Title: 200911 Capital Budget Development Training
12009-11 Capital Budget Development Training
- Prepared by Tom Henderson
22007-09 Capital Budget4.3 Billion
CTCs 12.1
- /millions
- Govt. Operations 997.4
- Human Services 301.6
- Natural Resources 1,036.2
- Transportation 5.4
- K-12 1,000.1
- Universities 547.5
- CTCs 518.4
- Statewide Total 4,296.6
K-12
23.3
Transportation
.01
3SBCTC 2007-09 Capital BudgetTypes of Projects
Replacements 21.5
Renovations 13.1
Locally Funded 4.6
Minor Repairs 2.9
MO/Infrastructure 5.3
Growth Projects 42.1
Matching/Minor Imp 5.0
Repairs 5.5
4SBCTC Capital History
in millions
518
471
426
289
229
171
106
116
5Target Assumptions ( in millions)
6SBCTC Percent of Higher Education G.O. Bonds
50.0
57.4
54.8
40.9
44.5
39.6
33.9
22.0
Includes Gardner Evans Bonds
7Capital Policy
- Construct quality buildings
- Yakima Valley Science and Instructional
Building - Highline Higher Education Center
- Everett Science and Art Building
- Flexibility to respond to changing program
requirements - Keep facilities from deteriorating and eliminate
temporary structures on main campuses - Focus on renovating and replacing the worst
buildings first
8Capital Outlook
- Budget level between 550M and 600M
- Evans-Gardner bonds not available in 2009-11
- Greater focus on preservation and backlog
reduction by Legislature - 2-year college priority system is well respected
- 4-year universities still implementing a
statewide priority system - Design to State requirement for LEED Silver
buildings
9Capital Process
- Plan, plan, plan
- Survey repair needs and facility condition
- Select and prioritize new growth, renovation,
replacement and matching fund projects - Build a budget request that is reasonable and
defensible
10Master Plan
- Build better choices through strategic planning
- Short term 2-6 years
- Mid-term 7-12 years
- Long range 13-20 years
- Recommended attachments to the master plan
- 10 year plan
- Facility Condition Survey (maintenance)
- CAM Model (integrates FTES, FAE and budget
actions committed changes)
11Capital Impact
- New facilities are transformational
- Changing dynamics of student use
- Decisions may need to be reconsidered
- Changing demands and space utilization
(expansion of online and hybrid courses) - It may not be prudent to accelerate the capital
facilities plan
12Evaluation of Campus Dynamics
- Individual program issues
- Coordination of programs
- Student Services delivery and consolidation
- Changes in the center of activity
- Circulation pedestrian and vehicle
- Adequacy of space for education
13Schedule
- Major milestones
- Critical deadlines
- December 5, 2007 PRRs due
- April 11, 2008 Budget requests due
- July 2, 2008 Predesigns due
- Critical review and decision activities
- OFM and legislative process
14Changes in the Capital Budget
- Matching funds raised to 2 million per project
- Incorporated improvements to the selection and
ranking process - 70,000 GSF maximum and 25,000 GSF minimum
(exceptions approved by WACTC Capital Committee)
15Selling the Capital Budget
- What is the problem being solved?
- What are the benefits to students and the
college? - What is driving the need for capital investment?
- Preservation
- Program
- Will the project increase capacity? How many FTE?
16Predesign
- Follow the OFM outline structure
- Make sure you have spelled out the programmatic
needs and benefits of the project - Simplify sections that are not useful
- No site selection for renovation projects
- Analyze whether it is better to renovate or
replace - Clearly identify reasons for replacement
- Dont copy the detailed appendices on predesigns
sent to State Board for distribution to OFM and
the Legislature
17C-100
- OFM C-100 use links to ensure you are using the
latest documents (enable macros) - Use consultants to help define scope, cost and
schedule information on projects greater than 1
million (pay attention to Extra and Other Design
Services) - Make sure the estimate is complete remember
equipment, permits, bonds, etc. - Review similar projects and check with colleges
to help avoid omitting key elements
18Project Request Reports
- Build the case for funding a project
- Establishes need, scope and costs
- Document will be read by selection committee,
OFM, HECB and legislative fiscal committees - Primary decision tool for selecting and ranking
new growth, renovation, replacement and matching
fund projects
19Building the 2009-11 Request
- Repair and Minor Improvements
- Matching Funds
- Renovation
- Replacement
- Growth
- Alternative Financing
20Repair and Minor Improvements
- Make permanent alterations to buildings that will
be retained - Work to improve the useful remaining life of
facilities - Coordinate repair decisions with the facility
master plan - Use ERF funds now to solve critical problems
identified in the 2007 Facility Condition Survey
(score over 60)
21Repair and Minor Improvements (contd)
- Dont make temporary component repairs on failed
systems - Do a complete job coordinate the work (e.g.
roofing and HVAC) - Use GA Energy office to assist with major
mechanical and lighting projects (ESCOs and
Treasurer Lease Purchase Funding) - Infrastructure repairs greater than 1M are
requested separately, less than 1M are included
with site repairs.
22Matching Funds
- Up to 2 million in state match
- Project should be able to start construction
before the end of the biennium - Matching funds must be cash from non-state
sources - Additional funds can be from college reserves
23Renovation
- Have you owned the problem more than 20 years (as
of 12/07)? - Are you sure the building is worth renovating?
Invest in investigation. - Professional assistance and estimating is
essential to a successful project - Renovation is costly - even with a higher
contingency we often experience problems with
cost and scale back projects
24Renovation (contd)
- It is difficult to approach the Legislature twice
on the same building. If unsure ask for design
funding in 09-11 and construction funding in
11-13. - If it will cost more than 80 of the replacement
value to renovate, it is generally better to
replace the facility. - Can you maintain programs and renovate the
proposed space? Do you have surge space?
25Replacement
- Resolve problems of small space, inflexible,
cheaply built facilities inadequate power, data
and communication, low ceilings, structural and
energy problems, bad educational environments - Aggregate small buildings and portables into
larger structures with internal circulation - Minimum footprint 20,000 sf, look for economies
of scale, 3 story, 65,000 sf buildings
26Replacement (contd)
- Space doesnt need to be replaced in-kind
- Right size spaces
- Use factor to provide internal circulation
- Coordinate replacement space with needs
identified in the master plan - Replacement and renovation allows for a 30
increase in area to improve program delivery and
to add needed office space and support space
27Replacement (contd)
- Locations need to be consistent with the master
plan - Build lasting, quality facilities that meet the
program needs today but are flexible enough to be
modified in the future. - No, you cannot import failing portables to get a
new building - Project requests must be independent
28Growth
- Need to show the FTE levels that will be served
by the new facility - Must have a strong pattern of enrollment growth
- Generally have a significant shortage of
instructional and instructional related space
29Growth (contd)
- The strategic and facilities master plan needs to
identify the type and character of programs
served by the proposed facility - Must clearly establish the programmatic drivers
for building a new facility - Recognize the competitive nature of this category
only 2 to 3 projects may be selected to move
forward
30Alternative Financing
- Legislature is looking for C-2s, C-100s, and
predesigns to support COP projects in the same
way direct appropriations are requested - Be able to start construction within the biennium
- Must have bids in hand to sell Certificates of
Participation (COPs) - Work with State Treasurer to identify timing of
bond sales and prepare supporting data
31Alternative Financing (contd)
- Smaller COPs are only affordable if coordinated
with other two-year college bonds. Asking for
less than 1M may be a waste of time - Timing of bond sales is not always consistent
with college needs - File an intent to use COP funds
- Use of local funds to bridge COP revenue
32Alternative Financing (contd)
- Colleges need to self-fund predesign and design
cost on COPs - Legislature and OFM are looking for more process
in decision making from our Boards on satellite
facilities - Acquisition of buildings needs to include dollars
to renovate and remodel the structure at the time
of purchase
33Submitting the Budget
- Narrative format from last biennium on the SBCTC
website - http//www.sbctc.edu/college/_f-capbgtmessage.asp
x - One copy in a 3 ring binder and a CD
- Use the checklist to order the submittal and
ensure all documents are transmitted - An additional copy of the PRR is not needed in
the April 2008 submittal
34Submitting the Budget (contd)
- C-100s must match the predesign C-100s
- WACTC has a financial penalty for late submittal
(loss of 25,000 in RMI funds). Penalty may
extend to end runs. - If you have significant changes in projects, we
need to know about them before April 11 (i.e.
mitigation costs, potential overruns, etc.) - Project costs must be reasonable and reflect the
current market conditions.
35Questions?