Title: US ATLAS Tracking Upgrade
1(No Transcript)
2Staves An Integrated Tracking Structure for the
ID
3Outline
- Issues from Genoa
- Derived specifications
- Progress on Phase 1 program
- Plan for future work
4Genoa Meeting
- Basic configuration consensus
- Pixel region
- Intermediate region 3 SS layers 3cm x 80mm
- Outer region 2 DS layers 10cm x 150mm,
- Z measurement provided by stereo
- Radiation issues implication for S/N and
operating temperature - -25C suggested
- Strong emphasis on material and services
reduction alternate powering schemes
5Basic Genoa Layout
62 Types of Staves
16 modules/side
18 modules/side
- 20ltRlt50cm 1 meter stave, 6.4 x 3 cm strips,
alternate along Z, top/bottom provides full
coverage - Rgt50cm 2 meter stave, 6.4 (12.8) x 12 cm strips,
axial/stereo top/bottom design to provide Z at
large radius - Width driven by economics and electrical issues
(voltage drops)
7Mechanical Core
8Stave End View
Silicon Sensors 4mm separation
Peek Cooling channels 2.9 x 5.6 mm
Hybrid electronics
Carbon Fiber Skin
Foam Core
9Integrated support structure 2 int bulkhead 3
outer bulkheads 2(3) barrels
10Structure with one outer barrel and maximum of 1
meter unsupported staves
11Details of CDF Bulkhead
See stave core mechanical samples
12Stave Specifications
- Electrical
- Power distribution
- Signal transmission
- HV
- Mechanical advocate a monitored approach with
software corrections implicit. There are many
examples of large scale precision systems done
that way. - Accuracy in plane
- Sag effects
- Operating temperature and gradients
13Property Short stave Long Stave
width 6.4 cm 6.4 cm (12.8 cm)
length 98 cm 192 cm
detector width 6.4 cm 6.4 cm (12.8 cm)
detector length 3 cm 12 cm
detectors per side 18 16
gap between detector along the stave 2.4 cm 3 mm
detector thickness 280 microns 300 microns
number of strips 768 384 (768)
strip pitch 80 microns 160 microns
Power in front end chips 3 watts 1.7 watts (3.3 watts)
Power in silicon no dose 1 milliwatt 1 (2) milliwatt
Power in silicon high dose 1 watt 1 (2) watt
Maximum temperature at silicon -25 C -10 C
Maximum temperature variation lt5 C lt5C
Max detector position shift from nominal Dy 30 microns 30 microns
Max detector position shift from nominal Dx 30 microns 30 microns
Survey accuracy Sy 5 microns 5 microns
Survey accuracy Sx 10 microns 5 microns
Survey accuracy Sq 0.13 mRad 0,13 mRad
Ladder sag maximum 250 microns 500 microns
Ladder sag stability 50 microns 50 microns
14(No Transcript)
15Operating Temp S/N
- At Genoa values quoted -15 to -25 C
- Depends on how the specd S/N (10?) is achieved,
many variables at play - Leakage current vs dose well known
- Silicon thickness
- CCE, orientation (n in p, n in n, p in n)
- Strip pitch cluster size, capacitance
- FE noise, integration time
16Continued
- p bulk gives us high field at collection, good
for CCE issue - Wide pitch (150 um) gives us large volume for
current generation (bad) but favors single strip
clusters (good), and lower capacitance - Fast electronics allows us to reduce integration
time (good for shot noise) but has larger series
noise (bad, but how bad?) and required more power
(bad for cooling). - Etc.
17Comments on Monitoring
- Stave sag and other deformations (temperature)
will be present - Position monitoring and readout should be
designed into the system from the start. - A number of precise and long range position
sensing technologies are commercially available - We should be prepared to apply software
corrections to the alignment extensively
18Phase 1 Stave
- An ATLAS version of the CDF Run2b device
- 1 sensor hybrid 1 module (hybrid glued to Si)
- 6 modules per side
- Modules linked by embedded bus cable and
- readout token passing scheme
- 2 sided axial/stereo or axial/axial
- 1 Interface Card /stave
- Total length 66 cm
- 6144 channels /stave
- Built around carbon fiber/foam laminate
Purpose is do demonstrate low noise multi-module
performance with ATLAS electronics
19Phase 1 Milestones (completion dates given) full
electrical specification and schematic for Phase
1 stave 10/04 done establishment of test stands
at LBNL, BNL, and Hampton 11/04 done validation
of test stand operation on test
parts 12/04 done design and layout of Phase 1
hybrid 12/04 done fabrication of
hybrid 03/05 done assembly and test of
hybrid 04/05 done re-commission and tests with
existing fixtures 03/05 done assembly of ATLAS
staves 06/05 11/05 initial test of ATLAS
staves at LBNL 07/05 11/05 transfer to and
test of staves at BNL/Hampton 08/05 12/05 irradia
tion studies of staves 10/05 02/06 transfer of
assembly methods to BNL 07/05 12/05
20Bus cable detail shows bonding region
The bus cable runs UNDERNEATH the sensors.
Connections to the hybrids made with wirebonds
in small Z gaps between consecutive crystals Bus
cable is copper/kapton/Al laminate with 100
micron lines/spaces and thin Al shield
layer Electrical isolation of bus from detectors
by grounded shield and diagonal traces (not
parallel to strips)
21(No Transcript)
22ABCD Hybrid
- Fabricated in BeO
- Fine pitch (100 micron) etched line-work
- 7 micron Au thickness
- Bond to pc card for test
- Re-bond on stave
- No connectors
- Schematic similar to standard SCT hybrids
- Electrically OK
- 64 fabricated
23Module Assembly/Hybrid Mount
24Module Test
Conducting rubber
25(No Transcript)
26Main Technical Issue Clock Distr.
- Existing bus cable design individual clock/com
to each of 6 modules - This was at the edge of practicality (layout)
- Genoa long staves with N modules
- Prefer to use a multidrop configuration
- This may be the only practical solution for
longer staves - Stave bus cable has been redesigned, layout
revision in progress - Timing and reflections have been studied
- Implications for ABCD-Next design, etc.
27Bus Cable Geometry and Impedance
Materials Al foil 2mil, Dupont LF0100, Shinetsu
CA333 2 mils, Cu 18 um, Kapton 1 mil, Adhesive
2
Al
1
ADHESIVE
1
1
0.7
Cu
1
KAPTON
1
CF
gtgtMatches measured impedance
28Issue of timing
- Hybrid stubs 12 pf
- LVDS risetime 3.5 ns
- Bandwidth 0.35/3.5 100 MHz
- Impedance of hybrid stub due to capacitance
- 1/(2pi 100 MHz 12 pf) 130 ohms
- Propagation time 60 ps/cm (3 ns for 50 cm)
29Measurements
- Literature available on LVDS multidrop
performance - Application reports from TI, National, Fairchild
- TI study of 36 receivers
- Need to understand this configuration as part of
the ongoing study - Significant impact on cabling
30Bus Cable Test
75 W termination
1212 W
31Implications
- Bus cable test results imply that Phase 1 test
stave with 6 hybrids (4 ABCD chips/hybrid) will
probably work with a single clock line. - For large N staves need to consider an LVDS
receiver chip at the hybrid input to reduce
capacitance seen by the bus drivers - This is consistent with reduced services model
- AC coupling
- Regulators
- Current monitor
- Addressing issues (A.G. note)
- The module receiver chip (MRC) definition and
specification should become an important aspect
of the ABCD-next discussion.
32Continued Activity FY06
- Complete Phase 1 stave
- Apply a multidrop configuration
- Alternative powering add to a second version of
the Phase 1 stave - Serial
- DC-DC?
- Study of bussing and system issues.
- Development of stave readout electronics
- Evaluate performance of SCTDAQ for multi-module
tests - Development of detectors
- BNL is pursing the 3 cm design
- Study of mechanical concepts for long staves
Bill Miller - Material
- Geometry, cross-section
- Cooling
- Fabrication
- ABCD-next
- MRC definition?
33Complete Phase 1 Stave
- Fabricate bus cable
- Continue fabrication and test of remaining
hybrids and modules - Assemble and test 2-3 staves for LBNL and BNL,
Hampton - Costs within FY05 funding
34Alternate Powering
- Development of specs (LBNL)
- Add serial powering test to the Phase 1 stave
- New version of the bus cable (LBNL)
- Add power interface hybrid (LBNL, RAL)
- Use commercial components
- Investigate a universal configuration for
serial and DC-DC tests (LBNL) - System issues bypass, failure, noise (BNL)
35Readout System
- Need to understand how well current UK test stand
works for multi-module staves tests, issue of
concurrent operation - Alternative is a simple pattern generation
approach similar to LBNL Patt Board developed
by MGS for CDF - Engineering on this would be done at BNL and is
included in FY06 budget
36Detectors
- To go beyond the Phase 1 stave based upon CDF
Run2b surplus detectors required ATLAS specific
devices - Candidate is the 3cm short strip design
- BNL will do a design and fabricate.
- For the outer stave the CDF devices may still be
useful need to do inventory and availability
37Mechanics
- 1m and 2m designs require new ME effort for
design and fabrication - Laminates
- Boxes
- Extrusions
- Low temperature operation
- Materials
- B.Miller effort LBNL
- Fixture studies LBNL (FNAL connection)
- BNL engineering
- RAL engineering
38Conclusions/Actions
- Complete phase 1 stave
- Near term
- Develop serial powering modification to stave
- Summer 06
- ABCD-next effort
- Define interface aspect, MRC
- Continue mechanical studies
- Include monitored alignment concepts
- Develop test detectors for phase 2 stave
- Readout electronics study
39(No Transcript)
40- abcdefghijklmnopqrstuvwxyz
- ABCDEFGHIJKLMNOPQRSTUVWXYZ
- 1234567890-,./
- !_at_(()_?gtlt