Title: Estimates and Contract Finalization
1Estimates and Contract Finalization
2Narrative Schedule
- Please make sure the narrative schedule is
submitted on applicable contracts (Roy Sturgill). - First estimate cannot be processed and the
contractor cannot be paid until the schedule has
been submitted.
3Is Contract in eMARS?
- Before submitting estimate number 1 for a
contract, make sure the contract is ready in
eMARS. - Use Doc_Viewer or SiteManager to confirm that the
contract is established. - Use Doc_Viewer to check line balances before
submitting estimates for processing.
4Checking Doc_Viewer
Open Doc_Viewer, click on eMARS
5Select Purchase Order Hearders and Lines (it is a
typo in the programming it should be Headers)
6Use the Data Filter Center to filter for Doc_ID,
Contains, Contract ID number. If no PO2 shows up
in your search, the contract is not yet in eMARS.
If the contract is in eMARS select the most
recent PO2.
7Select the Line Records tab the OPEN_AM is the
balance left in each line in eMARS for the
selected contract.
8E-mars flag in Sitemanager
- Before submitting Estimate 1 make sure passed to
e-mars in DOCVIEWER or SiteManager
KyTag flag 3 passed to E-Mars KyTag flag blank or
2 Not yet
9Diary and DWRs
- Make sure to use the remarks to document daily
happenings. - Examples special or unusual events visitors.
10Fuel and Asphalt Adjustments
- Run fuel and asphalt adjustments as the work is
being done. - A new software program FAA to help with Fuel and
Asphalt adjustments is in the works and expected
to be available next month - Do not wait until the contract is complete to
calculate adjustments. Monitor if index goes down
and do NOT overpay a contract
11Change Orders
- Keep change orders current.
- Make sure all change orders are approved or
denied before submitting a Final to the Central
Office.
12Key Dates
- There are several key dates that must be entered
in SiteManager before submitting the contract to
Central Office as a Final. - Open to Traffic
- Work Complete Date
- All necessary inspection dates (this varies by
contract) - Corrective work dates (if applicable)
13Key Dates continued
- Ready for Materials Check-RE
- Resident Final Check
- Files Received in District Office
- District Final Check
- Ready for Material Check-DME
- Materials Certification Letter
14What to Submit with Final
- Electronic copies of Fuel and Asphalt adjustments
- Electronic copies of Lot Pay Adjustments
- Electronic copy of Liquidated Damages Report
- Send notification via email to Stephanie Rich,
Beverly Terry, and Terri Cunningham that includes
all above electronic copies, and the anticipated
final amount.
15Records and Retention
- Construction Project files must be maintained by
the district for three years after the Division
of Account makes final payment to the contractor. - Blueprints/plans of the original project design
can be destroyed after the final payment is made. - As-Built Plans and Profile sheets should be sent
to Central Office Construction when the Final is
submitted. These are then processed and Division
of Design microfilms and retains permanently.
16Records and Retention continued
- Cross-section and structure plan sheets are to be
sent to Central Office Construction.
Cross-sections will be retained for three years
after final payment. Structure Sheets are held
until the structure is demolished. - Field Records, such as weigh tickets, should be
retained in the District for three years after
final payment. - Radiographic Film and Ultrasonic reports for
bridge beams are to be sent to Central Office
Construction and held for three years after the
final.
17Records and Retention continued again
- Shop Drawings and Designs for Bridge Construction
are to be forwarded to Central Office
Construction and retained until the final
estimate is paid. - Non-Plan Projects such as mowing and bridge deck
overlays may have related records. These can be
destroyed after the final estimate is paid by
accounts.