Title: 200911 Capital Budget Development Training


1
2009-11 Capital Budget Development Training
  • Prepared by Tom Henderson

2
2007-09 Capital Budget4.3 Billion
CTCs 12.1
  • /millions
  • Govt. Operations 997.4
  • Human Services 301.6
  • Natural Resources 1,036.2
  • Transportation 5.4
  • K-12 1,000.1
  • Universities 547.5
  • CTCs 518.4
  • Statewide Total 4,296.6

K-12
23.3
Transportation
.01
3
SBCTC 2007-09 Capital BudgetTypes of Projects
Replacements 21.5
Renovations 13.1
Locally Funded 4.6
Minor Repairs 2.9
MO/Infrastructure 5.3
Growth Projects 42.1
Matching/Minor Imp 5.0
Repairs 5.5
4
SBCTC Capital History
in millions
518
471
426
289
229
171
106
116
5
Target Assumptions ( in millions)
6
SBCTC Percent of Higher Education G.O. Bonds
50.0
57.4
54.8
40.9
44.5
39.6
33.9
22.0
Includes Gardner Evans Bonds
7
Capital Policy
  • Construct quality buildings
  • Yakima Valley Science and Instructional
    Building
  • Highline Higher Education Center
  • Everett Science and Art Building
  • Flexibility to respond to changing program
    requirements
  • Keep facilities from deteriorating and eliminate
    temporary structures on main campuses
  • Focus on renovating and replacing the worst
    buildings first

8
Capital Outlook
  • Budget level between 550M and 600M
  • Evans-Gardner bonds not available in 2009-11
  • Greater focus on preservation and backlog
    reduction by Legislature
  • 2-year college priority system is well respected
  • 4-year universities still implementing a
    statewide priority system
  • Design to State requirement for LEED Silver
    buildings

9
Capital Process
  • Plan, plan, plan
  • Survey repair needs and facility condition
  • Select and prioritize new growth, renovation,
    replacement and matching fund projects
  • Build a budget request that is reasonable and
    defensible

10
Master Plan
  • Build better choices through strategic planning
  • Short term 2-6 years
  • Mid-term 7-12 years
  • Long range 13-20 years
  • Recommended attachments to the master plan
  • 10 year plan
  • Facility Condition Survey (maintenance)
  • CAM Model (integrates FTES, FAE and budget
    actions committed changes)

11
Capital Impact
  • New facilities are transformational
  • Changing dynamics of student use
  • Decisions may need to be reconsidered
  • Changing demands and space utilization
    (expansion of online and hybrid courses)
  • It may not be prudent to accelerate the capital
    facilities plan

12
Evaluation of Campus Dynamics
  • Individual program issues
  • Coordination of programs
  • Student Services delivery and consolidation
  • Changes in the center of activity
  • Circulation pedestrian and vehicle
  • Adequacy of space for education

13
Schedule
  • Major milestones
  • Critical deadlines
  • December 5, 2007 PRRs due
  • April 11, 2008 Budget requests due
  • July 2, 2008 Predesigns due
  • Critical review and decision activities
  • OFM and legislative process

14
Changes in the Capital Budget
  • Matching funds raised to 2 million per project
  • Incorporated improvements to the selection and
    ranking process
  • 70,000 GSF maximum and 25,000 GSF minimum
    (exceptions approved by WACTC Capital Committee)

15
Selling the Capital Budget
  • What is the problem being solved?
  • What are the benefits to students and the
    college?
  • What is driving the need for capital investment?
  • Preservation
  • Program
  • Will the project increase capacity? How many FTE?

16
Predesign
  • Follow the OFM outline structure
  • Make sure you have spelled out the programmatic
    needs and benefits of the project
  • Simplify sections that are not useful
  • No site selection for renovation projects
  • Analyze whether it is better to renovate or
    replace
  • Clearly identify reasons for replacement
  • Dont copy the detailed appendices on predesigns
    sent to State Board for distribution to OFM and
    the Legislature

17
C-100
  • OFM C-100 use links to ensure you are using the
    latest documents (enable macros)
  • Use consultants to help define scope, cost and
    schedule information on projects greater than 1
    million (pay attention to Extra and Other Design
    Services)
  • Make sure the estimate is complete remember
    equipment, permits, bonds, etc.
  • Review similar projects and check with colleges
    to help avoid omitting key elements

18
Project Request Reports
  • Build the case for funding a project
  • Establishes need, scope and costs
  • Document will be read by selection committee,
    OFM, HECB and legislative fiscal committees
  • Primary decision tool for selecting and ranking
    new growth, renovation, replacement and matching
    fund projects

19
Building the 2009-11 Request
  • Repair and Minor Improvements
  • Matching Funds
  • Renovation
  • Replacement
  • Growth
  • Alternative Financing

20
Repair and Minor Improvements
  • Make permanent alterations to buildings that will
    be retained
  • Work to improve the useful remaining life of
    facilities
  • Coordinate repair decisions with the facility
    master plan
  • Use ERF funds now to solve critical problems
    identified in the 2007 Facility Condition Survey
    (score over 60)

21
Repair and Minor Improvements (contd)
  • Dont make temporary component repairs on failed
    systems
  • Do a complete job coordinate the work (e.g.
    roofing and HVAC)
  • Use GA Energy office to assist with major
    mechanical and lighting projects (ESCOs and
    Treasurer Lease Purchase Funding)
  • Infrastructure repairs greater than 1M are
    requested separately, less than 1M are included
    with site repairs.

22
Matching Funds
  • Up to 2 million in state match
  • Project should be able to start construction
    before the end of the biennium
  • Matching funds must be cash from non-state
    sources
  • Additional funds can be from college reserves

23
Renovation
  • Have you owned the problem more than 20 years (as
    of 12/07)?
  • Are you sure the building is worth renovating?
    Invest in investigation.
  • Professional assistance and estimating is
    essential to a successful project
  • Renovation is costly - even with a higher
    contingency we often experience problems with
    cost and scale back projects

24
Renovation (contd)
  • It is difficult to approach the Legislature twice
    on the same building. If unsure ask for design
    funding in 09-11 and construction funding in
    11-13.
  • If it will cost more than 80 of the replacement
    value to renovate, it is generally better to
    replace the facility.
  • Can you maintain programs and renovate the
    proposed space? Do you have surge space?

25
Replacement
  • Resolve problems of small space, inflexible,
    cheaply built facilities inadequate power, data
    and communication, low ceilings, structural and
    energy problems, bad educational environments
  • Aggregate small buildings and portables into
    larger structures with internal circulation
  • Minimum footprint 20,000 sf, look for economies
    of scale, 3 story, 65,000 sf buildings

26
Replacement (contd)
  • Space doesnt need to be replaced in-kind
  • Right size spaces
  • Use factor to provide internal circulation
  • Coordinate replacement space with needs
    identified in the master plan
  • Replacement and renovation allows for a 30
    increase in area to improve program delivery and
    to add needed office space and support space

27
Replacement (contd)
  • Locations need to be consistent with the master
    plan
  • Build lasting, quality facilities that meet the
    program needs today but are flexible enough to be
    modified in the future.
  • No, you cannot import failing portables to get a
    new building
  • Project requests must be independent

28
Growth
  • Need to show the FTE levels that will be served
    by the new facility
  • Must have a strong pattern of enrollment growth
  • Generally have a significant shortage of
    instructional and instructional related space

29
Growth (contd)
  • The strategic and facilities master plan needs to
    identify the type and character of programs
    served by the proposed facility
  • Must clearly establish the programmatic drivers
    for building a new facility
  • Recognize the competitive nature of this category
    only 2 to 3 projects may be selected to move
    forward

30
Alternative Financing
  • Legislature is looking for C-2s, C-100s, and
    predesigns to support COP projects in the same
    way direct appropriations are requested
  • Be able to start construction within the biennium
  • Must have bids in hand to sell Certificates of
    Participation (COPs)
  • Work with State Treasurer to identify timing of
    bond sales and prepare supporting data

31
Alternative Financing (contd)
  • Smaller COPs are only affordable if coordinated
    with other two-year college bonds. Asking for
    less than 1M may be a waste of time
  • Timing of bond sales is not always consistent
    with college needs
  • File an intent to use COP funds
  • Use of local funds to bridge COP revenue

32
Alternative Financing (contd)
  • Colleges need to self-fund predesign and design
    cost on COPs
  • Legislature and OFM are looking for more process
    in decision making from our Boards on satellite
    facilities
  • Acquisition of buildings needs to include dollars
    to renovate and remodel the structure at the time
    of purchase

33
Submitting the Budget
  • Narrative format from last biennium on the SBCTC
    website
  • http//www.sbctc.edu/college/_f-capbgtmessage.asp
    x
  • One copy in a 3 ring binder and a CD
  • Use the checklist to order the submittal and
    ensure all documents are transmitted
  • An additional copy of the PRR is not needed in
    the April 2008 submittal

34
Submitting the Budget (contd)
  • C-100s must match the predesign C-100s
  • WACTC has a financial penalty for late submittal
    (loss of 25,000 in RMI funds). Penalty may
    extend to end runs.
  • If you have significant changes in projects, we
    need to know about them before April 11 (i.e.
    mitigation costs, potential overruns, etc.)
  • Project costs must be reasonable and reflect the
    current market conditions.

35
Questions?