Title: Estimates and Contract Finalization


1
Estimates and Contract Finalization
  • Plus Record Retention

2
Narrative Schedule
  • Please make sure the narrative schedule is
    submitted on applicable contracts (Roy Sturgill).
  • First estimate cannot be processed and the
    contractor cannot be paid until the schedule has
    been submitted.

3
Is Contract in eMARS?
  • Before submitting estimate number 1 for a
    contract, make sure the contract is ready in
    eMARS.
  • Use Doc_Viewer or SiteManager to confirm that the
    contract is established.
  • Use Doc_Viewer to check line balances before
    submitting estimates for processing.

4
Checking Doc_Viewer
Open Doc_Viewer, click on eMARS
5
Select Purchase Order Hearders and Lines (it is a
typo in the programming it should be Headers)
6
Use the Data Filter Center to filter for Doc_ID,
Contains, Contract ID number. If no PO2 shows up
in your search, the contract is not yet in eMARS.
If the contract is in eMARS select the most
recent PO2.
7
Select the Line Records tab the OPEN_AM is the
balance left in each line in eMARS for the
selected contract.
8
E-mars flag in Sitemanager
  • Before submitting Estimate 1 make sure passed to
    e-mars in DOCVIEWER or SiteManager

KyTag flag 3 passed to E-Mars KyTag flag blank or
2 Not yet
9
Diary and DWRs
  • Make sure to use the remarks to document daily
    happenings.
  • Examples special or unusual events visitors.

10
Fuel and Asphalt Adjustments
  • Run fuel and asphalt adjustments as the work is
    being done.
  • A new software program FAA to help with Fuel and
    Asphalt adjustments is in the works and expected
    to be available next month
  • Do not wait until the contract is complete to
    calculate adjustments. Monitor if index goes down
    and do NOT overpay a contract

11
Change Orders
  • Keep change orders current.
  • Make sure all change orders are approved or
    denied before submitting a Final to the Central
    Office.

12
Key Dates
  • There are several key dates that must be entered
    in SiteManager before submitting the contract to
    Central Office as a Final.
  • Open to Traffic
  • Work Complete Date
  • All necessary inspection dates (this varies by
    contract)
  • Corrective work dates (if applicable)

13
Key Dates continued
  • Ready for Materials Check-RE
  • Resident Final Check
  • Files Received in District Office
  • District Final Check
  • Ready for Material Check-DME
  • Materials Certification Letter

14
What to Submit with Final
  • Electronic copies of Fuel and Asphalt adjustments
  • Electronic copies of Lot Pay Adjustments
  • Electronic copy of Liquidated Damages Report
  • Send notification via email to Stephanie Rich,
    Beverly Terry, and Terri Cunningham that includes
    all above electronic copies, and the anticipated
    final amount.

15
Records and Retention
  • Construction Project files must be maintained by
    the district for three years after the Division
    of Account makes final payment to the contractor.
  • Blueprints/plans of the original project design
    can be destroyed after the final payment is made.
  • As-Built Plans and Profile sheets should be sent
    to Central Office Construction when the Final is
    submitted. These are then processed and Division
    of Design microfilms and retains permanently.

16
Records and Retention continued
  • Cross-section and structure plan sheets are to be
    sent to Central Office Construction.
    Cross-sections will be retained for three years
    after final payment. Structure Sheets are held
    until the structure is demolished.
  • Field Records, such as weigh tickets, should be
    retained in the District for three years after
    final payment.
  • Radiographic Film and Ultrasonic reports for
    bridge beams are to be sent to Central Office
    Construction and held for three years after the
    final.

17
Records and Retention continued again
  • Shop Drawings and Designs for Bridge Construction
    are to be forwarded to Central Office
    Construction and retained until the final
    estimate is paid.
  • Non-Plan Projects such as mowing and bridge deck
    overlays may have related records. These can be
    destroyed after the final estimate is paid by
    accounts.