PROJECT SCHEDULING - PowerPoint PPT Presentation

1 / 25
About This Presentation
Title:

PROJECT SCHEDULING

Description:

Plumbing. Electrical. Clearing. Grading. Pour Slab. Frame slab. Pour. Finish. MGMT 360 - Ops Management ... NETWORK DIAGRAMS. 1. 3. 2. 6. 4. 5. 7. MGMT 360 ... – PowerPoint PPT presentation

Number of Views:19
Avg rating:3.0/5.0
Slides: 26
Provided by: marksp4
Category:

less

Transcript and Presenter's Notes

Title: PROJECT SCHEDULING


1
PROJECT SCHEDULING
  •  Projects Vs. Conventional Manufacturing
  •   
  • Project Scheduling Techniques
  • Identifying Critical Paths
  • The Critical Path Method
  • Crashing and Simulating

2
PROJECTS VS. CONVENTIONAL MANUFACTURING SERVICE
  • Projects are complex, one-of-a kind
    ,non-repetitive operations
  • Building construction
  • Engineering design
  • Marketing
  • New software installation
  • Projects have a beginning, a list of interrelated
    tasks, and (one hopes) an end

3
WORK BREAKDOWN STRUCTURES
  • To identify all elements of a project, a work
    breakdown structure breaks down the big picture
    into component tasks

4
PROJECT MANAGEMENT
  • Since many different but interdependent tasks
    need to be performed on a project . . .
  • A project team is formed with members from
    different functional areas
  • The project manager's job is to plan and
    coordinate the different tasks
  • Project scheduling techniques enable the project
    manager to plan, identify, and monitor the
    project's most critical tasks

5
PROJECT SCHEDULING TECHNIQUES
  • The first step in project scheduling is to
  • Identify each task i
  • Estimate its duration ti
  • Determine the precedence among the tasks
  • This information can be represented in 'network'
    form
  • Nodes represent activities/tasks (Activity on
    Node)
  • Arcs represent precedence among tasks
  • Activity A is a predecessor of activity B
  • Activity B is a successor of activity A

6
NETWORK DIAGRAMS
7
IDENTIFYING CRITICAL TASKS
  • The project manager needs to know
  • The earliest possible finish time for the project
  • The "critical path" of activities whose delay
    would delay the entire project
  • How much slack time exists for each non-critical
    activity
  • To answer these questions, the project manager
    must determine the following times for each
    activity
  • ESi -- early start time -- earliest time activity
    i can be started
  • EFi -- early finish time -- earliest time
    activity i can be finished
  • LSi -- late start time -- latest time activity i
    can be started without delaying the project
  • LFi -- late finish time -- latest time activity i
    can be started without delaying the project

8
THE CRITICAL PATH METHOD
  • The Critical Path Method (CPM) is an algorithm
    used to identify these times
  • 1) Assign a time (usually 0) to the ES of the
    first activity
  • 2) The forward pass. Proceeding from left to
    right through the project network, determine ES
    and EF as follows
  • Where "pred(i)" All immediate predecessors of
    activity i

9
CPM THE FORWARD PASS
10
CPM THE FORWARD PASS
11
CPM THE FORWARD PASS
12
CPM THE FORWARD PASS
13
CPM THE FORWARD PASS
14
CPM THE FORWARD PASS
15
CPM THE FORWARD PASS
16
THE CRITICAL PATH METHOD
  • The earliest finish time for the project has now
    been identified.
  • A backward pass is necessary to identify the
    critical tasks
  • 3) set LF EF for the last activity
  • 4) The backward pass. Proceeding from right to
    left through the network, determine LS and LF as
    follows
  • Where succ(i)" All immediate successors of
    activity i

17
CPM THE BACKWARD PASS
18
CPM THE BACKWARD PASS
19
CPM THE BACKWARD PASS
20
CPM THE BACKWARD PASS
21
CPM THE BACKWARD PASS
22
CPM THE BACKWARD PASS
23
CPM THE BACKWARD PASS
24
THE CRITICAL PATH
  • We may now find the total slack of each activity
    using either early or late start and finish times
  • Activities with no slack are on the critical path

25
CRASHING, PROBABILITIES, AND SIMULATING
  • "Crashing" is a technique which shows the
    potential gain of investing in reducing the time
    needed for a critical path
  • Yields time-cost tradeoff graph
  • Another technique exists which replaces each time
    estimate with a probability distribution
  • Project evaluation and review technique (pert)
  • A more realistic probabilistic approach involves
    simulating project networks
Write a Comment
User Comments (0)
About PowerShow.com