CITY OF POLOKWANE

Description:

Received tender price = R 1 245 236 999. Funding. Funding from National Government ... the tender. Follow the MFMA guidelines for procuring the tender. THANKS ... – PowerPoint PPT presentation

Number of Views:76
Avg rating:3.0/5.0
Slides: 13
Provided by: pmg2
Category:
Tags: city | polokwane | tender

less

Transcript and Presenter's Notes

Title: CITY OF POLOKWANE


1
CITY OF POLOKWANE
2
Funding
  • Total cost estimated QS R 864 659 644
  • Received tender price R 1 245 236 999

3
Funding
  • Funding from National Government
  • R 696 776 897.00
  • OC TT cost estimated submitted to DG 2010 R 812
    000 000.00

4
Estimated Shortfall and Progress to date
  • Estimated shortfall before process re-engineering
    R 576 299 520.00
  • Estimated shortfall after process re-engineering
    R 476 299 520.00
  • Tender closed 14/12/2006 received 3 tenders out
    of 5
  • Negotiation took place on 16/01/2007 with bidders
    to reduce cost
  • Final prices to be received on 23/01/2007.
  • Only be in a position to have the final shortfall
    on the 26/01/2006

5
Prose's re-engineering
  • Omit aluminum facade and replace with
    hand-railing
  • Downgrading of some specifications
  • Reducing number of lifts
  • Change in seating specifications
  • Requested contractors to re-look at tender
    amounts and offering potential savings and
    alternatives to reduce tender price

6
Process re-engineering (continue)
  • Reducing the number of electronic equipment
  • Alternative construction guarantees in order to
    reduce price
  • Possible saving by extending the contract period

7
Approach to development of Stadium
  • Investigation to upgrade existing stadium
  • Old stadium upgrade extra cost to project
  • R 48 000 000.00
  • Income lost of R 750 000 per year if old stadium
    was demolish.

8
Stadium Designing
  • Design be done in accordance with FIFA
    requirements
  • Use of elements that is maintenance free
  • Plans submitted to OC TT team for approval
  • Taking environmental aspect in consideration

9
Treasury view point on Escalation
  • National Treasury will express their view point
    on escalation
  • According to newspapers report
  • Steel increased by 20
  • Labour cost increase 20
  • Copper cost increase by 84

10
Reason for increasing of Tender Price
  • Material shortages
  • Skilled labour shortages
  • Shortage of skilled personnel in management
    positions
  • Pant and equipment shortages
  • Concurrent construction of stadiums
  • Importing of some material
  • Media reporting

11
Constrains MFMA
  • Funds on the budget before awarding the tender
  • Follow the MFMA guidelines for procuring the
    tender