Title: Zebulun Krahn
1Straw Tubes and Hall D
Zebulun Krahn
Carnegie Mellon University
Advisor Curtis Meyer Technician Gary Wilkin
GlueX Collaboration Meeting
December 11-13, 2003
2Outline of the Talk
- Gas simulations, endplate production, etc
- Straws, feed-through system, glue tests,
stringing
- Electronics, DAQ, prototype testing
3Built Gas Mixing System
Matches JLAB equipment
Can mix up to three gases
Completed June 02
4Garfield Gas Simulations
Lorentz Angle vs. Drift Time
Note 62 -Completed Nov. 02
5Studies of BNL Chamber
Studied performance of chamber with cosmics and
Ru106
- Studied coincidence between tubes
- Studied position dependence
- Dissection to analyze construction methods
Completed Dec. 02 Note 54
Note Very Leaky!
6Prototype Endplates
¼ endplates machined checked at JLAB
Straight and Stereo layers
2-3 man months set-up and machining
Completed June 03
Note 61
Final Accomplishment Successfully closed out a
JLAB RD account
7Current Work
Goal Build a prototype full scale ¼ chamber at
CMU
Since May of 03
8Issues with Straw Tubes
Straw Tube vendors
- Vendors differ widely in price and service
- On preliminary order, as many as ¾ of the
tubes, not usable
How do you cut a 4 mil walled straw tube?
12,000RPM with a 10 mil blade
9Issues with Straw Tube Chambers
They leak!
- Look for design that allows for gas-tight system
- Determine methods of containing leaks that do
exist
- System design and product testing
10Epoxy Testing
Pressure Gauges
Two important criteria
Used a known non-conductive epoxy as
baseline 3M Scotch-Weld 2216
Two candidates, to date might use both
Held 2.5 PSI for several weeks
Fill Valve
11Feed-Through System
Two main components
- Inserted in end of straw tube
Tube
- Hole and V-notch allow injection of epoxy
12Feed-Through System II
- Inserted through
- endplate and
- captures donut
- Chamfer allows space for glue
13Gas Flow System
Towards Gas-Tight goal
- Learned a lot from BNL chamber minimize leaks
Gas Seal
Gas Seal
14Stringing Method
Axle system for stringing
- Whole chamber rotates on axis
- Tension cables prevent bowing
Note We are building stringing apparatus for
actual full size chamber!
15Sliding Collars
Allow for capture of inner radius of endplates
Lower collar bolted to axle for strength
Upper collar allowed to slide capture, set
screwed in
16Hook Swivel Joint
Steel plug inserted into aluminum axle
- Allows for use of crane/winch
- Allows for rotation of chamber
This steel plug will also be the anchor point for
tension cable/rods
17Ball Joint Base Plate
Steel Plug inserted into aluminum axle
- Captures the bottom of axle
- Allows for rotation
- and more!
Base Plate will bolt to floor
18The Axle
Specifications
Limiting factor ability to machine the axle
- Maximal Deflection for 600lb chamber 1.6 mm
19Future Work
- Actual Manufacture of required pieces
- Donuts, Feed-Throughs, sliding collars, 50 tube
prototype
- Electronics
- Setting up DAQ
- Upon completion of prototype, testing will be
needed
20Conclusion
- Gas simulations, endplate production, etc
- Straws, feed-through system, glue tests,
stringing
- Electronics, DAQ, prototype testing