MPS)
  • Time-phased plan specifying how many and when the
    firm plans to build each end item

Aggregate Plan (Product Groups)
MPS (Specific End Items)
4
MPS Example Maine Woods Toy Co.
One possible MPS
5
Products are combinations of parts
Example Bicycle
Handle bars (1)
Metal Frame (1)
Wheels (2)
6
Dependent vs Independent Demand
  • Dependent Demand
  • Demand for a component (raw material, part,
    sub-assembly) is dependent on the demand for the
    end-item into which the component goes.
  • demand often occurs in batches
  • Independent Demand
  • Demand for an item is independent of the demand
    for other items. These demands are typically
    determined by outside customers and are end-item
    demands

7
Bill of Materials (BOM)
  • Shows all the assemblies, subassemblies,
    components, and raw materials required to produce
    an item
  • Shows way a finished product or parent item is
    put together from individual components
  • Parent item shown at highest level or level zero
  • Parts that go into parent item are called level 1
    components and so on
  • Production planners explode BOM for level zero
    item to determine the number, due dates, and
    order dates of subcomponents

8
Lets look at an example BOM...
A
Question How many Ds we need in order to
produce 50 As?
B(2)
C(1)
D(3)
E(3)
D(1)
9
Schematic of MRP System
10
Material Requirements Planning (MRP)
  • Computer-based information system that schedules
    and orders dependent-demand inventory components
  • Uses the master production schedule, bills of
    materials, and inventory records as inputs
  • Outputs recommendations
  • When to release new orders
  • When to reschedule open orders.

11
Lets look at an example BOM...
A
B(2)
C(1)
D(3)
E(3)
D(1)
12
How do we manage order release?
We need information on delivery times!
13
Lets look at an example BOM...
A
(10)
Question When do we start producing/ordering
each part?
B(2)
C(1)
(15)
(10)
(15)
D(3)
E(3)
D(1)
(15)
(10)
14
Lets assume that we need 50 units of A
Delivery date for final product
5 days
15
Lets assume that we need 50 units of A
Start assembly for 50 units of A
16
Lets assume that we need 50 units of A
Start assembly for 100 units of B
17
Lets assume that we need 50 units of A
Start assembly for 50 units of C
18
Lets assume that we need 50 units of A
Order 300 units of D for Bs process
19
Lets assume that we need 50 units of A
Order 50 units of D for Cs assembly
20
Lets assume that we need 50 units of A
Order 50 units of E for Cs assembly
21
Summary How does MRP work?
Material Requirements Planning
Production
Assembly
Customer
Production
Assembly
Production
Units are PUSHED forward according to the plan!
22
What about JIT/Lean Production?
Production
Assembly
Customer
Production
Assembly
Production
Units are PULLED forward only when needed!
23
Push/Pull Decoupling Point
Material Requirements Planning
Cheeseburger
Hamburger Patties
Forecast
Hamburger
Chicken Patties
Chicken Sandwich
Units are PUSHED forward to a certain point.
Final configuration (PULL) occurs only when the
actual customer demand occurs.
24
Lot Sizing in MRP Systems
  • MRP generates material orders
  • Order sizes/lots can be chosen according to
    various objectives
  • Lot-for-lot (L4L)
  • Produce to cover next period
  • EOQ
  • Apply the EOQ approximation for yearly demand
  • Least Unit Cost
  • Minimize total cost (order carry) per unit

These are all approximate methods, none is
guaranteed to be optimal. We can apply all of
them and find the least-cost one to implement.
25
Example
Cost per item 10 Order/setup
cost 47 Inventory carrying cost/month 2 Start
ing inventory 50 Production lead time 1
month Monthly requirements 1 2 3 4 5 6 100 50 80
120 70 80
For the solution, see file mrp_methods.pdf
26
MRP Evolution
MRP
Schedule Materials
Closed Loop MRP
Schedule Materials Incorporate Feedback
MRP II
Schedule Purchase Materials Coordinate w/ Mfg
Resources
ERP
27
Closed-Loop MRP
Production Planning Master Production
Scheduling Material Requirements
Planning Capacity Requirements Planning
No
Feedback
28
Manufacturing Resource Planning (MRP II)
  • Goal Plan and monitor all resources of a
    manufacturing firm (closed loop)
  • manufacturing
  • marketing
  • finance
  • engineering
  • Simulate the manufacturing system

29
ERP Systems
  • Enterprise Resource Planning Systems is a
    computer system that integrates application
    programs in accounting, sales, manufacturing, and
    other functions in the firm
  • This integration is accomplished through a
    database shared by all the application programs

30
Typical ERP System
31
Video ERP at Hillerich Bradsby
  • Notes

32
Major ERP Providers
Source AMR Research
33
Reasons to Implement ERP
  • Desire to standardize and improve processes
  • To improve the level of systems integration
  • To improve information quality

34
ERP Drawbacks
  • Cost
  • 250M for a Fortune 100 company
  • Transition pain
  • Implementation resources
  • Training
  • Resistance to change

35
Summary and Conclusions
  • Master Production Schedule (MPS) converts
    aggregate plan to a detailed schedule
  • Primary inputs to MRP are MPS, BOMs (for part
    relationships) and Inventory Records (for lead
    times and inventory position)
  • MRP is a push system but can be used in
    conjunction with pull systems
  • MRP grew and evolved to include closed-loop,
    Manufacturing Resource Planning (MRP II), and
    eventually ERP
Write a Comment
User Comments (0)
About PowerShow.com