Title: chaired by HCC


1
Two daily Meetings at 830 1630 in the CCC
Glassbox
7.00
22.00
15.00
morning shift
afternoon shift
14.00
  • chaired by HCC
  • results of the evening run
  • open issues blocking circuits, control,
    infrastructure
  • presentation of the programme of the day
    planning which goes beyond the day (dedicated
    Twiki)
  • results of the day
  • debriefing (open meeting)

830

1630
2
The staff per even point
dedicated to an even point
Operation Crew
common to all the points
Coordination
Mr.Circuit, PO, MEL, MPP, CO, ACROP, CPP
System Experts
PO, QPS, EE, PIC, Current Leads, ElQA, MPP, CO,
ACR, DFB, Inner Triplet
On-call service
On two shifts
Field Crew
3
Powering Test Coordinator
  • Acts globally
  • Masters the test procedures of all the circuit
    types and ensures they are compliant with the
    needs and specification by all the equipment
    groups as well as MPP
  • Keeps track of the status of the individual test
    procedures implemented by the sequencer for each
    circuit type
  • Keeps track of the status of the software tools
    (sequencer, post mortem, logging, supervision
    applications, logbook, etc.) to carry out the
    commissioning
  • During powering tests
  • Are in charge on a weekly basis
  • Participates to the coordination meetings
  • Follows up open issues concerning procedures,
    implementation of the procedures by the sequencer
    , software tools
  • With the Point Owners, prepares the SOC and the
    test plan of the day
  • Decides on schedule changes to comply with
    conflicts and situations (blocked circuits,
    resource, etc) arising in the field

4
Even Point Owner
  • Acts locally on the two sectors adjacent to
    his/her even point
  • Is aware of all the systems (e.g. injection, warm
    magnets, dump, rf, etc) around his/her point and
    knows and coordinates the ISTs and commissioning
  • Before a new step starts, ensures that all the
    Individual System Tests and the Hardware
    Commissioning have been carried-out, the data has
    been stored and interpreted by the responsible
    person
  • Ensures that the equipment/components of the
    circuits are in a state compatible with the
    execution of the tests and organizes diagnostics
    /repairs
  • Prepares and follows-up the IST, the tests during
    cool down and the cool down
  • Keeps track of the planning, of the progress and
    of the non-conformities encountered
  • During powering tests
  • Must be available to intervene during two shifts
    (stand-by duty)
  • Minutes issues concerning his/her point during
    the 8.30 and the 16.30 meetings chaired by HCC
  • Follows up open issues concerning his/her point
  • Chases people needed during the coordination
    meetings
  • With the PTC prepares the SOC and the test plan
    of the day
  • Decides on schedule changes to comply with
    conflicts and situations (blocked circuits,
    resource, etc) arising in the field

5
Engineer in Charge
  • Acts locally on two fronts with an operator
  • Ensures the smooth running of the powering tests
    of the SOC of the day following the powering test
    procedures
  • During powering tests
  • Is present in the CCC during two shifts
  • Is responsible that safety-wise incompatible
    co-activities are not authorized
  • Coordinates work with the teams (QPS, EE, PC,
    PIC, Cryo Operation, etc) participating to the
    commissioning of his front
  • Creates the SOC of the day
  • Ensures that the morning run starts at 700 and
    takes over the evening run at 1400
  • Updates the war map for his/her point
  • Is responsible for the detailed reporting in the
    logbook of all what happens during the shift
  • Ensures that test data and results are recorded
    as expected in the logging system and the
    post-mortem system
  • Is responsible for the detailed reporting of test
    results in the MTF
  • Reports to the coordination meetings chaired by
    HCC the outcome of the powering tests
  • Requests support from the piquet services (CV,
    EL, PO, VAC, CO, ACR, etc.) in case of need
  • Consults with the Point Owner (or the Powering
    Tests Coordinator) on conflicts and situations
    (blocked circuits, resource, etc) arising in the
    field

6
Coordination
Group owning the equipment
Inform
HCC
Intervention team