Title: Bonding meeting


1
FNAL Bonding
  • Since our last report we have built and bonded an
    additional 10 TOB 4-chip modules
  • 3 RMT pitch adapters
  • 7 Planar pitch adapters
  • By adjusting bonding parameters on a case by case
    basis for the RMT modules we were able to
    eliminate all of the sensor-to-PA bond repairs.
  • Last fall we reported a 2 repair rate
  • Pull test results for the RMT PAs were still low
    (6-8 grams) even with the bond parameter tuning,
    but with the transition to Planar PAs this is no
    longer an issue. See the enclosed histogram.
  • Bonding time for the Planar modules is typically
    around 10 minutes. An additional 15 minutes is
    needed for the sensor-to-PA pull tests and
    rebonding.
  • We are assuming that pull tests will not be done
    for the majority of modules during normal
    production.
  • With the change in the way ST sensors are tested
    data is no longer entered into the DB in a
    standard way, and this is giving us difficulties
    in determining bad channel information for wire
    bond skips and may also lead to difficulties with
    the Bonding interface.

2
FNAL Bonding
Average pull strengths from the every 50th wire
sen-to-PA pull tests. Modules 702-708 have RMT
PAs modules 709-715 have Planar PAs.