Title: Installation, next steps now to August 2005


1
Installation, next stepsnow to August 2005
  • 7th Oct 2004, ATLAS plenary
  • On behalf of TC

2
UX15 Cavern Status now
  • Truck and shifted platform to be put in place
    this week. Then ready for 1st BT coil.
  • Barrel Calorimeter ready for cryostat.
  • HS arch extensions added.
  • HM brackets (for muon big wheels) load test
    completed.
  • Services schlaps platform being added to HS on
    USA15 side.
  • Services being added to Barrel Calorimeter.
  • HS gangways being added between HO and HS.

3
In UX15 Cavern now
HM Brackets Test
Gangways HS to HO
4
Schedule
5
Major phases to Aug 2005
  • Barrel Toroid 1st coil to Point 1 starting 20th
    Oct 2004
  • Barrel cryostat lowered into cavern 26th Oct 2004
  • Barrel Calorimeter into BT in August 2005
  • Barrel services installation on truck - now
  • Some services including cryo.
  • Some Muon barrel installation
  • HS Arch (after BC in BT)

6
Barrel Toroid
7
Lowering of BT Coil
  • First BT coil arrives at Point 1 on Oct 20th 2004
  • Lowered into cavern Oct 21st.

8
BT Coil casing transport
9
BT trials in May
10
BT Trials in May
11
BT Coil Installation
12
BT Coil Installation
13
First Coil installation
14
BT Installation drawing
15
Coils connection box assembly
16
Warm structure assembly
Most critical connection is 6 and 7
All bolted connections compliant with Eurocode 3
Using sand blasted surfaces to increase friction
co-efficient.
Will use strain gauges etc to corroborate FEA
calcs.
17
Top coils support
18
Barrel toroid Assembled
19
BT Assembly plus muon rail positions
20
Barrel Toroid Installation Structures
21
Gangways in BT
  • The brackets for the access gangways in the BT
    coil will be installed where possible as the coil
    is assembled.
  • After removing the BT coil jacks, and the barrel
    calorimeter put into position, the gangways and
    barrel muons will be installed as the BT assembly
    platforms are removed.
  • Prototype platform received from Pakistan.

22
Gangways in BT
23
Gangways in BT
24
Barrel Calorimeter
25
Barrel calorimetry
  • Activities on truck C
  • Approx 50 of the Tile Calorimeter assembled.
  • Installing now on the lower half all calorimeter
    cable trays, cooling pipes, cryostat
    supports, CS sources pipes, some cables.
  • Lower the barrel cryostat on Oct 26th
  • Complete the mechanical installation of the Tile
    Calorimeter
  • Trial movement of Barrel Calorimeter (1 metre)
  • Install on the upper half all possible calo
    services
  • Install and then partially remove all ID cables
    supports on the calorimeter surface and front
    faces, including all possible pipes
  • Install the LAr electronics racks and start the
    electronics cards installation and commissioning
  • Commission the tiles drawers electronics
  • Prepare all hardware to move the calorimeter
    inside
  • Move barrel calorimeter into BT (August 2005)

26
Cryostat in Building 180
27
Barrel Cryostat to be lowered on Oct 26th
28
LAr cryostat installation
A cradle will be used in the pit for LAr
positioning
29
Barrel movement system
Aim to have trial move March 2005
30
End Cap Calorimeter Assembly
Ready for installation in cavern
31
Barrel Muon Chambers
32
Muon barrel 1st Phase installation Jan 2005
  • First phase installation planned for muon
    chambers in feet region.
  • Will consist of all BMF, 4 - BOF, 6 - BOG in
    sectors 12 and 14.
  • Maybe some BML and BOL in sector 13 (depends on
    truck position).
  • Feet region very complex detail design with small
    clearances between chambers and feet.
  • Installation has to be quick as on critical path.
  • Access is complicated over the large volume
    occupied by muon chambers.
  • Will try and put as many brackets and rails in as
    building up the BT. But there will be final
    adjustment of brackets and rails after jacks
    removed from BT.
  • Task force working on variations of installation
    sequence/methods to save time in schedule.

33
Barrel Muons Layout
34
Muon brackets on BT in Building 180
35
Muon barrel sectors 12 to 14
36
Muon Barrel Installation
37
BMS Installation options (part of task force
study)
Using crane and during BT assembly. Saves time
but risk of damage
Using tooling from BML rail.
38
Services
39
Services
  • As much as possible of the services that run
    along the barrel calorimeter surface to Z zero
    will be added while the calorimeter is on the
    truck.
  • At present services are being installed on the
    lower half.
  • When cryostat installed and top half of
    calorimeter completed then services installation
    will continue.
  • Elsewhere services are being added-
  • Calorimeter services from USA15 to HS.
  • ID Type 4 services from HS to USA15 and US15
  • Magnet bus-bar installation on HS and gallery to
    USA15
  • Cryo lines to Zzero.
  • Start equipping racks in USA15
  • Start installing racks on HS.

40
Magnet racks and bus-bars in USA15
Installation of bus-bars and racks on 1st
floor in USA15
41
Services design
TILECAL cable tray 75x24 mm2
Spacer bar 30x6 mm2
LARG cable tray 100x48 mm2
TileCal cooling pipes
LARg cooling metla pipes
TileCal CAN bus cables
42
Services Barrel Calorimeter
Services being added to Barrel Calorimeter on
truck
Aim to complete as much as possible of barrel
services for Tile, LAr, and ID on truck before
moving into BT
43
ID services trays in Barrel Cryostat bore
44
Inner Detector Piping
45
Cable Schlap Guide Supports
46
Racks and cable trays
250 racks in USA15 cable trays below installed
Cable trays from USA15 to UX15 installed
  • October-November, first installation of
    electronics, network, racks slow control, racks
    safety,..

47
Conclusions
  • Between mid Oct and Xmas 2004 very critical
    period for the installation of Atlas.
  • Installation of two BT coils.
  • Lowering of Barrel cryostat and build up of
    calorimeter.
  • Now know BT availability in more detail.
  • Planning to complete the BT by July/August 2005.
  • Install barrel calorimeter by end August 2005.
  • Not having components (inc small items e.g.
    bolts) on time and in right place will cause many
    delays.
  • As the toroid is assembled aiming for-
  • early installation of services.
  • early installation of muon chambers in the lower
    sector
  • preparation for the ID cables installation.