Title: PMBOK SECTION II: The Project Management Knowledge Areas
1PMBOK SECTION II The Project Management
Knowledge Areas
- Chapter 04 Project Integration Management
- Chapter 05 Project Scope Management
- Chapter 06 Project Time Management
- Chapter 07 Project Cost Management
- Chapter 08 Project Quality Management
- Chapter 09 Project Human Resource Management
- Chapter 10 Project Communications Management
- Chapter 11 Project Risk Management
- Chapter 12 Project Procurement Management
2Chapter 4 Project Integration Management
3Project Integration Management
- The processes required to ensure that the various
elements of the project are properly coordinated.
- Making tradeoffs among competing objectives and
alternatives to meet or exceed stakeholder needs
and expectations.
4Project Integration ManagementMajor Processes
- Project Plan Development.
- Project Plan Execution.
- Integrated Change Control.
- The PIM processes interact with each other and
processes in the other knowledge areas.
5Overview of Project Integration Management Major
Processes
6Project Plan Development
- Project plan development uses the outputs of the
other planning processes, including strategic
planning, to create a consistent, coherent
document that can be used to guide both project
execution and project control.
7Project Plan Usage
- Guide project execution.
- Document project planning assumptions.
- Document project planning decisions regarding
alternatives chosen. - Facilitate communication among stakeholders.
- Define key management reviews as to content,
extent, and timing. - Provide a baseline for progress measurement and
project control.
8Project Plan Inputs Tools Techniques - Outputs
9Project Plan Inputs
- Other planning outputs - All outputs of planning
processes in the other knowledge areas are inputs
to developing the project plan. - Other planning outputs include both base
documents, such as the WBS, and supporting
details. - Many projects require application area-specific
inputs. - Historical information - available historical
information should have been consulted during the
other project planning processes. - Historical information aids in verifying
assumptions and assessing identified
alternatives.
10Project Plan Inputs - cont
- Organizational policies (formal and informal)
policies whose effects must be considered, such
as - Quality managementprocess audits, continuous
improvement targets. - Personnel administrationhiring and firing
guidelines, employee performance reviews. - Financial controlstime reporting, required
expenditure and disbursement reviews, accounting
codes, standard contract provisions. - Constraints - an applicable restriction that will
affect the performance of the project. - Assumptions - factors considered to be true,
real, or certain. - Assumptions affect all aspects of project
planning, and are part of the progressive
elaboration of the project. - Project teams frequently identify, document, and
validate assumptions during the planning process.
11Project Plan Tools Techniques
- Project planning methodology - any structured
approach used to guide the project team during
project plan development - Most project planning methodologies make use of a
combination of "hard" tools, such as project
management software, and "soft" tools, such as
facilitated startup meetings. - Stakeholder skills and knowledge.
- Project management information system (PMIS) -
the tools and techniques used to gather,
integrate, and disseminate the outputs of project
management processes. - Earned value management (EVM) - a technique used
to integrate the project's scope, schedule, and
resources and to measure and report project
performance from initiation to closeout.
12Project Plan Outputs
- Project plan - a formal, approved document used
to manage project execution. - Supporting detail.
- Outputs from other planning processes not
included in the project plan. - Additional information or documentation generated
during project plan development such as
constraints and assumptions. - Technical documentation, such as a history of all
requirements, specifications, and conceptual
designs. - Documentation of relevant standards.
- Specifications from early project development
planning.
13Project Plan Components
- Project charter.
- A description of the project management approach
or strategy. - Scope statement that includes the project
objectives and deliverables. - WBS to the level at which control will be
exercised, as a baseline scope document. - Cost estimates, scheduled start and finish dates,
and responsibility assignments for each
deliverable within the WBS to the level at which
control will be exercised. - Performance measurement baselines for technical
scope, schedule, and cost. - Major milestones and target dates for each.
- Key or required staff and their expected cost
and/or effort. - Risk management plan that includes key risks,
constraints and assumptions, and planned
responses and contingencies for each. - Subsidiary management plans.
- Open issues and pending decisions.
14Project Plan Execution
- The primary process for carrying out the project
plan.
15Project Plan Execution Inputs Tools Techniques
- Outputs
16Project Plan Execution Inputs
- Project plan - the subsidiary management plans
and performance measurement baselines. - Supporting detail.
- Organizational policies.
- Preventive action any action that reduces the
probability of potential consequences from
project risk events. - Corrective action any action done to bring
expected future project performance in line with
the project plan. - Corrective action is an output of the various
control processes (completes PM feedback loop).
17Project Plan Execution Tools and Techniques
- General management skills such as leadership,
communicating, and negotiating. - Product skills and knowledge.
- Work authorization system - a formal procedure
for sanctioning project work (typically a written
authorization to begin work on a project activity
or work package). - Status review meetings - regularly scheduled
meetings at various frequencies and different
levels to exchange information about the project. - Project management information system.
- Organizational procedures - formal and informal
procedures that are useful during project
execution.
18Project Plan Execution Outputs
- Work results - outcomes (tangible and intangible
deliverables) of the activities performed to
accomplish the project. - deliverables collected as part of project plan
execution and fed into the performance reporting
process. - Change requests relative to project baseline
parameters (scope, costs, schedule, etc).
19Integrated Change Control
- Influencing the factors that create changes to
ensure mutually agreed upon changes. - Determining that a change has occurred.
- Managing actual changes as they occur.
20Coordinating Changes Across the Entire Project
21Integrated Change Control Inputs Tools
Techniques - Outputs
22Integrated Change Control Inputs
- Project plan - provides the baseline against
which to control changes. - Performance reports - information on project
performance used to alert the project team to
project issues. - Change requests.
- Oral or written.
- Direct or indirect.
- Externally or internally initiated.
- Legally mandated or optional requests.
23Integrated Change Control Tools and Techniques
- Change control system - a collection of formal,
documented procedures that defines how project
performance will be monitored and evaluated and
steps by which official project documents may be
changed. - Paperwork.
- Tracking systems.
- Processes.
- Approval levels for authorizing changes.
- Changes that may be automatically approved
without prior review. - Configuration management - any documented
procedure used to apply technical and
administrative direction and surveillance to - Identify and document the functional and physical
characteristics of an item or system. - Control any changes to such characteristics.
- Record and report the change and its
implementation status. - Audit the items and system to verify conformance
to requirements. - Performance measurement.
- Additional planning.
- Project management information system (PMIS).
24Integrated Change Control Outputs
- Project plan updates - any modification to the
project plan or supporting detail contents
(stakeholder notification). - Corrective action.
- Lessons learned
- Causes of variances.
- Reasoning behind chosen corrective actions.
- Other types of lessons learned.
- Become part of the historical database for both
the project and other projects of the performing
organization (the basis for knowledge management).
25Chapter 5 Project Scope Management