Title: Barriers for Energy Conservation (A management view)
1Barriers for Energy Conservation(A management
view)
- By
- D K Singhal
- Chandpur Enterprises Ltd.,
- Sumit Agarwal
- Shree Badri Kedar Papers Ltd.,
2Attending Seminars
- In most of the seminars, intended for energy
conservation, approximately half of the time is
spent on over-emphasizing need for energy
conservation. The presenters forget that the
persons who are attending these seminars already
are convinced that energy conservation is a must
for them. As a seminar attendee most persons are
interested to gain certain knowledge that can
save some energy and hence some money in their
plant.
3In Seminars.
- Furthermore, most of the general nature data do
not seem to be authentic, or, at least, seems
doubtful. In a recent seminar, one presenter
indicated Indias paper production to be 6.6
million ton, while other indicated the same as
7.7 million ton. On questioning, it was told that
the data were taken from different studies by
different agencies. - These data may be of some use for government
officers, but a common attendee, is only
interested in determining the possible savings
opportunity in his plant, and suitable ways for
achieving the same. - Wasting too much of time on such presentations,
is a wastage of time and energy.
4At the End of the Day
- Any management is interested to know from the
attendee whether his attending the energy
conservation seminar will be useful to the
company or not. If yes, what would be the
approximate amount of investment and what could
be the gains.
5Existing Trends
- Markets are very competitive, so conservation
automatically becomes vital. - Under such situation, no management can overlook
energy conservation. - Still, many approaches used by managers are
techno-economically viable, but at the same time
could prove not very acceptable. - Some such cases are illustrated here.
6Case 1 Fan Pump VFD
- In a small paper mill, the fan pump motor was of
75HP, drawing nearly 83Amps. - The system was running for past few years.
- Management refused option of VFD due to high cost
(approx. 3Lac).(Payback app. 3Months) - Manager revised situation and decided to have a
VFD of lower rating costing nearly Rs. 2 Lac. - This was again turned down by management due to
funds problem.
7Without a VFD
- The manager was enthusiastic, and decided to us
pulleys for rpm reduction. - As a result, load decreased to 54 Amps.
- After some time, pulleys were changed again.
- Load decreased to 40Amps.
- (Payback app. 3days)
- The manager demanded VFD again after a couple of
month, indicating that he had already saved the
money required for it. - The management reply was.
8A simple question
9Management Vision
- If you consider installation of VFD after
reaching to 40 Amps as in previous case, payback
period could be as high as 3-4 years. - For this mill, option A-B is better. But, had the
mill operating at point B, should option B-C be
followed?
Investment 10,000 Saving 43Amp Payback 3 days
Investment 3,00,000 Saving 3Amp
(Estimated) Payback 3Years
A
B
C
Investment 3,00,000 Saving 46Amp Payback
3Months
10Comments
- This mill had no portable energy audit equipment,
but hired an energy advisor for conducting audit,
who recommended the VFD initially. - If a VFD is to work within a narrow speed range,
please think twice. - Is it really required?
11Management Policy
- Energy conservation must be practiced for saving,
considering techno-commercial viabilities, and
must be suitably planned. - Installation of energy efficient system should
not be done just for others are doing so. - Always consider, If there exists a low-cost
midway?
12Case 2 Boiler Efficiency
- In a small mill having a 5TPH boiler, management
was worried about low efficiency. - An energy audit firm conducted detailed analysis
of the system, and came up with an 80 page report
after nearly one and a half month of plant study. - The major possible solutions recommended were
13After Energy Audit
Recommendation (Reason for lower efficiency) Mill Comments/Actions
1 High moisture in fuel Bound to run fuel that is available in the market.
2 High ash in fuel Bound to run fuel that is available in the market.
3 Excess air A new ID Fan was procured and installed.
14Layman's Approach
- At almost the same time, another mill nearby
asked a one man consultant(?) for the similar
problem, who suggested after just a walk through
audit, to reduce ID fan rpm by changing pulley. - Opinions may differ, but, first mill, after
hearing about this case feels second mills
decision was a better one as consultancy fee and
investment in first case was very high, while
final results were almost similar.
15For Small Mills
- It must also be noted that-
- Mill-1 had delayed energy audit by nearly 10
month, as the audit fee seemed much higher to the
mill. - Audit considered fuel properties that were
prevailing at the audit time. In most of the
small mills, there is a vide variation in fuel
over the year.
16Lack of Comparative Approach
- If we study BEE norms for the paper mills, data
lack comparative approach. Any mill can look at
its data and is supposed to decide where does it
stand. But, if comparisons are made section wise,
the managers concerned will obviously concentrate
more towards their plants to achieve better
results. - For example, if there are two papermakers, often
the discussion is how much vacuum do you apply on
your machine? The higher vacuum user gets
motivated to use lesser vacuum automatically.
But, total paper machine specific energy is not
so regularly discussed by them.
17Benchmarks
- Benchmarks must be simple and easy to grasp by
management. - This is because kWH/T or kg bagasse per ton
make better sense in management point of view
than GJ/T. Many small mills do not even
understand GJ/T. Though energy audit is not
mandatory for small mills, yet, policy makers
should not give attention only to large mills
only. - A such simple benchmark being followed by
papermakers is KVM of vacuum per daily ton of
paper. KVM has been taken by the model number of
a well known Indian vacuum pump manufacturer.
18Inferences
- For small energy consumers, we need to develop
low cost, simple and easy to use thumb rules in
the first phase. - For example-
- 1Amp saved Rs.100/per day saving
- Fan Pump ampere Ton Per Day Production
- ID Fan Amperage 0.9 X Ton Per Day Fuel
- After some time, when it is observed that at
least a certain percentage of units has been able
to obtain satisfactory results, the mouth
publicity will spread results very soon to other
mills also. - After most of the mills have achieved a certain
benchmark, they will automatically get interested
in implementing advance techniques e.g. energy
auditing, process up gradation, automation of
process operations etc. for better energy
efficiency.
19Thank You.
- D K Singhal
- deveshksinghal_at_rediffmail.com
- deveshksinghal_at_gmail.com
- Sumit Agarwal
- sumit_agarwal15_at_rediffmail.com