Title: Managing%20Risks%20in%20Projects
1Managing Risks in Projects
2Risk Concepts
- The Likelihood that some Problematical Event will
Occur - The Impact of the Event if it does Occur
- Risk f (likelihood, impact)
- Project is considered Risky if at least One
Factor is large
3Risk Identification
- Risk Tolerance is a Function of Experience
- PM
- Stakeholders
- Risk of Failure
- Schedule
- Budget
- Technical Goals
- Risk of Opportunity
- Rewards
- Savings
- Benefits
4Risk Identification (Continued)
- Ways to Identify Project Risk
- Chronology
- Type of Work
- High Risks
- Approach is New/Unusual
- Technology is New/Unusual
- Staff needs Training in New Tasks/Skills
- Process using New Equipment, Systems or Procedures
5Sources of Risk
- Any Factor of uncertain Probability which can
affect the Outcome is of a Project is a - Risk Source
- Risk Hazard
6Sources of Risk (Continued)
- Internal Risks
- Market Risk
- Ill Defined Market or Customer needs and
Requirements - Failure to Identify Changing Needs and
Requirements - Failure to identify Newly Introduced Products by
Competitors - Technical Risk
- Maturity
- Complexity
- Quality
- Concurrency, or Dependency
7Sources of Risk (Continued)
- External Risks,
- Market Conditions
- Competitors Actions
- Government Regulations
- Interest Rates
- Decisions by Sr. Mgmt or Customer
- Budgets
- Staffing
- Priorities
8Sources of Risk (Continued)
- External Risks (Continued)
- Customer Needs and Behavior
- Supplier Relations
- Weather
- Labour Troubles
- Material or Labor
- External Control by Customers or Subcontractors
9Risk Assessment
- Risk Likelihood
- Probability a Hazard or Risk Factor will
Materialize - Numerical Value between 1.0 (Certain) and 0
(Impossible) - Qualitative Rating
- High Greater than 50
- Medium 20 to 50
- Low 20 or Less
- Composite Likelihood Factor (CLF)
- Sum of Multiple, Independent Risk Sources
10Risk Assessment(Continued)
- Risk Impact
- What Happens if a Risk Hazard Materialized
- Specified in Terms of
- Time
- Cost
- Performance Measures
- Qualitative
- High
- Medium
- Low
11Risk Assessment(Continued)
- Risk Impact (Continued)
- Numerical Measure Between 0 and 1.0
- 0 not Serious
- 1.0 Catastrophic
12Risk Assessment(Continued)
- Risk Consequence
- Function or Likelihood and Impact
- Can be Expressed as Numerical rating between 0
and 1.0 - Risk Consequence Rating (RCR)
- RCR CLF CIF - CLF(CIF)
- Can be Expressed as an Expected Value or the
Average Outcome for large Tries - Risk Consequence (Impact) x (Likelihood)
13Risk Assessment(Continued)
- PERT
- Incorporates Risk through the three Estimates for
Each Project Activity - a, Optimistic
- m, Most Likely
- b, Pessimistic
- Use a larger value of b to account for Greater
Risk - This Produces a larger Variance for Project
Completion Time (Add buffer Time to Project) - PERT Provides a Way for Measuring the
Consequences of Risk on Project Completion Times
14Risk Assessment(Continued)
- Risk Priority
- PM must Define a Risk Tolerance Level
- Consider Risks at that Level and Higher
- Team Members Review all these Tasks and Make
Recommendations - In Complex Systems Joint Failures Can Occur
15Risk Response Planning How to Deal with the
Problem
- Transfer the Risk
- Avoid Risk
- Reduce Risk
- Contingency Planning
- Accept Risk (Do Nothing)
16Risk Likelihood, Risk Impact, and Expected Value
Consequences
17Avoid Risk
- Alter the Initial Project Concept
- Eliminate Risky Activities
- Minimize System Complexity
- Reduce End-Item Quality Requirements
- Change Contractors
- Incorporate Redundancies
- Change Safety Procedures
- Better to Reduce Risk to Acceptable Level Than
Eliminate Payoff Opportunity
18Reduce RiskTechnical Performance
- Reduce System Complexity to a Minimum
- Reorganize Tasks
- End Item Design
- Decouple Activities
- Contains Failure to one Activity
- Use Design Margins
- A Management Reserve
- Design Value is Greater than Design Requirement
19Reduce RiskMeeting Schedules
- Create Master Project Schedule
- Schedule Risky Tasks Early to Allow Time to
Recover - Focus on Critical and Near-Critical Activities
- Path
- Risk
- Best People on Time-Critical Tasks
20Reduce RiskMeeting Schedules (Continued)
- Incentives for OT
- Compensated Salary
- Compensated Time
- Do High Risk Activities in the Project Network in
Parallel - Organize Project Early with Adequate Staff
21Reduce RiskMeeting Project Cost
- Identify and Monitor Cost Drivers
- Perform Design Alternative Reviews and
Assessments - Validate System Design and Performance
- Modeling
- Assessment
22Accept Risk (Do Nothing)
- Not All Risks are Severe or Fatal
- Cost Benefit Analysis
- Not for Risks which are Potentially Severe
23Risk Management is Project Management
- Another Tool for PM
- Supplements
- Requirements Definition
- Task Definition
- Scheduling
- Budgeting
- Configuration Management
- Change Control
- Performance Tracking and Control
24Expect the Unexpected
- Do All You Can
- Cannot Cover Every Contingency
- Bonapartes Principle came along before Murphys
Laws, i.e., Something Surely Will Go Wrong Plan
for It to Occur
25Risk Analysis Methods
- Expected Value
- Decision Trees
- Uncertainty and Payoff Tables
- Simulations