Title: Section 10 Red Team Report
1Section 10 Red Team Report
. . . Ronald L. Thomas EO-1 Red Team Review
Chairman
2May 9, 2000
EO-1 RED TEAM REVIEW MRR Report to GSFC Program
Management Council
. . . Ronald L. Thomas EO-1 Red Team Review
Chairman
3Background
- EO-1 Project approved March 1996
- EIRR formed to review EO-1 Project in June 1999
- Participated in Orientation, Pre-Environmental,
SAC-C, Hyperion Pre-ship, and EO-1 Pre-ship
Reviews - Red Team formed to review the EO-1 Project in
March 2000 - Initial Review held March 28-31, 2000
- Red-Team met on April 11 to review findings
- Red Team Summary Report presented to Bill
Townsend on May 9, 2000 - Thermal Vacuum II Readiness Review held on June
11, 2000 - Red Team meeting held on June 13, 2000 to
review - Probabilistic Risk Management
- Failure Mode Effects Analysis
- Fault Tree Analysis
- Delta Pre-ship Review held August 9-10, 2000
- Co-chaired by C. Vanek and R. Thomas
4Team Membership
5Specific EO-1 Red Team Tasks
The Red Team evaluated the 13 Project Specific
Areas below (as contained in the Charter) on a
scale of 1-10 (with 7 being nominal) for each of
the Major Project Elements
- Technical Performance Reviews the level,
competence, and independence - System Level Reviews the performance, level,
and independence - Test and Verification Program the level and
thoroughness implemented include VV and IV V
used on software - Product Assurance level imposed on each project
element. Includes parts usage, workmanship
standards imposed, and software assurance
processes used - Systems Management level imposed on project.
Includes the performance and thoroughness of
analyses, requirements management, documentation
and technical-record keeping and workmanship and
test process management. - Verification Matrix that shows the verification
of the pre-launch requirements, and addresses the
fidelity and type of verification.
6Specific EO-1 Red Team Tasks (continued)
- 13 Project Specific Areas (continued)
- Staffing the experience of the implementing
organizations - Test and Integration all hardware and software
element results. Include information on review
and assessment of all failures and anomalies, and
their resolution - Failure-free and Total Operating Time consider
for all mission critical hardware and software - Technical Review Process consider the results,
and an assessment of all significant RFAs. Also
consider the Projects responses to these RFAs - Mission Simulations and Launch/Operations
consider the amount, level, and fidelity that has
been done, or planned to be done - FMEAs, Fault Tree Analysis, and Probabilistic
Risk Assessment Consider the use of these tools
in quantifying the residual risk of EO-1,
focusing on the Minimal Mission (as defined in
the EO-1Mission Success Criteria). - Single-point Failures consider all, and provide
a subjective assessment of the probability of
each such failure mode causing a mission failure.
7Specific EO-1 Red Team Tasks (continued)
- In evaluating these 13 items, the Red Team was
asked to do the following - Evaluate EO-1 in terms of the likelihood of it
completing the validation requirements for the
Minimal Mission - Document the 13 evaluation items for each Mission
Element on a score of 1-10 with 7 being nominal - Ascertain and document all residual risks, and
provide recommendations for mitigation - Assess all single-point failure mechanisms, and
provide recommendations on their acceptability or
non-acceptability, and the rationale for each
conclusion. The WARP is to be specifically
considered - Assess the FMEA, Fault Tree Analysis, and the
Probabilistic Risk Assessments - Provide a full Report of the above to the GSFC
PMC at the EO-1 MRR - Provide an overall mission risk statement, along
with justification for the statement. - Each member is to provide a written report to the
Chairman within 6 days after each review. - The Chairman is to provide a verbal report to the
GSFC Dep. Center Director within 10 days after
each review.
8Red Team Findings for theEO-1 Project Specific
Assessments
- GENERAL OBSERVATIONS
- EO-1 Team is to be commended for excellent Red
Team Reviews - All information very well presented in the
required Red Team format - All speakers knew their subjects and were very
open and responsive to detailed questions - All Red Team RFAs were very well addressed and
documented Web-based responses were very
helpful. - EO-1 was implemented as a NMP Faster, Better,
Cheaper Technology Program - Few NASA standards imposed on the program
- Primary focus to deliver the technology for the
cost and schedule proposed - Project not required to have an FMEA or Risk
Management - To reduce cost, S/C is single-string design and
has inherent risk. - EO-1 Project has had numerous Technical Peer
Reviews and Systems Level Reviews
9Red Team Findings for theEO-1 Project Specific
Assessments
- GENERAL OBSERVATIONS (continued)
- Accelerated Minimal Mission has been baselined
and increases opportunity for mission success
(can be achieved in 120 days) - Combining high technology in the S/C subsystem
(WARP) to get large amounts of data from the
instruments, adds risk (WARP must work to get
data from instruments) - WARP has worked very well throughout all testing
with exception of a low-voltage power supply
failure (heritage hardware) - WARP operated flawlessly during the second T/V
observatory test. - MAP heritage was to be flowed into EO-1, but EO-1
overtook MAP - There appears to be an imbalance between the
completeness of the environmental test program
for the various components. - The 3 instruments, 2 of which are not mission
critical, were subjected to a more complete
environmental test program which included T/V and
sine vibration. - WARP, ACDS, and PSE (which are single-string, and
are critical to the success of the program) were
subjected to ONLY random vibration and thermal
cycling (but not T/V). These operated flawlessly
during a second T/V test.
10General Observations
- This is Swales first time as a S/C integrator
- They have experienced staff
- They appear to have done a good job.
- Some of the GSFC supplied GFE (WARP) received
minimum QA processes - Resulted initially in a low program specific
assessment rating of 6 that the team believed
could not be rectified. (However, very few
failures occurred during subsequent observatory
level testing) - As the Red Team investigated the GSFC hardware,
particularly the WARP, it was found that the QA
was better than initially believed to be. - Note, the Red Team did not reach consensus on a
rating of 7, but most of the team believed a 7
more accurately represented the QA then the 6. - Although the FMEA, Fault Tree Analysis and
Probabilistic Analysis was done after S/C
development, they were done well and added value - Appropriate staffing of the EO-1 Project Office
(number and experience base) came on late in the
program. - No Chief Engineer function assigned continuously.
- Continuity of personnel was an issue (Minimal
Mission helps this)
11Red Team Rollup of Project Specific Assessments
for Each Element
12- WARP is required for mission success
- Combining high technology in the WARP to obtain
large amounts of data from the instruments,
introduces risk. - WARP technology functions high data rate, high
density storage, working well - Only failure has been the 5-volt power supply
(random failure of a diode) - Lack of an ETU for WARP made troubleshooting very
difficult - Boards required much re-work, jumpers, etc.
- Data Interface Board had to be replaced parts
unavailable to replace Data Boards - Red Team conducted an independent assessment of
the quality and analyses of the WARP Boards - The boards had been re-worked, but were found to
be in satisfactory condition - Parts Level Stress Analysis was assessed by Red
Team and found to be satisfactory. - Red Team requested Project provide thermal
analysis of the WARP hardware configuration to
determine thermal stresses of parts at their
maximum power operating mode. (Analysis was found
to be satisfactory). - Red Team endorsed Projects plan for proceeding
with a design for using empty board slot in WARP
to provide a backup WARP function for meeting the
minimal mission requirements. - With the additional T/V testing successfully
completed, Red Team agrees that project should
proceed with WARP as originally designed.
Red Team Findings for the EO-1 Project Specific
AssessmentsS/C Subsystems - WARP
13- Since Preliminary Red Team Report in May 2000,
the following work has been completed - All operations training
- Technical Peer Review of safe mode on-orbit test
- Security Review
- Close out of critical and urgent discrepancy
reports - End-to-end test of flight S/W load /dump and
compare S/W - Installation of launch version of ground software
- Spacecraft users guide and constraints and
restrictions document - All contingency procedures
- Remaining work to be completed by launch
simulation on 10/11-12/00 - Installation and verification of launch database
2.1 - Final testing of launch version of ground S/W
- Verification of all constraints and alerts
- Completion of all end-to-end tests and
simulations - With successful completion of launch simulation
on 10/12/00 and planned freeze of software and
database, Red Team believes that operations is
ready to support launch.
Red Team Findings for the EO-1 Project Specific
AssessmentsSummary Findings for Operations
14Red Team Findings for theEO-1 Project Specific
Assessments
- Launch Vehicle Evaluation Factors
- The launch vehicle was evaluated in the context
of a commercial launch services contract - Emphasis was placed on evaluating mission unique
and L/V to S/C interfaces the core vehicle was
reviewed to a lesser degree - Major mission-unique item (Dual Payload Attach
Fitting (DPAF)) was reviewed in detail - The Red Team assessment was based on a
presentation and action items answered by KSC no
contractor presentations were made - Observations
- There is no integrated mission document signed by
the two flight projects attesting to their
concurrence that their respective interface
requirements have been met and verified - KSC signs Boeing Mission Specification for NASA
- Although EO-1 depends on KSC to ensure correct
integration of all interface requirements with
other primary and secondary spacecraft, no signed
documentation exists which assigns clear
accountability for potential incompatibilities
between the two primary spacecraft - EO-1 dependent on KSC for updates
- Compliance is heavily dependent on MIWG process
15Red Team Findings for theEO-1 Project Specific
Assessments
- Concern
- The absence of S/C project signature gives the
impression of a lack of accountability by GSFC in
the verification of their payload requirement
interfaces - Recommendation
- Require that the two spacecraft projects clearly
document their accountability for all interface
requirement verifications - KSC continues to authorize Mission Specification
with current signature process
16Payload Fairing
- Fairing collision with overpass
- During transportation of the payload fairing from
Pueblo to VAFB, the fairing shipping container
was driven into an overpass, resulting in minor
damage to fairing - Fairing has been repaired
- Fairing contamination concern
- Review of Globalstars 5 and 7 post-flight video
indicated that some particulate debris had been
generated, most likely originating from the
Fluoroglide lubricant applied to the fairing
separation rail bellows - The EO-1 Project determined that this risk was
not acceptable because some spacecraft
instruments were located near the fairing split
line and were, therefore, potentially susceptible
to this contamination - The fairing contractor, Boeing, disassembled the
fairing and cleaned all the lubricate. GSFC
personnel inspected the cleaned parts and
confirmed that they satisfactorily met the EO-1
project requirements. - The fairing is being reassembled and will be
shipped to the launch site. - The Red Team will review the KSC ERB actions
concerning the laminate repairs, the disassembly,
cleaning, testing, and re-assembly of the fairing
in the very near future.
17Red Team Findings for theEO-1 Launch Vehicle
Risk
- Launch Vehicle Residual Risk for EO-1 Mission Is
Low
18Red Team EO-1 Residual Risks Recommendations
for Mitigation
RESIDUAL RISK ORIGINALLY REPORTED BY RED TEAM
RISK MITIGATION
- S/C is a single-string design
- WARP is an advanced technology data processor and
storage device that is necessary for Minimal
Mission success
- Obtain at least 300 hours of system failure-free
T/V operation - Successfully completed except for S-band
transponder - Implement around the clock, 3 shifts per day,
on-orbit operations this allows Minimal Mission
to be completed in about 120 days - Minimal mission has been base-lined
- Probabilistic Risk Assessment shows probability
of success for the Minimal mission to be 0.9 - Obtain at least 300 hours of WARP failure-free
operation - Successfully achieved in T/V II
- Need Stress Analysis that shows acceptable parts
de-rating. - Stress Analysis completed acceptable parts
de-rating - Define backup solution that utilizes the empty
slot in the WARP, or a new box that matches the
baseplate footprint, to meet the requirements of
the ALI only - Design successfully completed, but not
implemented because of successful operation in
T/V II.
19Red Team EO-1 Residual Risks Recommendations
for Mitigation
- Conduct walk-throughs of all mission critical
ground and flight software, and freeze software
no later than start of baseline functional
testing for T/V exercise this software during
T/V - This was successfully implemented
- Project should assess how they will conduct EO-1
operations utilizing the existing test bed with
an acceptable level of risk to the mission - Project successfully addressed this in the
Pre-ship Review Presentation. - Requires failure-free operating time on S/C and
accelerated operations plan - Failure-free operating time achieved (except for
S-band transponder), and Minimal-mission
base-lined. - Red Team members did review some GSFC supplied
hardware and QA paper work and found that they
were better than the Red Team originally thought
they were.
- Flight software still undergoing change and has
minimal failure-free operation time - High fidelity hardware / software test bed does
not exist for supporting on-orbit operations - The QA process as chosen by the Project for the
Goddard GFE has resulted in a level of program
risk that cannot be quantified.
20Red Team EO-1 Residual Risks Recommendations
for Mitigation
- Require that a worst case analysis be done that
quantifies the amount of margin that may be used
before launch - Project determined margin and has taken steps to
insure that margin does not erode. - Perform thermal analyses of hardware to determine
thermal stresses at maximum power operating mode.
Evaluate performance in upcoming S/C T/V
testing. - Successfully completed
- Problem could not be determined, but identical
unit from the TRIANA Mission is being
substituted. These transponders have a good
history and the TRIANA unit has completed
acceptance testing. Additional failure-free
hours will be put on the unit to achieve a total
500 hours of operation in TV and an additional
300 hours in ambient integrated with the S/C.
- The amount of He required to use up the Gyro
margin is unknown. The concern is that the Gyro
margin may be exceeded before launch. - Critical S/C hardware, WARP, PSE ACDS, received
only thermal cycling (not T/V). - S-band transponder suffered an intermittent
failure during S/C TV II Testing
21Red Team Assessment ofEO-1 Single-Point
Failures, FMEA, FTA, PRA
- Red Team Charter focuses on single-point failure
mechanisms as a major source of residual risk. - Three system engineering tools have been used (at
the NASA Administrators request) to estimate the
likelihood of occurrence and overall mission risk
associated with the predominate failure modes - Failure Modes and Effects Analyses (FMEA)
- Fault Tree Analysis (FTA)
- Probabilistic Risk Analysis (PRA)
- These tools were not used to develop the EO-1
design, but were performed as part of the Red
Team process after the design was completed - Single string design by policy (redundancy was
largely out-of-bounds) - Selective redundancy utilized where possible
- These tools have been used in a complementary way
to evaluate the likelihood of successfully
completing the EO-1 Minimal Mission - Included the Flight, Ground System and Launch
(mission unique) - Utilizing these tools, the Probabilistic Risk
Assessment yielded a mission success probability
of 0.90 for the Minimal Mission (120 days)
22Red Team Assessment ofEO-1 Single-Point
Failures, FMEA, FTA, PRA
- EO-1 S/C does have selected redundancy and not
all hardware is required to meet the Minimal
Mission - Solar Array Loss of a string can be tolerated
- Solar Array Drive Not required for Minimum
Mission - PSE some internal work-arounds available
- 1773 Data Bus Redundant fibers, Star Couplers,
and Transceivers - Propulsion Not required for Minimum Mission
- WARP Some internal partial redundancies
- X-Band Transmit Not required for Minimum
Mission - ALI Some internal partial redundancies
- Not all instruments/hardware are required to meet
the Minimal Mission - Hyperion, LAC
- X-Band Phased Array Antenna, Lightweight Flexible
SA, Pulse Plasma Thruster, GPS, Warp X-Band
Exciter - Launch Vehicle Mission-Unique FMEA
- EO-1 Separation from DPAF Bolt Cutters and
Wiring are redundant - Ground System FMEA
- Spares and alternative data paths
- Safe Hold will keep EO-1 unharmed during Ground
System outages
23Red Team Assessment ofEO-1 Single-Point
Failures, FMEA, FTA, PRA
- WARP as a Single-Point Failure
- Is a single string component
- Has an S-Band back-up to the X-Band Channel
- Memory chips can fail without any impact to the
WARPs operation - Can map around large areas of failed memory
- Entire memory board can fail without impact to
the other memory board - WARP reliability prediction is 0.896 for one year
and 0.950 for 120 days - Red Team believes the WARP represents an
acceptable risk for EO-1 - Received in-depth assessment from Red Team
(examination of boards, stress and thermal
analyses reviewed) - Red Team concerned there was no breadboard or
engineering model, but examination of boards
showed all re-work done well. (Memory Interface
Board was replaced) - Has never had a design failure and only one
hardware fix (defective part in LVPC) - Has had no software modifications
- Over 2000 hours of operation, over 750 hours of
T/V operation, and over 500 hours since the
replacement of the LVPC regulator board
24Red Team EO-1 Overall Mission Risk Statement
(with Justification)
- The Red Team assessment is that EO-1 is a low
risk for achieving success for the Minimum
Mission - Major risk is the single string design
- Power System, ACS, WARP, and ALI must operate
properly or mission is a complete loss - S/C systems and ALI instrument do have selected
redundancies - Mitigation
- Selected redundancy and many operational
work-arounds do exist - Loss of Star Tracker can be mitigated by use of
three-axis magnetometer (TAM) - Loss of IRU can be mitigated by use of the Star
Tracker - S-Band transmitter can backup the X-Band
capability (not vice-versa) - Housekeeping RSN essential only through Solar
Array deployment - WARP can lose a whole memory board (or parts of
both boards) and still meet mission requirements. - Failure of one of the ALI SCA channels can be
tolerated. - The ALI and S/C systems have a high number of
operating hours - The Flight Operations Team participated fully in
all S/C testing - The Delta is a proven LV
- Minimal Mission Success can be achieved in only
120 days at a probability of success of 0.90
(0.75 if spread over one year)
25Back-Up Charts
26Instruments ALI (Rating 7)
- The ALI is necessary to meet the Minimal Mission
- Lincoln Lab developed the instrument
- Lincoln Lab had good management involvement and a
long history of building this type of hardware. - They also had good peer reviews.
- They had a good test program with good factors of
safety. - The ALI has selective redundancies in the
mechanisms to reduce the possibility of failure - Red Team found all processes for the ALI to be a
7 (nominal) or above. However, the re-occurring
contamination that occurs in the focal plane
needed to be addressed. (Addressed at the Delta
Pre-Ship Review) - On-board reference lamp tracks contamination
- Heating of focal plane drives off contamination
- On-orbit decontamination process included in
mission planning - Failures in the ALI occurred early, were
successfully repaired, and were well documented.
27Instruments Hyperion (Rating 7)
- This is a TRW developed instrument
- Not required to meet the Minimal Mission
- Based on existing designs, good technical
reviews, and test and excellent calibration
processes. - Implemented excellent risk management and product
assurance program. - Built on schedule within 12 months and quality
was not cut or reduced. - Selected redundancies to increase probability of
success.
28Instruments LAC (Rating 7)
- This is a Goddard developed instrument which
implemented Goddard workmanship and quality
control standards. - They conducted all the appropriate environmental
testing, including T/V at the box level - LAC is not required for the Minimal Mission
- There have been no residual problems noted on
this hardware
29Spacecraft Subsystems
- 1. Technical Peer Reviews (Rating 7)
- Hardware
- All S/C Subsystems have documented peer reviews
- Software
- Some software was peer reviewed by the MAP
Project - RFAs submitted to identify all mission critical
software, and formal code walk-throughs have been
conducted for all critical software - Code walk-throughs completed for all critical
software
30Spacecraft Subsystems (continued)
- 2. System Level Reviews (Rating 8)
- Total of 32 Reviews completed between EO-1
Primary Configuration Review in May 1997 and Red
Team Preliminary Report in May 2000 - 403 RFAs assigned
- 6 Reviews to launch (including Red Team Reviews)
- Review Sponsorship
- 20 Reviews for Office of Flight Assurance (code
300) conducted - 17 External Reviews (EIRR, Littles Committee,
Senior Managers Review, Red Team) - 2 Engineering Directorate Reviews (AETD, Code
500) - 5 NMP/EO-1 Project Office Reviews
- Cross-involvement of all review teams in many
reviews - Additional GSFC and Red Team Reviews held since
May 2000 include - Thermal Vacuum II Readiness Review
- Red Team Review of RFAs and EO-1 Risk Analyses
- Delta Pre-Ship Review
31Spacecraft Subsystems (continued)
- 3. Test and Verification Program (Rating 7)
- The observatory functional and environmental test
program was complete and included all the
appropriate testing required - The philosophy of the Project was to defer
testing (in some cases) to observatory level by
limiting the box level testing -- Red Team
believes that this has resulted in additional
risk - Lack of Engineering test units is a residual risk
to program, trouble shooting difficult on ground
and on orbit - Red Team recommended a min. of 300 hours of
failure-free operating hours be obtained in T/V
on all hardware to obtain sufficient hardware
confidence. - This was successfully achieved except for a
failure of the S-band transponder (heritage
hardware). - Project obtained a replacement transponder from
the Triana Program and will achieve sufficient
hours of operation on it and in the system prior
to launch. - Software project utilizes 7 RSNs and 2 Mongoose
V Processors - Software has some heritage from SAMPEX, XTE, TRMM
and MAP. - Part of the software had formal IVV
- Software operated successfully during final 300
hour T/V testing of the observatory
32Spacecraft Subsystems (continued)
- 4. Product Assurance (Rating 7)
- The contractor elements ALI, Hyperion, etc.,
seemed to have a more rigorous quality process
than the GSFC elements. - Inconsistent across all of the hardware by the
Project / Institution. A serious consequence is
that it is difficult if not impossible to put
Product Assurance back into the hardware - Red Team initially concerned that a minimal
effort was performed on the GSFC hardware
regarding Product Assurance - Independent assessments of the GSFC hardware,
particularly the WARP, showed that the PA was
better then initially believed. - Successful completion of the 300 hour T/V testing
at the observatory level (except for the
transponder) adds confidence that the PA is
adequate
33Spacecraft Subsystems (continued)
- 5. Systems Management (Swales) (Rating 8)
- The Swales Systems Manager provided a good review
of their Systems management of the S/C - Good traceability of lowest level requirements
back to Level 1 (EO-1 Project Plan) - Each of the lowest level requirements, for a
given function, was verified by Analysis, or Test
and Evaluation - Critical S/C resources were well managed Mass,
Telemetry, Power, etc. - Configuration Management processes in place for
drawings and IT Procedures - Excellent work order process utilized
- Excellent IT Management
34Spacecraft Subsystems (continued)
- 6. Verification Matrix (Rating 7)
- The Project provided a complete verification
matrix for all the elements/subsystems. - The Verification Matrix was reviewed by each
presenter for his particular subsystem/area
during all subsequent reviews and was found to be
adequate
35Spacecraft Subsystems (continued)
- 7. Staffing (Rating 7)
- Project staff which presented to the Red Team
were knowledgeable and competent. - Swales provided names/experience of their project
personnel - Swales has excellent subsystems experience, but
this was their first S/C integration - Swales key personnel had extensive S/C
integration experience - The present GSFC staff has extensive experience
in their respective areas. We were informed that
the project staffing did get off to a very slow
start and had a high turnover rate. In fact, B.
Cramer and D. Schulz are the only two remaining
from the original EO-1 Team. - The project manager has extensive S/C experience.
- The current software manager has excellent
experience, but has only been on board since late
1999. - The GSFC supplied WARP, LAC, and Formation Flying
teams all appear to have well-qualified staff.
36Spacecraft Subsystems (continued)
- 8. Integration and Test (Rating 8)
- Technically sound Integration and Test program
- CPT to test every function and to measure
performance of every subsystem. - Contains about 100 individual tests
- All nominal and critical commands tested (about
500). - Performed non-CPT Performance Tests
- End-to-End optical for instruments, X-Band
pointing tests, GPS Constellation Tests, Solar
Array mechanical deployment, Heater tests, etc. - MOC simulation tests
- Thermal Vacuum Tests of complete S/C
- Conducted CPT at both hot and cold plateaus
- Functional tests conducted during pump-down and
at end before chamber break. - Conducted post-environmental CPT in Dec. 1999
- Good procedures for checking out all systems and
for reporting problems (RFA submitted). - 300 hour T/V test successfully completed at
observatory level prior to Delta Pre-Ship Review
(except for transponder)
37Spacecraft Subsystems (continued)
- 9. Operating Time (Rating 7)
- Red Team initially concerned that there was not
enough failure-free hours in T/V at the
observatory level due to - disassembly of S/C,
- software not completed or frozen,
- WARP power supply board had been changed, and
- many mission critical boxes did not undergo T/V
after re-work - Project alleviated this concern by successfully
completing a 300 hr. T/V test (except for the
transponder) prior to the delta pre-ship review. - During these tests the observatory was exercised
through its thermal, power, and data handling
extremes. - New Transponder will have sufficient operating
time at the box level and system level prior to
launch.
38Spacecraft Subsystems (continued)
- 10. Technical Review Process (Rating 7)
- Project has initiated actions to close RFAs
generated by Red Team. - The project has addressed RFAs from all the
reviews and is close to having them all closed
out. - Web-based system for reviewing and closing out
RFAs worked well - Project presented many of the critical Subsystem
RFAs and how they were closed during the Red Team
Review.
39Spacecraft Subsystems (continued)
- 11. Mission Simulations and Launch/Operations
(Rating 8) - Red Team has found the mission simulations plans
and implementation to be good. - Project has accomplished flight operations team
training using classroom techniques, the actual
vehicle, and training simulators. This training
plan is very thorough and complete. - ORR scheduled for October 3, 2000 and there are
still a number of actions that are not complete.
It is expected that the open actions will be
closed, but if not the rating of 8 will be
reduced.
40Spacecraft Subsystems (continued)
- 12. FMEA, Fault Tree Analysis, and Probabilistic
Risk Assessment - The FME, FTA and PRA were completed after the
design and development of EO-1 was nearly
complete. - Project conducted a special review for the Red
Team to review these Risk Analyses - The Risk Analyses appear to have been done well
and have added confidence that EO-1 is a low risk
for meeting the minimal mission of 120 days.
41Spacecraft Subsystems (continued)
- 13. Single-Point Failures (Rating 7)
- Single string systems have a long successful
history at Goddard, but hardware must have a
robust design and good quality. - Red Team recommended a minimum of 300
failure-free operation hours in T/V to mitigate
the S/C changes and the single-string risk. - Red Team supports the Project recommendation to
accelerate Operations so the Minimal Mission can
be verified as quickly as possible (120 days). - EO-1 is single-string, but some hardware has
selected redundancies - Mechanisms for the solar array deployment,
- ALI and Hyperion Instrument cover actuators
- Solar array parallel strings
- X-band antenna can fail gracefully due to
multiple SSPAs - X-band and S-band communication modes.
- WARP has redundant memory boards, each of which
can fail gracefully - 1773 data bus, and power harness
- ACS Separate safehold processor, main computer
memory, and propulsion heater. - All non-essential loads have fuse protection
42Spacecraft Technologies
- The S/C technologies are all rated 7 or above in
all the specific assessment areas they are - Enhanced Formation Flying, EFF
- Light-weight Flexible Solar Array, LFSA
- Carbon-Carbon Radiator, CCR
- X-band Phased Array Antenna, XPAA
- Global Position System, GPS
- Pulsed Plasma Thruster, PPT
- The above technologies with the exception of EFF,
XPAA and PPT can not jeopardize the Minimum
Mission. - PPT will not be activated until after the Minimal
Mission requirements are satisfied. - EFF software can be changed from the ground if
problems arise. - XPAA has many redundant SSPAs, and is backed up
by S-band.
43Spacecraft Technologies (continued)
- XPAA is rated 7 or above in all the specific
assessment areas. - XPAA is not necessary to meet the Minimal Mission
(ALI data only and using the S-Band), but is to
communicate the large amount of data from the
three instruments. - The Red Team believes the XPAA has a low risk of
failure - Designed and built by Boeing under fixed-price
contract with GSFC - NASA GRC provided independent evaluation of RF
Modules, packaging and array communications
performance using Boeing EM hardware. - Three formal contract reviews conducted.
- Experienced design / development team
- Has more than 350 hrs. on-time since integrated
on S/C - No open items
- Very redundant design except for the RSN
44Operations
- 1. Technical Peer Reviews (Rating 7)
- 2. System Level Reviews (Rating 7)
- Operations included in the Project system
reviews. - 3. Test and Verification (Rating 7)
- Test and Verification approach is sound.
- Verification of the flight and ground database
expected before ORR - Implementation and verification of constraints
and restrictions (CR) are nearly complete (
Review at ORR on 10/3/00) - Project has limited test bed for on-orbit anomaly
investigation and for trouble- shooting problems
but by combining MAP and EO-1 hardware all the
software can be tested on the ground - 4. Product Assurance (Rating 7)
- Operations products (procedures, database, CR)
are now under CM
45Operations (continued)
- 5. Systems Management (Rating 7)
- Systems management approach and plans are sound
- Team has done a good job of documenting problem
reports - Operations documentation is Web-based
- 6. Verification Matrix (Rating8)
- Project provided an Operations testing matrix
showing status/plans for all operations tests. - 7. Staffing and Experience (Rating 8)
- Operations Team appears to be adequately staffed
with experienced personnel. - Team presented detail plans on how it would
implement 24 hour, 120 day Minimal Mission
46Operations (continued)
- 8. Test and Integration (Rating 8)
- Project uses same ground system for operations
training and IT - By launch, the operations ground software will
have 600 hours with the S/C - 9. Failure Free and Total Operating Time (Rating
7) - Red Team recommended and EO-1 achieved a minimum
of 300 hrs. of failure-free S/C operation for T/V
tests prior to delta pre-ship review. - 10. Technical Review Process (Rating 7)
- Project has some open Operations RFAs assigned
by the Red Team (ORR item) - 11. Mission Simulations Launch/Operations
(Rating 8) - Project has conducted many mission simulations to
date, final plans TBD for ORR - Most of the operations staff have participated in
IT - Contingency planning was well done and nearly
complete (ORR Review)
47Operations (continued)
- 12. FMEA, FTA, PRA (Rating 7)
- Appropriate documents were supplied to Red Team
for review - 13. Single-Point Failures (Rating 7)
- Both S-Band and X-Band communication available
from S/C to ground. - Ground can communicate through at least two
ground stations and through the TDRSS System
48Launch Vehicle Evaluation Factors
- Dual Payload Attach Fitting (DPAF)
- DPAF comments based on review of documentation
and splinter meeting with DPAF program office
management team - DPAF documents reviewed
- Design Certification Review (9/28/99)
- Design Certification Review Update (3/7/00)
- Delta L/V Design Certification Review (9/29/99)
- Requirements Verification Matrix
- Failure Modes and Effects Analysis
- Specification Control Drawing (1D89290)
49Launch Vehicle Evaluation Factors (continued)
- Overall DPAF Observations
- DPAF program was well planned and executed
- Mission Success was top priority throughout
program (no cut corners) - DPAF design was heavily based on Ariane
4/MMS/SPELDA design and process heritage - Critical flight items were fully redundant and
thoroughly tested - Matra Marconi Space (MMS) and Boeing have
significant relevant flight experience - Very Low Residual Risk
- Lack of modal survey prevents reduction of small
uncertainties in predicted loads - Load/deflection was used to verify structure and
interface stiffness - Modal survey is more rigorous
50Launch Vehicle
- 1. Technical Peer Reviews - 8
- DPAF (Dual Payload Attach Fitting)
- DPAF major new development item
- DPAF reviewed more extensively than the few other
mission unique elements - Several independent peer reviews held for DPAF
- Independent reviews attended by relevant
subsystem experts (considerable breadth) - Other Mission Elements
- Level, competence and independence of KSC
resident teams very good - Continuity of KSC review function stable
throughout transition of mission - KSC Delta specific depth limited
51Launch Vehicle (continued)
- 2. System Level Reviews - 7
- DPAF
- Standard set of system level reviews
- Additional Design Certification Review held
- Many different organizations involved in reviews
- NASA KSC, NASA OLS, Boeing,etc
- Vested interest in mission success by all parties
(potential future capability) - Other Mission Elements
- Standard set of system level reviews
- Experienced background for MIT (mission
integration team) - limited experience in current roles
- above average experience in other aspects or
other launch vehicles - For mission unique items, KSC conducts some
independent reviews - KSC has contractual right to approve/disapprove
or right to review all mission unique or mission
specific analyses, testing and reports - Heavy dependence, with KSC participation, on
Boeing review process for core vehicle items
Aerospace under contract for pedigree reviews
52Launch Vehicle (continued)
- 3. Test and Verification Program (for mission
uniques) - 9 - DPAF
- DPAF Test and Verification very complete and
detailed very high standard - Although subcontractor had exceptional heritage
on SPELDA program, DPAF still re-tested as a new
design - LCCD systems subjected to both SPELDA and US
conventional Lot Acceptance Testing - DPAF LCCD gets the benefit of MMS standard
practices and US testing philosophy - LCCD Lot Acceptance Testing and Margin testing
performed - Second Proof Test after pathfinder activity
eliminates risks - Small residual risk due to lack of Modal Survey
- Other Mission Elements
- PAF Fit check and shock testing with flight PAF
- GN2 purge standard mission specific item
numerous flights standard design - Independent KSC review of standard Boeing vehicle
testing
53Launch Vehicle (continued)
- 4. Level of Mission Assurance - 8
- DPAF
- GSFC Code 300 performed DCRs and provided
important continuity - Experienced NASA FA individual continuous on DPAF
throughout program - Transitioned with program to KSC
- Additional KSC mission assurance capability still
developing - Consistent NASA Project Office involvement
throughout DPAF program - Boeing and NASA mission assurance present
throughout development of DPAF - DPAF received greater scrutiny as a development
program - MMS quality control processes appear to be quite
thorough - Other Mission Elements
- Boeing mission assurance processes above average
for DPAF, average in general - KSC mission assurance limited but growing
54Launch Vehicle (continued)
- 5. Systems Management for Mission Uniques - 7
- DPAF
- NASA DPAF team constant throughout life of system
- Minimum Boeing Personnel turnover
- Minimal Boeing subcontractor personnel turnover
(MMS) - Detailed configuration control implemented by
Boeing through Specification Control Drawing
Process - Other Mission Elements
- KSC focus on mission unique and integration items
- Mission Specification (a.k.a. Interface Control)
Document not formally signed by spacecraft
projects (see special topic)
55Launch Vehicle (continued)
- 6. Staffing - 8
- DPAF
- Experienced NASA project office personnel
- Boeing and MMS team have considerable previous
experience - Other Mission Elements
- Experienced KSC resident team at Boeing
- Stable Boeing workforce reported by KSC
- Limited Delta-specific contractor and civil
servant experience at KSC - Technical depth improving with experience
56Launch Vehicle (continued)
- 7. Integration and Test - 9
- DPAF
- Thorough integration and test program for DPAF
- Good waiver/nonconformance process
- Rigorous tracking of non-conformances
- Most waivers issued against documentation
corrections - Other Mission Elements
- Strong ERB System review by KSC Systems
Engineering and Flight Assurance - Well defined system tests
- Well defined PAF Fit and Shock Tests
- NASA telemetry lab participates in Delta testing,
allowing detailed analysis
57Launch Vehicle (continued)
- 8. Operating Time - 7
- DPAF
- DPAF does not contain any active electronic items
(i.e.. black boxes) - Other Mission Elements
- No mission unique electronic configurations
required for mission.. - 9. Technical Review Process - RFAs - 8 (Above
Standard) - DPAF
- All RFAs tracked and answered
- All DPAF independent review team RFAs were
implemented - Other Mission Elements
- RFAs tracked and answered
58Launch Vehicle (continued)
- 10. Mission Simulations/Testing - 7
- DPAF
- S/C PAF Fit checks shock testing performed
- Pathfinder activity performed
- Prepared launch site personnel for DPAF
processing - Validated facility capabilities and
accommodations - Other Mission Elements
- KSC Delta experience recently exercised on Image
launch campaign - Other recent DS-1, Landsat-7
- Detailed mission dress rehearsal
59Launch Vehicle (continued)
- 11. Assess FMEA, FTA and PRA for Completeness - 7
- DPAF
- FMECA and Separation Reliability Analysis
completed - Other Mission Elements
- FMECA, FTA, PRA tools not formally used for
launch vehicle - FTA used for post-failure analysis
- KSC active participant, with approval authority,
in all phases of mission unique development and
implementation - FMEA, PRA, FTA not required for vehicle mission
uniques
60Launch Vehicle (continued)
- 12. Mission Requirements Verification Matrix - 8
- DPAF
- DPAF detailed verification matrix completed
- Launch Vehicle specific requirements for DPAF
also tracked and documented - Other Mission Elements
- Heritage GSFC and Boeing verification processes
- The Boeing Mission Specification (nominal
interface control document) not signed by
spacecraft projects (see special topics) - Boeings formal verification process for their
mission specifications occurs very late in the
integration process - Not an early program process or document
(end-game process) - KSC developing independent verification database
EO-1/SAC-C first use - KSC process improvement
61Launch Vehicle (continued)
- 13. Single Point Failures - 7
- DPAF
- Single point failures limited to high reliability
item (i.e. structures) - DPAF is quite simple (mostly structure), and
robust - LCCD fully redundant
- Other Mission Elements
- Core vehicle not reviewed
- No Single point failures identified for EO-1
interface - standard Delta 37 Clampband with dual 37 pin
connectors