3KEY FOCAL AREAS
- Issues for the next Budget Year
- In general it is apparent that the Departments
budgetary allocation is far inadequate to fund
the Departments critical programmes as would be
demonstrated in slides 16 - 19. - The Department has demonstrated capacity to spend
its allocated budget, as evidenced by the
R34million over-expenditure in the 2001/02
financial year as well as the current expenditure
trends that indicate a potential over-expenditure
of R40 million - The serious negative implications of
under-funding are in the next forthcoming slides
4PROGRAMME 1 ADMINISTRATION
- O Conducting the overall management of
- the Department
- O Formulates policy issues relating to the
- Departments mandate
- O Provides centralised leadership support
- of the Ministry and the Senior
- Management
- O Transformation Programme
5 PROGRAMME 2 PROVISION OF LAND AND ACCOMMODATION
- Custodian of fixed State Assets
- Design and Construction of Buildings and Support
Infrastructure - Repair and Maintenance of State Facilities
- Leasing
- Municipal Services (Water and Electricity)
- Rates and Taxes
- Acquisition of Property
- Property and Facilities Management
6PROGRAMME 3 NATIONAL PUBLIC WORKS PROGRAMME
MISSION
- To implement the National Public Works Programme
by - Delivering assets, jobs and capacity building
through the Community Based Public Works
Programme (CBPWP) as a basis for sustainable
rural development. - Promoting construction industry growth,
development and transformation for enhanced
infrastructure delivery through the
Construction Industry Development Programme (CIDP)
7COMPARISON OF REQUESTED BUDGET WITH PROPOSED
ALLOCATION AT PROGRAMME LEVEL
AMOUNT REQUESTED R millions PROPOSED ALLOCATION R millions DIFFERENCE R millions
1 Programme 1 Administration 304 277 27
2 Programme 2 Provision of Land and Accommodation 4,321 3,851 470
3 Programme 3 National Public Works Programme 420 322 98
4 Programme 4 Auxiliary and Associated 12 12 0
TOTAL 5,057 4,465 592
8 COMPARISON OF REQUESTED BUDGET WITH PROPOSED
ALLOCATION AT STANDARD ITEM LEVEL
AMOUNTS REQUESTED R millions PROPOSED ALLOCATION R millions DIFFERENCE R millions
Personnel expenditure 611 611 0
Administrative Expenditure 73 73 0
Inventories 57 42 15
Equipment 100 66 34
Leases 1,041 861 180
Rates Taxes, Municipal Services and Maintenance 2 800 2505 295
Transfer payments 374 306 68
Miscellaneous expenditure 1 1 0
TOTAL 5,057 4,465 592
9IMPLICATIONS
- The implications of underfunding as they
relate to the main cost Items are - Leasing The failure to honour lease commitments
will result in the affected client departments
being evicted from the offices they occupy. - Rates Taxes The municipal Services will be
terminated with catastrophic results to public
facilities like hospitals etc. In addition, this
sphere of Governments service delivery efforts
will be greatly compromised
10IMPLICATIONS (continued)
- Maintenance May result to non compliance with
Occupational Health and Safety Act as some
buildings are already in dilapidated state. - Transfer Payments The shortfall in the main is
in CBPWP. The department will therefore be
unable to provide as many public assets as it had
wished to provide. A number of potential
temporary jobs opportunities have therefore been
lost.
11COURSE OF ACTION
- In view of the underfunding, service
delivery by the - department will be compromised. There
however - exists a window of opportunity in that
additional funding may still be found around
October during the consideration of Adjustment
Estimates Appropriation Bill. - To this end, the department appeals to the
- Committee to provide whatever support it has
to ensure that additional funding is received as
indeed, the cut back on expenditure is not a
realistic solution to the problem.
12CONCLUDING REMARKS
- In conclusion, the department wishes to highlight
the - positive impact and achievements that its
programmes - continue to contribute to governments overall
objectives - and priorities in areas of
- Employment creation
- Black economic empowerment
- Infrastructure investment
- Land reform initiatives and
- Poverty alleviation.
- The department requests the Committee to
assist the department in its endeavours to
solicit additional funding in future
appropriations as the service delivery will be
severely compromised due to inadequate funding.