Title: Regional Transmission Adequacy Guidelines


1
Regional Transmission Adequacy Guidelines
  • Non-Wires Round Table
  • March 2006

2
Regional Transmission Adequacy Guidelines
  • Transmission Adequacy Steering Committee approved
    guidelines for N-2 outages
  • Guideline is for Facilities 230 kV and below
  • breaker failure
  • common tower outages
  • 500 kV and 345 kV main grid is covered by
    WECC/NERC

3
Regional Transmission Adequacy Guidelines
  • Transmission Adequacy Steering Committee approved
    guidelines for N-2 outages
  • Controlled load shedding up to 100 MW or 50 of
    total local area load is allowed
  • Above 100 MW or 50 of total local area load
  • Identify solutions and associated cost
  • Make cost effective fixes
  • Planned and Controlled load shedding up to 300 MW
    is acceptable if solutions are not cost effective
  • Document findings
  • Above 300 MW of total local area load
  • Societal Cost/Benefit Analysis to determine
    whether to implement solution beyond planned and
    controlled load shedding
  • Document findings

4
Regional Transmission Adequacy Guidelines
  • Regional N-2 Guidelines
  • For N-2 breaker failures and common tower outages
  • Assumes load forecast of 1 in 2 years
  • No load loss beyond the intended local load area
  • No cascading
  • Apply prudent utility practice
  • Guidelines are voluntary

5
Regional Transmission Adequacy Guidelines
Motion to Approve Guidelines for N-2 as
stated Motion passed 8-0 with 3 abstain (and no
votes against)
  • YES VOTES Eight
  • Puget Sound Energy
  • PGE-Power Supply
  • Powerex
  • Tacoma City Light
  • Snohomish PUD
  • PacifiCorp
  • Seattle City Light
  • BPA TBL

6
Regional Transmission Adequacy Guidelines Next
Steps
  • Transmission Adequacy Steering Committee
  • Jan. 17 Approval of TAG for N-2
  • Future work continue work on remaining issues
    to be addressed
  • N-2 common corridor outages
  • N-1(adjusted)-1 for load area
  • RAS
  • Transfers Vs Load Areas
  • Feb. 17 TAWG/TASC meeting
  • BPA
  • March Open BPA comment period
  • Provide briefings to existing regional forums
    (utility, tribal, constituent, legislative, etc.)
  • April BPA decision on adopting guidelines to
    standards
  • April/May Begin implementation if approved