Title: Materials for Lecture 19


1
Materials for Lecture 19
  • Readings Chapter 14
  • Lecture 19 Short Project Management.XLS
  • Lecture 19 Project Management.XLS
  • Lecture 19 Event Management.XLS

2
Project Management
  • Project management involves estimating the length
    of time to complete a project
  • Once a project has been undertaken then a project
    manager is responsible for carrying out the
    project on the assigned time table
  • How do the managers establish a time schedule
  • Generally based on average length of time for
    each component
  • Average length of time based on past experience
  • Length of time to complete each step is a random
    variable

3
Project Management
  • Who does project management?
  • Engineers, managers, accountants
  • They calculate number of days to completion
  • They do not incorporate risk most times
  • Benefits of incorporating risk into project
    management analysis
  • Assign a probability to number of days until
    project completion
  • Assign a probability to getting a project done in
    a fixed timeframe

4
Project Management
  • The KOV for a project management problem is
    How long will it take?
  • There is no final answer until it is completed
  • Answer is an unknown PDF of days, weeks, or
    months
  • Simulation provides a methodology for estimating
    unknown PDFs
  • Formulate the problem as a Monte Carlo simulation
    problem

5
Project Management
  • Model formulation
  • KOV is Number of Days to completion
  • Identify each task (step) for project
  • Specify order of each task for the project
  • Identify bottlenecks where tasks will wait on
    precious stages
  • Determine the PDFs for number of days (or weeks,
    months, etc.) to complete each task
  • Use past performance to estimate parameters for
    PDF of days for each task
  • Depend on experts for time to complete each task
  • PDF may be dependent on resources available

6
Project Management
  • Critical to identify the order of the tasks and
    their linkages (dependencies)
  • For example
  • Task 10 starts after Tasks 5 and 8 are completed
  • Task 11 starts after Task 10 is completed
  • Thus, Task 5 or 8 could hold up the whole project
  • If analysis shows 5 is the bottleneck is it worth
    investing more resources in Task 5 to get the
    project completed earlier?

7
Project Management
  • Create a Project Network Diagram to summarize the
    order of tasks
  • Can be drawn in Excel with simple arrows and
    boxes
  • Network diagram shows potential bottlenecks

8
Project Management
  • Tasks 1-6, 2 and 3 wait on 1, 4 waits on 2, 5
    waits on 3 and 4, last task waits on 5
  • Assumes new task starts the next day
  • Days in column C are GRKS() stochastic

9
Project Management
10
Spreadsheet of a Project Management Analysis
11
Event Planner
  • Event planner KOVs
  • Number of days ahead to start planning an event
  • Cost of the event
  • Research application KOVs
  • Time to complete a research project
  • Cost of project
  • Wedding planner
  • Probability of being ready on time
  • Cost of the event
  • Banquet planner

12
Event Planner