Homework 3 Group Technology Design and Operational Scheduling - PowerPoint PPT Presentation

About This Presentation
Title:

Homework 3 Group Technology Design and Operational Scheduling

Description:

L = Lathe. M1 = Machine Type 1. M2 = Machine Type 2. D = Drilling Machine. G = Grinding Machine ... for each type are 2 Lathes,1 Drill, 2 Grinders, 1 M1 ... – PowerPoint PPT presentation

Number of Views:35
Avg rating:3.0/5.0
Slides: 10
Provided by: johne2
Category:

less

Transcript and Presenter's Notes

Title: Homework 3 Group Technology Design and Operational Scheduling


1
Homework 3Group Technology Design and
Operational Scheduling
  • Due on November 22, 2006
  • Maximum group size is 2 students

2
Question 1
  • Assume that a machining operation produces 20
    products with a machine and routing operation
    shown in Figure 1.
  • Consider the following production requirements
    for the 20 different part numbers given in Table
    1. Develop a machine grouping plan to build the
    products in part families.
  • Illustrate the new layout and routing for the
    facility accounting for all machines.

3
Figure 1 - Production Flow
4
Table 1. Production Operations
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
L X X X X x x x x x x x x x x x
M1 x x x x x x x x x x X x
M2 x x X x x x x x x x x
D x x x x x x x x x x x x x x
G x x x x x x x x x x x
L Lathe M1 Machine Type 1 M2 Machine Type 2
D Drilling Machine G Grinding Machine
5
Question 2
  • Next assume that production for each part in one
    group did not have the same processing routing
    sequence. The routing sequence for a series of
    parts is noted in the following Table 2.
  • 2.A) For this operation, a loop operation using
    the diagram as shown in Figure 2 is proposed.
    Arrange the lathes, machine, drill, and grinder
    to minimize the flow for the loop conveyor.
  • 2.B) If you are allowed to buy one more machine
    (i.e. machine duplication), which machine would
    you like to buy and why? What will be the new
    layout?

6
Table 2. Product Sequence for One Group
Product Volume Sequence
A 800 L-D-G
B 1200 L-M1-G-M2
C 3700 D-L-M1-G
D 1500 D-M1-L-G
E 900 D-M1-G-L-G
F 2200 M1-G-L-D
G 1400 D-M1-L-M1-G
7
Figure 2 Loop Layout
Material Flow
Lathe
Grind
Machine 1
Drill
Machine 2
Lathe
Grind
8
Question 3
  • Assume that the following Table 3 provides a
    series of parts to be produced in the proposed
    cell. The dates show the required due date for
    production and the cost shows the tardiness cost
    per unit per week for each product. Develop a
    production schedule to produce the products while
    minimizing the total tardiness cost.
  • Assume that the available production time is 40
    hours per week (or 8 hours per day) on each
    machine. The number of machines for each type are
    2 Lathes,1 Drill, 2 Grinders, 1 M1 and1 M2.
  • Products A, B and C belong to Family 1, and
    Products D, E, F and G belong to Family 2. If you
    switch from one family to another one on any
    machine, the required setup time is 4 hours.
    There is no setup time for the products within
    the same family.

9
Table 3. Operational Data
Product Volume Sequence Time (min) Cost/Unit Due Date
A 800 L-D-G 2-3-1 150 Week 1
B 1200 L-M1-G-M2 3-1-4-4 100 Week 2
C 3700 D-L-M1-G 1-1-2-5 200 Week 3
D 1500 D-M1-L-G 2-2-3-1 400 Week 4
E 900 D-M1-G-L-G 1-2-2-1-5 200 Week 4
F 2200 M1-G-L-D 1-2-3-2 400 Week 5
G 1400 D-M1-L-M1-G 1-1-2-1-4 200 Week 5
Write a Comment
User Comments (0)
About PowerShow.com