Title: - DCWAC -
1 - DCWAC - Where weve come from, Where we
are, Where were headed
2Goal Statement To create a Watershed Management
Master Plan for the Dominguez Channel Watershed
that will establish sound measures to protect and
improve its environment and beneficial uses.
3History
- February 1, 2001 - LACDPW submits application to
State Water Board requesting 200,000 as part of
Prop 13 money to create a Watershed Management
Master Plan for the Dominguez Channel Watershed. - February 6, 2001 - 27 individuals representing 18
agencies met at the City of Carson to discuss
happenings in the Dominguez Channel Watershed and
LACDPWs desire to form a working group to create
a watershed management master plan - DCWAC is
born. - May 8, 2001 - Established four
committees within
the DCWAC to
tackle various tasks within
the scope
of watershed management
TMDLs,
outline/scope of master plan,
funding, technical. - May 18, 2001 - Prop 13 money approved
for award to DCWAC to help fund the
Dominguez Channel
Watershed Management
Master Plan.
4Present
- August 1, 2001 - As of today there are
approximately 100 individuals involved in some
way with the DCWAC representing over 40
organizations - The DCWAC is currently involved in two primary
tasks - 1. Developing the Watershed
Management Master Plan - 2. Assisting the Regional Board
in TMDL
development for the
Dominguez
Channel
Watershed.
5Future (proposed for outline/scope committee)
- The Master Plan is scheduled to be completed by
December 2003 and can be divided into three basic
components.
1. Background and Existing Conditions of the
Watershed 2. Issues/Concerns/Problems addressed
by stakeholders, identified by local government
and
regulated by governing
agencies.
3. Prioritized list of project concepts to
address issues, correct problems and improve
conditions of the watershed.
6Future (proposed for outline/scope committee)
1. Background and Existing conditions of the
watershed
- Include geography, geology, seismology,
topography, land uses, hydrology, hydraulics,
natural and imported resources, environmental and
socioeconomic conditions, designated and desired
beneficial uses...etc.
- Propose bringing a consultant on board to compile
existing info and discover missing pieces. - Complete background section by Jan 2003.
7Future (proposed for outline/scope committee)
2. Issues/Concerns/Problems addressed or
identified by stakeholders and regulating
agencies.
- Between now and June 2003, compile problem
statements based on input from all those
interested in or part of Dominguez Channel-LA/LB
Harbor Watershed
- Proactive solicitation of public input and
involvement
- As the Background and Existing Conditions
portions of the plan are completed, these goals,
issues and problem statements can be adjusted to
more thoroughly address the state of the
watershed. - Completed by mid 2003.
8Future (proposed for outline/scope committee)
3. Prioritized list of project concepts to
address issues, correct problems and improve
conditions of the watershed.
- Between January and September 2003, develop
project concepts based on existing conditions and
identified problems.
- Consultant pulls together all project concepts
and completes final draft of Master Plan by
December 2003.
- DCWAC coordinates efforts of all stakeholders to
secure funding and implement Master Plan,
updating it as necessary.
9Future (proposed for outline/scope committee)
Implement Plan
Project concepts submitted to consultant Sept
2003
Master Plan completed Dec 2003
Background finished Jan 2003
stakeholders
consultant
1st draft background June 2002
Consultant selected-Jan 2002
10Next Steps (proposed for outline/scope committee)
- 1. Prepare draft RFP for consultant by August 22.
- Gather and compile Background and Existing
Conditions info - Discover data gaps - suggest plans to fill gaps
- Coordinate with outline committee
- Solicit input and involvement of the public
- Assist in conducting public meetings
- Suggest issues/goals/problems for the watershed
- Write Master Plan
- 2. Review of RFP
- Outline committee review
- Available for comment by
next DCWAC
meeting - 9/5 - 3. RFP on street by 10/1
- 4. Consultant on board by
Dec/Jan.