Title: Commissioning of BLM system
1Commissioning of BLM system
L. Ponce With the contribution of B. Dehning,
E.B. Holzer, M. Sapinski, C. Zamantzas and all
BLM team
2Outlines
- Overview of the BLM system
- Principle of the simulations
- Strategy for BLM positioning and the thresholds
settings - Signal available
- hardware commissioning
- commissioning with beam
- conclusions
3BLM for machine protection
- The only system to protect LHC from fast losses
(between 0.4 and 10 ms) - The only system to prevent quench
- dynamic range 102 -1010 MIPs/(cm2s)
BLM
BLM QPS
damage
BLM
Quench
4BLM system Detector
- about 3600 ionisation chambers 310 Secondary
EMission detectors - measure the secondary shower outside the
cryostats created by the losses - dynamic range 108 (or 1013 with SEM)
corresponding to few pA to 25 A
Ionisation chamber Diameter 8.9 cm, Length 60
cm, 1.5 litre, Filled with N2
SEM Diameter 8.9 cm Length 15 cm
5BLM system signal chain
- 8 channels per tunnel card, 2 tunnel cards per
surface card and 335 surface cards - 12 integration periods and 32 energy level per
channel ( per monitor) - signal over the thresholds generate a beam dump
request via the BIC - Some channels can be maskable with the Safe_Beam
flag
6Simulation loss locations
- Loss pattern given by R. Assmann team (C. Bracco,
S. Redaelli, G. Robert-Demolaize) Example
(MQ27.R7) - Peak before MQ at the shrinking vacuum pipe
location (aperture limit effect) - End of loss at the centre of the MQ (beam size
effect)
7Simulation geometry description
- GEANT 3 simulation of the secondaries shower
created by a lost proton impacting the beam pipe - simulation of the detector response to the
spectra registered in the left and right detector
(M. Stockner with G4) - 500 protons same z position and same energy
- Typical impacting angle is 0.25 mrad
- longitudinal scan performed for primary impact to
optimize the BLM location
Top view
8Simulation typical result
Longitudinal distribution of the secondaries
outside the cryostat in DS for different loss
location (z)
- Maximum of the shower 1m after impacting point
in material - increase of the signal in magnet free locations
- factor 2 between MQ and MB
z (cm)
9Simulation Particle Shower in the Cryostat
example of MQ27R7 signal for each location given
by the loss map (red) and sum signal (black)
Position of the detectors optimized to
- catch the losses
- MB-MQ transition
- Middle of MQ
- MQ-MB transition
- minimize uncertainty of ratio of deposited energy
in the coil and in the detector - B1-B2 descrimination
10Strategy BLM for quench prevention
beam 1
beam 2
- At each Quads, 3 monitors per beam 2 aperture
limitation middle - positions as much standardized as possible
(integration problems) same procedure for quads
in LSS - to define families of monitors (about 250)
- Beam dump threshold set to 30 of the quench
level (to be discussed with the uncertainty on
quench level knowledge)
11(No Transcript)
12 Strategy BLM for warm elements
beam 2
top view
collimator
TDI
beam 1
- BLM in LSS at collimators, warm magnets, MSI,
MSD, MKD,MKB, all the masks - Beam dump threshold set to 10 of equipment
damage level (need equipments experts to set the
correct values) - Simulation from FLUKA team for IR7 and IR6, from
MARS for IR3
13Generation of threshold table
- Quench and damage level threshold tables will be
created for each family of BLM locations. - They will be assembled together into MASTER table
(damage or quench threshold vs beam energy and
integration time) - For every location a threshold for 7 TeV beam
will be calculated (seed for parameterization). - Table will be filled from the seed using
parameterized dependence of quench level on
Energy and Integration time. - MASTER table, MAPPING table (BLM location vs
electronic channel) will be stored in LSA
database.
14Calibration and Verification of Models
- Simulation is needed for
- secondaries shower simulation
- magnet quench (dependance with beam energy,
duration, magnet types, 2 dim...) - detector response
- Verification
- measurements of the tails of the secondary shower
with BLM on HERA dump comparison with G4
simulation (still to validate, M. Stockner) - quench tests campaign in SM18 for quench magnet
model verification (steady state losses) (D.
Bocian, A. Siemko) - detector model checked with the CERN/H6
experiment (M. Stockner PhD thesis)
15 Proposed implementation
LSA
- Threshold GUI
- Reads the master table
- Applies a factor to a family (lt1)
- Saves new table to DB
- Sends new table to CPU
- CPU flashes table if allowed (on-board switch)
- Thresholds are loaded from the memory on the
FPGA at boot. - Combiner initiated test allows CPU to read
current table. - Concentrator receives all tables
- Compares tables
- Notifies BIS (if needed)
- -gt Details of implementation under discussion
16Consequences on the reliability of the system?
- Flexibility given by changing remotely the
thresholds has to be balanced with the loss of
reliability of the system - Possibility to scale the thresholds by families
(to be discussed which families and who can
define it) - The proposed implementation allows both
possibilities - But the remote access will have to be validated
by machine protection experts when more detailed
implementation of MCS and comparator are
available (by the beginning of summer?).
17BLM system signals available
- 12 running sums (40 µs to 84 s) to cover the loss
duration and 32 energy levels used for filling
different buffers - logging at 1 Hz, max loss rate in each running
sums over the last second corresponding quench
levels error and status from tests - Post-Mortem study data the last 1.7 s with a
40 µs sample rate (43690 values) the last 2 min
of the logging data thresholds and masking
tables system status info - XPOC possible to get up to 32000 values per
channel for the chosen running sum (need to be
specified by LBDS) - Collimation on request, 32 consecutive sums of
2,54 ms
18Fixed Display in the CCC
- Used thresholds values (change with energy)
- Loss signals
- Max values of integration intervals between 40
us and 84s updated every 1 s - Values normalised to the used thresholds or in
Gy? - BLM concentrated by quad?
- If decided, possibility to scale the thresholds
table by a factor Flt1, by families
19Other uses of BLM
- Mobile BLM
- Same Ionisation Chambers
- use the spare channels per card 2 in the arcs
at each quad, a bit more complicated in the LSS
because of more elements. - electronics is commissioned as for connected
channel - a separate Fixed display for non-active channels
is planned to be discussed - No dump thresholds
- BLM for ions
- same hardware, same electronics, same thresholds
as for protons (simulation from R. Bruce) - some more specific loss locations on dipoles in
DS and arcs of IR7 and 3 (G. Bellodi, H. Braun),
cells 11 13 in IR1 and IR5, cells 10 12 in IR
2 (BFPP, J. Jowett and S. Gilardoni)
20Status of the system
- Hardware IC on time for LHC start-up, SEM
delivery in summer - Installation sector 7-8 done (cables missing in
7 left), sector 4-5 half done (delayed due to
LHC schedule), 8-1 started - Acquisition system continuously running at HERA,
post-mortem collimation data check at
collimator MD - Threshold comparator software and combiner card
(first version done) to be implemented - Fixed display in CCC to be completed by CO
- Threshold tables generation start to specify
and implement - post-mortem database and analysis still to be
defined - Extensive software tools for data analysis
(essential to fulfill the specification). Start
now to specify and implement
21Hardware commissioning
- complete detailed procedure documented in MTF
- functionalities linked with Machine protection
will be reviewed in the Machine Protection System
Commissioning Sub-Working Group - validation of the connectivity topology
registration in database of the link between
position in the tunnel-channel identification-thre
sholds - Radiation source check (moving in the tunnel)
22BLM Testing Procedures
Ph D thesis G.Guaglio
Detector
Tunnel electronics
Surface electronics
Combiner
Functional tests
Barcode check
Current source test (last installation step)
Radioactive source test (before start-up)
HV modulation test (implemented)
Beam inhibit lines tests
Threshold table beam inhibit test (under
discussion)
10 pA test
Double optical line comparison (implemented)
Thresholds table and channel assignment SW checks
Inspection frequency Reception
Installation and yearly maintenance
Before (each) fill Parallel with
beam
23Commissioning with beam
see presentation of A. Koschik in CHAMONIX 06
- Motivation of the test
- Verification of the correlation between energy
deposition in the coil ( quench level) and BLM
signal ( thresholds) - Verify or establish real-life quench levels
- Verify simulated BLM signal and loss patterns
- gt Accurately known quench levels will increase
operational efficiency! - simple idea steer beam into aperture and cause
magnet quench - possibility to check steady state losses quench
limit with circulating beam (part of the MPS
commissioning) - possibility to check fast losses quench behavior
if sector test
24Conditions for a quench test
- Requirements
- Pilot beam 5x109
- Clean conditions, orbit corrected (to better /-
3 mm?) need to know impact position and length
for determination of the lost proton density - BPM data/logging available -gt Trajectory
- BLM data/logging available
- Up to 6 additional mobile BLMs at the chosen
locations
Vary intensity5x109 max. 1x1011logging all
relevant data (BPM, BLM,BCT,emittance )
Set optics (3-bump)
Magnet quench
25Summary
- BLM system designed to be reliable and cover the
specification of machine protection and quench
prevention - Unique hardware and software for all spec to easy
maintenance - Controlled, defined test with beam is essential
for an early verification of the BLM system, even
if beam time consuming - Absolute quench limits and BLM threshold values
- Model and understanding of correlation of loss
pattern, quench level, BLM signal - Remote access to the thresholds table has still
to be approved by machine protection experts - Specification of families to scale has to be
defined (OP)