Compaction piles - PowerPoint PPT Presentation

About This Presentation
Title:

Compaction piles

Description:

These piles are used for improving the Geo technical engineering proprties – PowerPoint PPT presentation

Number of Views:2326
Slides: 16
Provided by: yugi
Tags:

less

Transcript and Presenter's Notes

Title: Compaction piles


1
Compaction piles
  • compacted by driving piles into soil
  • Compaction achieved by simple displacement
  • For granular soil displacement vibration
  • Amount of compaction depends on
  • Spacing
  • Size
  • Vibrating energy (proportional to fine content ,lt
    20)

2
  • Compaction piles
  • Structural piles (timber / pre-cast/ concrete)
  • Fill material pile (Sand piles, gravel)
  • Structural piles densifies loose soil
  • Sand piles
  • installed by driving a hollow steel mandrel with
    a false bottom to the required depth
  • fill the mandrel with sand
  • applying air pressure to the top of the sand
    column
  • Withdraw the mandrel
  • Pore water pressure increases

3
  • Design based on
  • stability of the sand column
  • the piles and soil are subjected to equal
    vertical deformation
  • soils of low permeability below the water table-
    sand piles as drains
  • A well-compacted layer of soil is placed on top
    of the sand piles to obtain a better load
    concentration on the piles by arching

4
  • Vibro-composer method
  • driving a casing to the required depth by means
    of a vibrator.
  • A quantity of sand is then placed in the pipe
    which is partially withdrawn as compressed air is
    blown down the casing
  • Next the pipe is vibrated downwards to compact
    the sand pile.
  • The process is repeated until the ground surface
    is reached

5
Vibro composer sand piles
6
Gravel compaction piles
  • a tube closed by a plug of gravel (or zero slump
    concrete) is driven into the ground by means of a
    drop-hammer striking the plug
  • the soil is compacted radially around the tube
    while driving
  • tube _at_ design depth an expanded base is formed by
    ramming with a high-energy hammer
  • tube is then raised in lifts gravel is driven
    from the tube so forming a continuous pile of
    compacted gravel

7
(No Transcript)
8
Concrete columns
  • support structures on weak cohesive, organic or
    loose granular soils and fills
  • vibrator which contains a special hollow shoe
    that houses a tremie pipe down to which concrete
    is pumped
  • pipe is connected by hose to a trailer-mounted
    concrete pump
  • Pipe pumps concrete under pressure
  • Vibrations _at_ 3000Hz

9
  • the vibrator is withdrawn about a metre while
    pressurized concrete is tremied in at the toe
  • The vibrator is then driven back to the original
    depth to create a bulbous bearing end
  • withdrawn at a slower speed than the pumping flow
    so as to maintain pressure in the concrete column
  • Once grade level is reached the concrete is shut
    off
  • the vibrator is briefly re-immersed in the
    concrete to finish off the column

10
(No Transcript)
11
Dynamic compaction
  • repeatedly impacting the ground surface by
    dropping a pounder from a given height from a
    heavy duty crane
  • _at_ of one blow every 13 mins
  • the distances between the centres of impact
    frequently ranging between 4 and 20 m
  • set out on a grid pattern
  • The energy per blow is chosen to maximize
    penetration of the resultant stress impulses
  • Densify a wide range of soils from organic and
    silty clay to loosely packed coarse-grained soil
    sand fills 

12
  • The energy required to achieve a given result
    increases with the amount of fines in the ratio
    13 when going from coarse gravel to silty clay.
  • Compactor with Wt 200t n height 40 m can
    compact 50-60m of clayey silt
  • Vibration frequency is around 5 Hz, and usually
    lower than 12 Hz
  • The threshold vibration velocity above which
    damage may occur in buildings is normally taken
    at 50 mm/s
  • extensive site investigation must be carried out
    prior to the commencement of dynamic compaction

13
Dynamic compaction
14
  • Dynamic compaction is carried out in several
    phases 
  • spacing between the points of impact is large in
    the first pass and is reduced successively in
    subsequent ones
  • The modulus of deformation of the soil maybe
    increased by two to ten times
  • the depth of the imprint does not exceed half the
    width of the pounding mass
  • must have three or four types of tamping weights
    available on site.

15
  • After each pass the craters formed in the ground
    by tamping are filled with soil (ideally
    well-graded granular) before the next pass
  • Finally ground is given a final ironing pass in
    which the weight is dropped from 1 to 2 m at
    spacings smaller than the width of the weigh
  • saturated or partially saturated soils and soft
    peaty or organic deposits are not subjected
    to direct dynamic compaction
  • For soft clays use vertical drains to result in
    compaction
  • Small machine (a large hydraulic pile hammer
    mounted on a crawler crane) consolidates upto 4m
    for small constructions
Write a Comment
User Comments (0)
About PowerShow.com