Summary of Procurement Phase 1 Programme - PowerPoint PPT Presentation

1 / 12
About This Presentation
Title:

Summary of Procurement Phase 1 Programme

Description:

This presentation has been prepared for and only for Cheshire County Council. ... full details are available from Paul Haycock of PwC or Neil Thompson of Vendigital ... – PowerPoint PPT presentation

Number of Views:40
Avg rating:3.0/5.0
Slides: 13
Provided by: cheshi
Category:

less

Transcript and Presenter's Notes

Title: Summary of Procurement Phase 1 Programme


1
TRANSFORMING CHESHIRE
This presentation has been prepared for and only
for Cheshire County Council. We do not accept or
assume any liability or duty of care for any
other purpose or to any other person to whom this
report is shown or into whose hands it may come,
save where expressly agreed by our prior consent
in writing.
  • Summary of Procurement Phase 1 Programme
  • October 2006

2
Executive Summary
  • In November 2005, a scoping exercise was
    conducted to identify cashable savings in
    procurement
  • This set out a savings plan with spend categories
    grouped into three blocks
  • Categories of low political sensitivity in which
    quick wins could be achieved within the
    financial year 2006-07
  • Further categories to be addressed in 2006-07
  • Wider spend categories in which further scoping
    was necessary to identify potential savings
  • The work to generate savings in this first block
    of categories (agency staff, IT consumables and
    print) has now been completed. Against an
    original annualised target of 250k across the
    three categories, the following results have been
    achieved
  • Agency Staff (internal benchmarking phase 1)
    total annual saving 255k minimum, 06-07 CCC
    impact 190k
  • IT Consumables total annual saving 220k,
    06-07 CCC impact 58k
  • Print total annual saving 598k, CCC 06-07
    impact 153k (assumes implementation 01/11/06)
  • Further procurement work will form a part of the
    wider Transforming Cheshire programme, i.e. as
    part of the reviews of each council service,
    rather than as a stand-alone procurement project

3
Scoping Exercise approach
  • In November 2005 a scoping exercise was conducted
    to identify cashable savings in procurement. This
    work consumed 20 person-days of PwC consulting
    input, and around 10 person-days of Cheshire
    County Council input, and involved the following
    steps

Understand spend
  • Spend Data Data from the Spikes Cavell
    initiative previously delivered was used as the
    basis for the scoping exercise. This enabled us
    to identify and prioritise key spend areas and
    assess supplier rationalisation opportunities
  • Interviews Discussions were held with over 20
    Council officers involved in the purchasing of
    various products and services. We used these
    interviews to gain an understanding of the
    current procurement situation (suppliers,
    contracts, processes, etc.) in each key spend
    category
  • Savings opportunities We assessed the scale of
    potential savings at category level, using our
    experience of programmes undertaken with
    authorities of similar spend profile, procurement
    structure and approach. We also used our
    knowledge of market pricing and detailed analysis
    of achievable savings in commodity areas

Understand procurement situation
Understand savings opportunities
  • The results of the exercise can be found
    overleaf. Categories are split into three blocks
    quick wins in areas of low political
    sensitivity, categories to be address in
    financial year 2006-07 and longer-term categories
    in which further scoping work was necessary

4
Scoping Exercise findings
5
Results overall
  • Implementation of the initiatives in each of the
    phase 1 categories has exceeded original savings
    estimates by a significant factor
  • Savings achieved are summarised below
  • Whilst the calendar time taken to deliver these
    savings exceeded original expectations, the scale
    of savings has ensured that FY06-07 have been
    significantly surpassed. The phase 1 programme
    has also been delivered on budget with regard to
    PwC costs
  • Details of the approach and savings for each of
    these initiatives follow

722k
6
Results Agency Staff (phase 1)
  • The review of agency staff spend has two key
    phases
  • Internal benchmarking complete
  • Market tender ongoing at time of writing (Oct
    06)
  • Phase one of this work centred around analysis of
    existing procurement arrangements and rates /
    charges incurred amongst the existing supplier
    base
  • This was delivered through a series of surveys
    and interviews with users across the council.
    These examined current usage, suppliers, terms,
    rates, future requirements, processes and factors
    deemed important in the sourcing of temporary
    workers. Key findings from this analysis
    included
  • The final key finding from a potential savings
    point of view was the variance in charge rates
    incurred by council services for similar kinds of
    agency worker see overleaf

Total spend c. 5.7m p.a.
gt 115 different providers used, and limited
aggregation with individual suppliers
No audit trail of worker vetting high potential
risk
Autonomous sourcing no overall responsibility
or view of expenditure
Limited management reporting
gt 8,000 invoices processed in 12 month period
7
Results Agency Staff (phase 1)
  • An illustration of the typical variances in rates
    incurred by services is given below
  • The average variance identified was 28.8. Quick
    win savings were therefore achieved by
    establishing a preferred supplier list (PSL).
    This was created from the base of suppliers
    already used by CCC, thereby eliminating the need
    to conduct a full tender process in the short
    term
  • Developing this PSL, together with effective
    measures to monitor and ensure compliance to the
    new arrangements, identified 255k of annualised
    savings, of which 190k was agreed to impact
    FY06-07 budgets
  • It should be noted that the savings figures above
    reflect a conservative 50 compliance figure in
    the short term, accounting for the run-down of
    existing usage. Whilst this compliance rate is
    likely to increase over time, additional savings
    are likely to be superseded by those generated
    through the phase 2 market tendering work

8
Results IT Consumables
  • A full data gathering exercise was conducted to
    assess the Councils spend on IT consumables
    including data from Roses, CBS, incumbent
    suppliers and IT supplier EDS. The data were
    analysed and split into two categories of
    product Data Storage Media and IT Consumables.
    Annual spend for the two categories combined was
    around 750k p.a.
  • The e-auction took place on July 3rd 2006. 12
    bidders took part in the e-Auction including
    incumbents of the Council and other major
    suppliers. This was from an initial list of over
    200 suppliers contacted. 68 were invited to
    submit pre-qualification responses, from which 26
    qualified and were sent the Invitation to Tender
  • The auction result gave rise to a number of
    options for realising savings, based on the type
    of products selected (OEM branded or alternative
    products such as re-manufactured toner
    cartridges) and the delivery channel used (i.e.
    through central storage and distribution facility
    CBS, or direct delivery via the Roses electronic
    marketplace)
  • CCC selected the option to source alternative
    brand items, where available, from a single
    supplier XMA. Items will be sourced directly
    through Roses
  • Auction results and savings achieved can be found
    overleaf

9
Results IT Consumables
  • Savings from the implementation option selected
    were as follows
  • Total annual savings of 221k were therefore
    achieved, representing a 29 overall cost
    reduction
  • Of this total, 145k directly benefits the
    Council with the remainder comprised of
    expenditure relating to schools and external
    customers of CBS
  • In calculating FY06-07 budget reductions, CCC
    Design Authority requested that 80 of the total
    saving be used to reflect some caution around the
    immediate switch to alternative products. With an
    effective implementation date of 1st October
    2006, this gives a FY06-07 impact of 58k

10
Results Print
  • The aims of the project were to reduce overall
    print spend and consolidate the number of
    suppliers used. This was achieved through a full
    information gathering, tendering and e-auction
    project, together with structural changes to
    improve the way Cheshire Council commissions
    print work
  • Data was gathered from a number of sources,
    including invoices, CCC spend information and
    suppliers. This was then analysed and divided
    into five lots with an overall spend of
    1,014,016 per annum
  • The e-auction took place on September 4th 2006.
    33 bidders took part in the e-Auction including
    incumbents of the Council and other major
    suppliers. This was from an initial list of over
    450 suppliers contacted. 97 were invited to
    submit pre-qualification responses, from which 54
    qualified and were sent the Invitation to Tender
  • A potential total saving of over 597k is
    available to the Council by using the best
    bidders for each lot (excluding implementation
    costs). This represents a 59 reduction in
    overall spend. The auction result is summarised
    overleaf, and full details are available from
    Paul Haycock of PwC or Neil Thompson of
    Vendigital
  • In order to implement these savings, CCC is
    required to appoint a central Print Buyer. The
    role will be to commission work from the winning
    suppliers where requirements defined by Services
    meet the specifications included in the tender.
    For specifications against which suppliers have
    bid (e.g. one-offs) the role will be to
    negotiate prices with the preferred suppliers or,
    by exception, the wider marketplace

11
Results Print
  • For three of the five lots, a proportion of items
    were specifically priced by each supplier in
    their bids. The remaining tail of spend will
    also be supplier by the winning bidder for each
    lot with the same level of savings as the auction
    value
  • For all lots, each supplier was rated against
    non-price criteria such as service / delivery
    levels, quality offered, management reporting,
    environmental factors etc. The auction then
    ranked each suppliers according to their total
    score comprising 50 price and 50 non-price
    criteria
  • The savings achieved, excluding implementation
    costs, through the auction were as follows
  • Therefore, from a total annual spend of
    1,014,016, the auction identified a total saving
    of 597,794, representing 59 of total spend
  • With the deal and commissioning arrangement
    coming into place on 1 November 2006, CCC will
    benefit from five months savings in FY06-07
    229,081 (adjustment made for implementation
    costs, i.e. print buyers, recruited internally)

12
Next Steps
  • A statement of work was compiled for phase 2 of
    the procurement programme. This covered the next
    stage of work around agency staff, a number of
    quick win initiatives in the councils social
    care spend, plus further scoping in the areas of
    IT telecoms and advertising. This approach and
    the required funding were approved by Members in
    May 06
  • However, as a result of developments in the
    overall Transforming Cheshire programme, we have
    agreed to continue only with the agency staff
    work. This follows on from the phase 1 work to
    address the potential for improved rates in the
    marketplace, following the Competitive Dialogue
    tendering process
  • Other procurement opportunities both scheduled
    for phase 2 and in further spend areas will be
    addressed as part of the wider review of all
    council services in the Transforming Cheshire
    programme. This means that the Procurement
    programme will cease to be a stand-alone project,
    and will be subsumed into the wider programme
Write a Comment
User Comments (0)
About PowerShow.com