Title: Summary of Procurement Phase 1 Programme
1TRANSFORMING CHESHIRE
This presentation has been prepared for and only
for Cheshire County Council. We do not accept or
assume any liability or duty of care for any
other purpose or to any other person to whom this
report is shown or into whose hands it may come,
save where expressly agreed by our prior consent
in writing.
- Summary of Procurement Phase 1 Programme
- October 2006
2Executive Summary
- In November 2005, a scoping exercise was
conducted to identify cashable savings in
procurement - This set out a savings plan with spend categories
grouped into three blocks - Categories of low political sensitivity in which
quick wins could be achieved within the
financial year 2006-07 - Further categories to be addressed in 2006-07
- Wider spend categories in which further scoping
was necessary to identify potential savings - The work to generate savings in this first block
of categories (agency staff, IT consumables and
print) has now been completed. Against an
original annualised target of 250k across the
three categories, the following results have been
achieved - Agency Staff (internal benchmarking phase 1)
total annual saving 255k minimum, 06-07 CCC
impact 190k - IT Consumables total annual saving 220k,
06-07 CCC impact 58k - Print total annual saving 598k, CCC 06-07
impact 153k (assumes implementation 01/11/06) - Further procurement work will form a part of the
wider Transforming Cheshire programme, i.e. as
part of the reviews of each council service,
rather than as a stand-alone procurement project
3Scoping Exercise approach
- In November 2005 a scoping exercise was conducted
to identify cashable savings in procurement. This
work consumed 20 person-days of PwC consulting
input, and around 10 person-days of Cheshire
County Council input, and involved the following
steps
Understand spend
- Spend Data Data from the Spikes Cavell
initiative previously delivered was used as the
basis for the scoping exercise. This enabled us
to identify and prioritise key spend areas and
assess supplier rationalisation opportunities - Interviews Discussions were held with over 20
Council officers involved in the purchasing of
various products and services. We used these
interviews to gain an understanding of the
current procurement situation (suppliers,
contracts, processes, etc.) in each key spend
category - Savings opportunities We assessed the scale of
potential savings at category level, using our
experience of programmes undertaken with
authorities of similar spend profile, procurement
structure and approach. We also used our
knowledge of market pricing and detailed analysis
of achievable savings in commodity areas
Understand procurement situation
Understand savings opportunities
- The results of the exercise can be found
overleaf. Categories are split into three blocks
quick wins in areas of low political
sensitivity, categories to be address in
financial year 2006-07 and longer-term categories
in which further scoping work was necessary
4Scoping Exercise findings
5Results overall
- Implementation of the initiatives in each of the
phase 1 categories has exceeded original savings
estimates by a significant factor - Savings achieved are summarised below
- Whilst the calendar time taken to deliver these
savings exceeded original expectations, the scale
of savings has ensured that FY06-07 have been
significantly surpassed. The phase 1 programme
has also been delivered on budget with regard to
PwC costs - Details of the approach and savings for each of
these initiatives follow
722k
6Results Agency Staff (phase 1)
- The review of agency staff spend has two key
phases - Internal benchmarking complete
- Market tender ongoing at time of writing (Oct
06) - Phase one of this work centred around analysis of
existing procurement arrangements and rates /
charges incurred amongst the existing supplier
base - This was delivered through a series of surveys
and interviews with users across the council.
These examined current usage, suppliers, terms,
rates, future requirements, processes and factors
deemed important in the sourcing of temporary
workers. Key findings from this analysis
included - The final key finding from a potential savings
point of view was the variance in charge rates
incurred by council services for similar kinds of
agency worker see overleaf
Total spend c. 5.7m p.a.
gt 115 different providers used, and limited
aggregation with individual suppliers
No audit trail of worker vetting high potential
risk
Autonomous sourcing no overall responsibility
or view of expenditure
Limited management reporting
gt 8,000 invoices processed in 12 month period
7Results Agency Staff (phase 1)
- An illustration of the typical variances in rates
incurred by services is given below - The average variance identified was 28.8. Quick
win savings were therefore achieved by
establishing a preferred supplier list (PSL).
This was created from the base of suppliers
already used by CCC, thereby eliminating the need
to conduct a full tender process in the short
term - Developing this PSL, together with effective
measures to monitor and ensure compliance to the
new arrangements, identified 255k of annualised
savings, of which 190k was agreed to impact
FY06-07 budgets - It should be noted that the savings figures above
reflect a conservative 50 compliance figure in
the short term, accounting for the run-down of
existing usage. Whilst this compliance rate is
likely to increase over time, additional savings
are likely to be superseded by those generated
through the phase 2 market tendering work
8Results IT Consumables
- A full data gathering exercise was conducted to
assess the Councils spend on IT consumables
including data from Roses, CBS, incumbent
suppliers and IT supplier EDS. The data were
analysed and split into two categories of
product Data Storage Media and IT Consumables.
Annual spend for the two categories combined was
around 750k p.a. - The e-auction took place on July 3rd 2006. 12
bidders took part in the e-Auction including
incumbents of the Council and other major
suppliers. This was from an initial list of over
200 suppliers contacted. 68 were invited to
submit pre-qualification responses, from which 26
qualified and were sent the Invitation to Tender - The auction result gave rise to a number of
options for realising savings, based on the type
of products selected (OEM branded or alternative
products such as re-manufactured toner
cartridges) and the delivery channel used (i.e.
through central storage and distribution facility
CBS, or direct delivery via the Roses electronic
marketplace) - CCC selected the option to source alternative
brand items, where available, from a single
supplier XMA. Items will be sourced directly
through Roses - Auction results and savings achieved can be found
overleaf
9Results IT Consumables
- Savings from the implementation option selected
were as follows - Total annual savings of 221k were therefore
achieved, representing a 29 overall cost
reduction - Of this total, 145k directly benefits the
Council with the remainder comprised of
expenditure relating to schools and external
customers of CBS - In calculating FY06-07 budget reductions, CCC
Design Authority requested that 80 of the total
saving be used to reflect some caution around the
immediate switch to alternative products. With an
effective implementation date of 1st October
2006, this gives a FY06-07 impact of 58k
10Results Print
- The aims of the project were to reduce overall
print spend and consolidate the number of
suppliers used. This was achieved through a full
information gathering, tendering and e-auction
project, together with structural changes to
improve the way Cheshire Council commissions
print work - Data was gathered from a number of sources,
including invoices, CCC spend information and
suppliers. This was then analysed and divided
into five lots with an overall spend of
1,014,016 per annum - The e-auction took place on September 4th 2006.
33 bidders took part in the e-Auction including
incumbents of the Council and other major
suppliers. This was from an initial list of over
450 suppliers contacted. 97 were invited to
submit pre-qualification responses, from which 54
qualified and were sent the Invitation to Tender - A potential total saving of over 597k is
available to the Council by using the best
bidders for each lot (excluding implementation
costs). This represents a 59 reduction in
overall spend. The auction result is summarised
overleaf, and full details are available from
Paul Haycock of PwC or Neil Thompson of
Vendigital - In order to implement these savings, CCC is
required to appoint a central Print Buyer. The
role will be to commission work from the winning
suppliers where requirements defined by Services
meet the specifications included in the tender.
For specifications against which suppliers have
bid (e.g. one-offs) the role will be to
negotiate prices with the preferred suppliers or,
by exception, the wider marketplace
11Results Print
- For three of the five lots, a proportion of items
were specifically priced by each supplier in
their bids. The remaining tail of spend will
also be supplier by the winning bidder for each
lot with the same level of savings as the auction
value - For all lots, each supplier was rated against
non-price criteria such as service / delivery
levels, quality offered, management reporting,
environmental factors etc. The auction then
ranked each suppliers according to their total
score comprising 50 price and 50 non-price
criteria - The savings achieved, excluding implementation
costs, through the auction were as follows - Therefore, from a total annual spend of
1,014,016, the auction identified a total saving
of 597,794, representing 59 of total spend - With the deal and commissioning arrangement
coming into place on 1 November 2006, CCC will
benefit from five months savings in FY06-07
229,081 (adjustment made for implementation
costs, i.e. print buyers, recruited internally)
12Next Steps
- A statement of work was compiled for phase 2 of
the procurement programme. This covered the next
stage of work around agency staff, a number of
quick win initiatives in the councils social
care spend, plus further scoping in the areas of
IT telecoms and advertising. This approach and
the required funding were approved by Members in
May 06 - However, as a result of developments in the
overall Transforming Cheshire programme, we have
agreed to continue only with the agency staff
work. This follows on from the phase 1 work to
address the potential for improved rates in the
marketplace, following the Competitive Dialogue
tendering process - Other procurement opportunities both scheduled
for phase 2 and in further spend areas will be
addressed as part of the wider review of all
council services in the Transforming Cheshire
programme. This means that the Procurement
programme will cease to be a stand-alone project,
and will be subsumed into the wider programme