Managing%20Risks%20in%20Projects - PowerPoint PPT Presentation

About This Presentation
Title:

Managing%20Risks%20in%20Projects

Description:

The Impact of the Event if it does Occur. Risk = f (likelihood, impact) ... Bonaparte's Principle came along before Murphy's Laws, i.e., 'Something Surely ... – PowerPoint PPT presentation

Number of Views:25
Avg rating:3.0/5.0
Slides: 26
Provided by: angel101
Category:

less

Transcript and Presenter's Notes

Title: Managing%20Risks%20in%20Projects


1
Managing Risks in Projects
2
Risk Concepts
  • The Likelihood that some Problematical Event will
    Occur
  • The Impact of the Event if it does Occur
  • Risk f (likelihood, impact)
  • Project is considered Risky if at least One
    Factor is large

3
Risk Identification
  • Risk Tolerance is a Function of Experience
  • PM
  • Stakeholders
  • Risk of Failure
  • Schedule
  • Budget
  • Technical Goals
  • Risk of Opportunity
  • Rewards
  • Savings
  • Benefits

4
Risk Identification (Continued)
  • Ways to Identify Project Risk
  • Chronology
  • Type of Work
  • High Risks
  • Approach is New/Unusual
  • Technology is New/Unusual
  • Staff needs Training in New Tasks/Skills
  • Process using New Equipment, Systems or Procedures

5
Sources of Risk
  • Any Factor of uncertain Probability which can
    affect the Outcome is of a Project is a
  • Risk Source
  • Risk Hazard

6
Sources of Risk (Continued)
  • Internal Risks
  • Market Risk
  • Ill Defined Market or Customer needs and
    Requirements
  • Failure to Identify Changing Needs and
    Requirements
  • Failure to identify Newly Introduced Products by
    Competitors
  • Technical Risk
  • Maturity
  • Complexity
  • Quality
  • Concurrency, or Dependency

7
Sources of Risk (Continued)
  • External Risks,
  • Market Conditions
  • Competitors Actions
  • Government Regulations
  • Interest Rates
  • Decisions by Sr. Mgmt or Customer
  • Budgets
  • Staffing
  • Priorities

8
Sources of Risk (Continued)
  • External Risks (Continued)
  • Customer Needs and Behavior
  • Supplier Relations
  • Weather
  • Labour Troubles
  • Material or Labor
  • External Control by Customers or Subcontractors

9
Risk Assessment
  • Risk Likelihood
  • Probability a Hazard or Risk Factor will
    Materialize
  • Numerical Value between 1.0 (Certain) and 0
    (Impossible)
  • Qualitative Rating
  • High Greater than 50
  • Medium 20 to 50
  • Low 20 or Less
  • Composite Likelihood Factor (CLF)
  • Sum of Multiple, Independent Risk Sources

10
Risk Assessment(Continued)
  • Risk Impact
  • What Happens if a Risk Hazard Materialized
  • Specified in Terms of
  • Time
  • Cost
  • Performance Measures
  • Qualitative
  • High
  • Medium
  • Low

11
Risk Assessment(Continued)
  • Risk Impact (Continued)
  • Numerical Measure Between 0 and 1.0
  • 0 not Serious
  • 1.0 Catastrophic

12
Risk Assessment(Continued)
  • Risk Consequence
  • Function or Likelihood and Impact
  • Can be Expressed as Numerical rating between 0
    and 1.0
  • Risk Consequence Rating (RCR)
  • RCR CLF CIF - CLF(CIF)
  • Can be Expressed as an Expected Value or the
    Average Outcome for large Tries
  • Risk Consequence (Impact) x (Likelihood)

13
Risk Assessment(Continued)
  • PERT
  • Incorporates Risk through the three Estimates for
    Each Project Activity
  • a, Optimistic
  • m, Most Likely
  • b, Pessimistic
  • Use a larger value of b to account for Greater
    Risk
  • This Produces a larger Variance for Project
    Completion Time (Add buffer Time to Project)
  • PERT Provides a Way for Measuring the
    Consequences of Risk on Project Completion Times

14
Risk Assessment(Continued)
  • Risk Priority
  • PM must Define a Risk Tolerance Level
  • Consider Risks at that Level and Higher
  • Team Members Review all these Tasks and Make
    Recommendations
  • In Complex Systems Joint Failures Can Occur

15
Risk Response Planning How to Deal with the
Problem
  • Transfer the Risk
  • Avoid Risk
  • Reduce Risk
  • Contingency Planning
  • Accept Risk (Do Nothing)

16
Risk Likelihood, Risk Impact, and Expected Value
Consequences
17
Avoid Risk
  • Alter the Initial Project Concept
  • Eliminate Risky Activities
  • Minimize System Complexity
  • Reduce End-Item Quality Requirements
  • Change Contractors
  • Incorporate Redundancies
  • Change Safety Procedures
  • Better to Reduce Risk to Acceptable Level Than
    Eliminate Payoff Opportunity

18
Reduce RiskTechnical Performance
  • Reduce System Complexity to a Minimum
  • Reorganize Tasks
  • End Item Design
  • Decouple Activities
  • Contains Failure to one Activity
  • Use Design Margins
  • A Management Reserve
  • Design Value is Greater than Design Requirement

19
Reduce RiskMeeting Schedules
  • Create Master Project Schedule
  • Schedule Risky Tasks Early to Allow Time to
    Recover
  • Focus on Critical and Near-Critical Activities
  • Path
  • Risk
  • Best People on Time-Critical Tasks

20
Reduce RiskMeeting Schedules (Continued)
  • Incentives for OT
  • Compensated Salary
  • Compensated Time
  • Do High Risk Activities in the Project Network in
    Parallel
  • Organize Project Early with Adequate Staff

21
Reduce RiskMeeting Project Cost
  • Identify and Monitor Cost Drivers
  • Perform Design Alternative Reviews and
    Assessments
  • Validate System Design and Performance
  • Modeling
  • Assessment

22
Accept Risk (Do Nothing)
  • Not All Risks are Severe or Fatal
  • Cost Benefit Analysis
  • Not for Risks which are Potentially Severe

23
Risk Management is Project Management
  • Another Tool for PM
  • Supplements
  • Requirements Definition
  • Task Definition
  • Scheduling
  • Budgeting
  • Configuration Management
  • Change Control
  • Performance Tracking and Control

24
Expect the Unexpected
  • Do All You Can
  • Cannot Cover Every Contingency
  • Bonapartes Principle came along before Murphys
    Laws, i.e., Something Surely Will Go Wrong Plan
    for It to Occur

25
Risk Analysis Methods
  • Expected Value
  • Decision Trees
  • Uncertainty and Payoff Tables
  • Simulations
Write a Comment
User Comments (0)
About PowerShow.com