Title: Project
1Projects methodology application for TEM
- D. Tsamboulas
- External Consultant
2Objective
- identify projects prioritization/
categorization, - support elaboration of a medium and long-term
investment strategy in the region concerned - encourage the realization of projects that have
good chances of implementation and fall within
the TEM Master Plans objectives.
3Phases of Methodology
- PHASE A Identification
- PHASE B Forecasting
- PHASE C Evaluation
- PHASE D Prioritisation
4Identification Phase
- Identification of the projects that worth further
analysis and evaluation according to their.. - Relevance
- Readiness
- Viability
- countries complete TEMPLATES 1 and 2
5TEMPLATE 1 Identified Projects
6TEMPLATE 2A Road and related infrastructure
Project Fiche
7(No Transcript)
8(No Transcript)
9(No Transcript)
10TEMPLATE 2C Maritime/port Fiche
11(No Transcript)
12(No Transcript)
13Forecasting Phase
- Any official forecasts or official estimations
could serve in verifying and finalize
consultants forecasts. - Alternative demand scenarios are to be produced
in the framework of WP3, in a qualitative
macro-scale based on the expected economic
development of the countries concerned as well as
other characteristics. - If forecasted data are not collected, then WP3
results will be used. For any forecasted data
provided, consistency with the macro-level
forecasts (elaborated in WP3) will be
investigated.
14Evaluation Phase
- Selection of Criteria 3 hyper-criteria
- CLUSTER A Socio-economic return on investment
(CA) - CLUSTER B Functionality and coherency of the
network (CB) - CLUSTER C Strategic/ Political concerns
regarding the network (CC) - Quantification of Criteria - Scores
- Weighting/ Hierarchy of Criteria Delphi/Paired
Comparison - Total Performance of Project
- (gt to assist Prioritization on the next Phase)
15Selection and Quantification of Criteria -1
- 1. Degree of urgency
- A Immediate requirement (in the next 2
years-until 2005), B Very urgent (between 2005
and 2010), C Urgent (between 2010 and 2015), D
May be postponed for some years (between 2015 and
2020), E To be reconsidered later (after 2020) - 2. Cost effectiveness
- A Excellent (IRR more than 15), B Very
good (13-15), C Good (10-13), D Acceptable
(4,5-10), E Low (less than 4,5)
16Selection and Quantification of Criteria -2
- 3. Relative investment costs (costs/GDP)
- Rehabilitation/upgrading of highways A less
than (min cost of this project type/GDP)
(intermediate values to be calculated assuming
linearity, see next figure) E more than (max
cost of this project type/GDP) - New two-lane highway or single carriageway A
less than (min cost of this project type/GDP)
(intermediate values to be calculated assuming
linearity, see next figure) E more than (max
cost of this project type/GDP) - Complete four-lane motorway A less than (min
cost of this project type/GDP) (intermediate
values to be calculated assuming linearity, see
next figure) E more than (max cost of this
project type/GDP) -
17X1 the min cost of the project type observed in
the country (in million or ). X2 the max
cost of the project type observed in the country
(in million or ) X3 the considered project
cost (in million or ) Countrys GDP given in
million or
ED DC CB BA1 and A5, B4, C3, D2, E1
Figure 1
18Selection and Quantification of Criteria -3
- 4. Level of transport demand
- Highways A present traffic more than 14000
vpd B present traffic from 10000 to 14000 vpd
C from 6000 to 10000 vpd D from 3000 to 6000
vpd E less than 3000vpd - Border crossings A present traffic more
than 3500 vpd B present traffic from 2500 to
3500 vpd C from 1500 to 2500 D from 800 to
1500 E less than 800 vpd -
- 5. Financing feasibility
- A Excellent, B Very Good, C Good, D
Medium, E Low
19Selection and Quantification of Criteria -4
- 6. Relative importance of international demand of
traffic (passengers) - A more than 30 of total traffic B from
25 to 30 of total traffic C from 15 to 25
of total traffic D from 7 to 15 of total
traffic E less than 7 of total traffic - 7. Relative importance of international demand of
traffic (goods) - The same as 6.
- 8. Alleviation of bottlenecks
- A Satisfactory, B Adequate, C Medium, D
Inadequate, E Unsatisfactory
20Selection and Quantification of Criteria -5
- 9. Interconnection of existing networks
- A Missing Link, B Natural Barrier, C
Improve the connection, D No influence, E
Averse effects on rest of network -
- 10.Technical interoperability of network
- A No interoperability problems, B Minimal
interoperability problems, C Tolerable
Interoperability problems, D Serious
interoperability problems, E Unsolvable
interoperability problems -
21Selection and Quantification of Criteria -6
- 11.Border effects
- A No border problems, B Minimal border
problems, C Tolerable border problems, D
Serious border problems, E Unsolvable border
problems -
- 12.Political commitment
- A Strong, B High, C Medium, D Adequate,
E Low -
- 13. Regional and international cooperation
- A Satisfactory, B Adequate, C Medium, D
Inadequate, E Unsatisfactory -
22Selection and Quantification of Criteria -7
- 14. Historical/ heritage issues
- A No effects, B Minimal effects, C
Tolerable/ Reversible effects, D Serious
effects, E Irreversible effects -
- 15. Economic impact
- A Strong impact, B High impact, C Medium
impact, D Low impact, E No impact -
23Criteria Scores
- A value is 5 (the highest) in terms of score.
Respectively for value E, is 1 (the lowest). - Therefore
- where
- J A, B or C and
- i 1,.,5
- The template for criterions scores is TEMPLATE 3.
24TEMPLATE 3 Project Criteria Scores
25Criterion Scores from Country Experts
- Good communication between the externals and the
country experts is necessary. - For instance, war effects or weather that
destroyed sections of transport infrastructure.
If the external consultants for some reason will
not identify them as missing links in criterion
CB4, then country experts must do it, when
reviewing the criterion scores.
26Weighting/ Hierarchy of Criteria
- Country experts have received TEMPLATE 4 with
proposed default set of weights, derived by the
consultants, using Paired Comparison Matrix. - The sum of criteria weights should be 1.
-
- Therefore and
- where
- J A, B or C and
- i 1,.,5
27Paired Comparison
- Paired comparison approach is a scaling approach.
- Only one question to be answered is is this
criterion more important than the other?. - This means that the paired comparison matrix (see
Table I next) can be filled with zeros and ones,
where one represents is more important. - By adding these values over the column, a measure
is obtained for the degree to which a criterion
is important compared to all other criteria, if
finally these measures are standardised (see
Formula I next), a set of criteria weights is
created.
28Table I An example of Paired Comparison matrix
Standardised score wi (I)
29TEMPLATE 4 Project Criteria Weights
30Criteria Weights from the Country Experts
- As an example, if country A wishes to put high
priority for sections of the network destroyed by
war or weather. Then, the experts have to
classify them as missing links, and in the
weighting they have to put high values in the
criterion CB4, as well as criterion CC2 . - Another example is when a country wishes to
promote a link that it considers important as a
domestic link in such a case it has to put a
very low weight to criteria (CB1), (CB2), (CC1). - Furthermore, if country experts provide their own
weights, with the proper justification then they
will be used instead of default weight introduced
by the external consultants.
31Projects Total Score/ Performance -1
- To derive the projects total score in each
country we use the following relationship - T.S.Project/Country
- where
- CJi ? 1,5
- WJi ? 0,1
- J A, B or C and
- i 1,.,5
- TSProject/Country ? 1,5
32Projects Total Score/ Performance -2
- For Total Score per Project, we use Country/
Spatial Weights (SW). -
- SWCountry of projects length in the
country/ total projects length. - So the Total Score per project will be
-
- T.S.Project T.S.Project/Country SWCountry
33Prioritization Phase
- The combination of the criterions scores and
priorities puts each project in one of the four
priority categories. - If the project scores between 4-5 then it belongs
to priority category I. - If the project scores 3 then it belongs to
priority category II. - If the project scores 2 then it belongs to
priority category III. - If the project scores 1 then it belongs to
priority category IV.
34Priority Categories
- I projects, which may be funded and implemented
rapidly, including on-going projects up to 2010. - II projects requiring some additional
investigations for final definition before likely
financing, or planned for implementation up to
2015 - III projects requiring further investigations
for final definition and scheduling before
possible financing, or planned for implementation
up to 2020. - IV projects to be implemented in the long run,
including the projects where insufficient data
exists.
35Prioritization Results
- If a project results i.e. to be in priority
category II according to TEM Methodology but
according to Van Miert prioritization belongs in
another Priority Class (i.e. A, B or C) then Van
Mierts prioritization will be followed, at least
for the EU member states (current and the ones to
be members in 1/5/2004). - On the other hand, in the unlikely case that the
priority of a project differs with the national
priority, a more thorough analysis on the
underlying assumptions will take place.
36Assumptions for Criteria Quantification
37Criterion CA1 Degree of urgency
- Where the countries indicated the time plan of
the projects elaboration, the time plan was used
for the quantification of this criterion - Where time plan was not mentioned but in the
goals -or the expected benefits of the project-,
the project was described as necessary for
compliance with EU directives/ policies, or for
decreasing unemployment or for other very
important reason and at the same time the total
implementation period of the project was between
1-5 years, the score given was 5A - Where time plan was not mentioned but in the
goals -or the expected benefits of the project-,
the project was described as necessary for
compliance with EU directives/ policies, or for
decreasing unemployment or for other very
important reason and at the same time the total
implementation period of the project was between
5-10 years, the score given was 4B - For any other case (of implementation years), the
score given was 3C - If there werent any available data to support
the quantification of this criterion, then the
score given was the lowest 1E unless there was a
good justification and then the score given was
2D, assuming that the project merits some
consideration.
38Criterion CA2 Cost effectiveness
- If the IRR was available then the quantification
was done as described earlier. - If no IRR was available without any
justification- the score given was the lowest 1E - If the IRR was not available with a strong
justification like i.e. the feasibility study is
not completed yet but it is on-going the score
given was the 3 C, assuming that the project
merits consideration. - For any other case of missing IRR, the score
given was 2D.
39Criterion CA3 Relative investment cost
- Where the min and max values of a country for
each project type were not available (and they
werent available in all countries that so far
have sent data) the following assumption was made
the min and the max values from the group of
projects presented were used.
40Criterion CA4 Level of transport demand
- If traffic data were available then the
quantification was done as described earlier. - If no traffic data were available without any
justification- the score given was the lowest 1E
- If traffic data were not available with a strong
justification like i.e. the traffic study is not
completed yet the score given was the 3 C,
assuming that traffic is such to justify the
project consideration. - For any other case of no traffic data the score
given was 2D.
41Criterion CA5 Financing feasibility
- Where the expected IRR was very high, the private
sector financial participation was also very high
and if the financial study was completed and
accepted, the score would be 5A. - Where the expected IRR was medium towards high,
the private sector financial participation was
also medium towards high and if the financial
study was completed and accepted, the score would
be 4B. - Where the expected IRR was medium, the private
sector financial participation was also medium
and if the financial study was completed and
accepted, the score would be 3C. - In any other case the score was 2D, except where
no IRR or no feasibility study was available or
IRR was really low and there were no private
funds as well, then the score given was 1E.
42Criteria CB1 CB2Relative importance of
international demand of traffic (passengers
freight)
- If traffic data were available then the
quantification was done as described earlier. - If no traffic data were available without any
justification- the score given was the lowest 1E
- If traffic data were not available with a strong
justification like i.e. the traffic study is not
completed yet the score given was the 3 C,
assuming that international traffic is such to
justify the project consideration. - For any other case of no traffic data the score
given was 2D.
43Criterion CB3 Alleviation of bottlenecks
- If traffic data before and after (through
forecasting), were available then their
comparison indicated whether alleviation of
bottlenecks took place. Based on these results
the scores are produced. - If no traffic data were available without any
justification- the score given was the lowest 1E
- If no traffic data were available before and
after, with a strong justification like i.e.
the traffic study is not completed yet the score
given was the medium one 3C, assuming that the
difference in traffic before and after the
project implementation is such to justify the
project consideration. - For any other case of missing traffic data the
score given was 2D.
44Criterion CB4 Interconnection of existing
networks
- If in the projects description was mentioned that
this project (road or rail) will alleviate a
missing link the score given obviously is 5A. - If in the projects description was mentioned that
this project (road or rail) will improve the
condition of the current situation the score
given obviously is 3C. - If nothing of the above was mentioned the
quantification was done based on unique
characteristics of each project. However for all
considered projects the score given was 3C and
in some cases 5A.
45Criterion CB5 Technical interoperability of
network
- If a project was cross-border and based on the
descriptions of the participating countries
interoperability problems exist, then 3C or
lower. - 4B is used only in not so severe
interoperability cases, where data exists and it
can be verified. - However all projects considered were inside
countrys borders so the score given to all was
5A.
46Criterion CC1 Border effects
- If a project was cross-border and based on the
descriptions of the participating countries
border problems exist was 3C or lower. - 4B is used only in cases when border problems
exist, but are not so critical. - However, all the projects considered were inside
countrys borders so the score given to all was
5A.
47Criteria CC2, CC3, CC4, strategically sensitive
criteria
- For the three strategically sensitive criteria
- Political commitment (CC2)
- Regional and international cooperation (CC3)
- Historical/ heritage/ environmental issues (CC4)
- the score given to all projects was 5A,
since the consultant believes it is rather
impossible for any country -and concerning any
type of project- not to be politically committed
to it and also not to try for the best regional
cooperation as well as to ignore environmental/
heritage issues. - In cases that a country expert assigns a
different value then the default value will be
changed.
48Criterion CC5 Economic impact
- Where a) the expected IRR was high, b) the
revenues from tolls -in case of roads-were
expected to be sufficient, c) the travel time was
reduced, d) safety was increased, e) access to
ports or other terminals was easier and f)
socio-economic parameters (economic development,
unemployment) of the region were expected to
benefit from the project, the score given was
5A. - Where a) the expected IRR was medium towards
high, b) the travel time was reduced, c) safety
was increased and d) socio-economic parameters
(economic development, unemployment) of the
region were expected to benefit from the project,
the score given was 4B. - Where a) the expected IRR was medium and b) the
travel time was reduced score given was 3C. - For any other case the score given was 2D,
except where no data were available and then the
score given was 1E.
49Example of Evaluation Methodology for TEM using
assumptions
- Greek Project
- Egnatia Motorway
- Section Komotini - Vanianos.
50Example steps
- Complete Project Fiche see next
- Derive Criteria Scores
- Use default set of Criteria Weights
- Derive Project Total Score
- Prioritize Project
51TEMPLATE 2A Road and related infrastructure
Project Fiche
52(No Transcript)
53(No Transcript)
54(No Transcript)
55Criteria Scores-1
- 1. Degree of urgency
- In the socio-economic evaluation of the project,
as included in the feasibility study, and
according to governmental priorities, the
projects implementation is characterized as A
immediate requirement. - CA15
- 2. Cost effectiveness
- Based on the data of TEMPLATE 2A, the projects
cost effectiveness is characterized as A
Excellent (IRR higher than 15 ). - CA25
56Criteria Scores-2
- 3. Relative investment costs (costs/GDP)
- Based on the data of TEMPLATE 2A, countrys
GDP and Figure 1 the projects relative
investment cost is characterized as C. - CA33 (or 2,8 from Figure 1 directly -see
example next) - 4. Level of Transport Demand
- Based on the data of TEMPLATE 2A, the level of
transport demand is 14000vdp, therefore the
projects level of transport demand is
characterized as B present traffic from 10000 to
14000 vpd. - CA44
57X1 110 million X2 200 million X3 159
million GDP 136.300 millions
Therefore (X1/GDP) 0,08 (X2/GDP) 0,15
(X3/GDP) 0,116
58Criteria Scores-3
- 5. Financing Feasibility
- In the viability study of the project, and
according to experts opinion, the projects
financing feasibility is characterized as B Very
Good. - CA54
- 6. Relative importance of international demand of
traffic (passengers) - Based on the data of section 1, the relative
importance of international demand of passenger
traffic is 5,2 (500/9500) therefore the
projects relative importance of international
demand of passenger traffic is characterized as
E less than 7 of total traffic. - CB11
59Criteria Scores-4
- 7. Relative importance of international demand of
traffic (goods) - Based on the data of section 1, the relative
importance of international demand of freight
traffic is 33,33 (1500/4500) therefore the
projects relative importance of international
demand of freight traffic is characterized as A
more than 30 of total traffic. - CB2 5
- 8. Alleviation of Bottlenecks
- Based on experts opinion the projects
alleviation of bottlenecks is characterized as A
Satisfactory. - CB35
60Criteria Scores-5
- 9. Interconnection of existing networks
- Based on experts opinion the projects
interconnection of existing networks is
characterized as A Missing Link. - CB4 5
- 10. Technical interoperability of network
- Based on experts opinion the projects
technical interoperability in the network is
characterized as A No interoperability problems. - CB55
61Criteria Scores-6
- 11. Border effects
- The project is a one-country one, therefore
regarding the border effects is characterized as
A No border problems. - CC1 5
- 12. Political Commitment
- The political commitment is characterized as A
Strong. - CC25
- 13. Regional and International Cooperation
- The regional cooperation (since there is no
international cooperation) is characterized as A
Satisfactory. - CC35
62Criteria Scores-7
- 14. Historical/ heritage Issues
- According to the Environmental Impacts Study
of the project, there are no effects on
historical heritage, therefore the project scores
A No effects. - CC4 5
- 15. Economic Impact
- According to the socio-economic study of the
project, it is expected to have a C Medium
Impact. - CC23
- See TEMPLATE 3 completed next..
63TEMPLATE 3 Criteria Scores
64TEMPLATE 4 Criteria Weights
65Projects Total Score
- In our case is only one country so spatial
weighting was unnecessary - Based on methodology described earlier the
calculation of Total Score is presented in
TEMPLATE 5. (It is the weighted sum of criteria
scores or else TEMPLATE 5 is the result of
multiplying TEMPLATES 3 and 4)
66TEMPLATE 5 Project Total Score
67Prioritization of Project
- The Project Total Score is
- T.S. 4,32
- Therefore the project belongs in Priority
category - I projects, which may be funded and
implemented rapidly, including on-going projects
up to 2010.
68First evaluation for submitted TEM projects
- See Matrix next results
- for the countries that sent data, namelyAustria,
Bulgaria, Czech Rep., Greece, Hungary, Lithuania,
Poland, Romania, Slovakia, Slovenia, Turkey and
Ukraine. - Countries for which data are pending.
- Italy, Belarus, Bosnia Herzegovina, Croatia,
Georgia, Serbia Montenegro, F.Y.R.O.M, Russia
Federation, Rep. Of Moldova
69(No Transcript)
70(No Transcript)
71(No Transcript)
72(No Transcript)
73POLAND
74(No Transcript)
75POLAND
76(No Transcript)
77(No Transcript)
78(No Transcript)
79(No Transcript)
80Notes on the Matrix
- In total the TEM projects are 232 with
- 13 (else 30 projects) belong in Priority
Category I - 35 (else 81 projects) belong in Priority
Category II - 1 (else 3 projects) belong in Priority Category
III - 51 (else 118 projects) belong in Priority
Category IV - with the last result a bit overestimated since
the consultant was force in most cases of no data
to put the minimum score.