Spain France Interconnection - PowerPoint PPT Presentation

1 / 5
About This Presentation
Title:

Spain France Interconnection

Description:

... at the same time the Northern part of ... the impact study. Declaration of public ... Construction work. 12 24 Months. France Spain Interconnection : ... – PowerPoint PPT presentation

Number of Views:19
Avg rating:3.0/5.0
Slides: 6
Provided by: vers150
Category:

less

Transcript and Presenter's Notes

Title: Spain France Interconnection


1
Spain France Interconnection
  • CEER Workshop
  • J VERSEILLE
  • Director System Development
  • 13th February 2007

2
Expected Benefits of the Interconnection for the
French system
  • Increased security of supply
  • main factor of risk in France
  • cold periods in Winter ( 1800 MW/C) due to
    anticyclonic conditions
  • often affect at the same time the Northern part
    of Europe
  • Spain can experience milder conditions at this
    time
  • Support from the spanish system to the french
    system
  • expected in such situations (ex winter 2005)
  • Market opportunities
  • High sensitivity of Spanish system to climatic
    conditions
  • Large variations of hydro generation on a yearly
    or seasonal basis
  • Large variations of wind generation on a weekly
    daily basis
  • High level of consumption in Summer in Spain
  • Market opportunities for increased imports
    /exports

3
Administrative procedures in France
  • Project endorsed by the Ministry
  • Public debate (expression of public opinion on
    the project)
  • 18 24 Months
  • Determination of general route
  • 30 42 months
  • Prior consultation
  • identifying study area
  • progressively define less impact area
  • produce the impact study
  • Declaration of public interest (DUP)
  • Consultation of mayors and departments
  • Public inquiry
  • gt Obtaining DUP
  • Determining the precise line route in details
  • 12 18 months
  • Approval of technical drawing
  • Planning permission
  • Amicable agreements and easements
  • Construction work

4
France Spain Interconnection present
situation
  • Public debate held in march june 2003
  • local opposition against the proposed route
  • Ministry asked to propose new options
  • Three main options to cross the border prepared
    by RTE / REE
  • compromise to be found between
  • environmental aspects
  • efficiency for the power system
  • local acceptance
  • No decision taken yet

5
Origin of the difficulties
  • History of the project a previous project in
    another area stopped in 1996
  • Crossing the border needs a high level political
    agreement
  • Agreement between national and regional/local
    authorities is a prerequisite
  • Acceptable compromises on one side of the border
    can be contradictory with the objectives of the
    other party
  • At the local level no clear and obvious
    advantages
  • Rejection of the usefulness of the line
  • Ideologic opposition
  • Landscape preservation
  • Nimby or Banana
  • Interconnection two countries, twice as many
    stakeholders with various objectives