Title: US CMS Silicon Tracker Project
1US CMS Silicon Tracker Project
2210 m2 of Silicon Strips
Outer Barrel (TOB)
End Caps (TEC 12)
Inner Barrel Disks (TIB TID)
2,4 m
5.4 m
volume 24.4 m3 running temperature 10 0C
3Silicon Strips
500 mm high resistivity
Blue double sided
320 mm thick low resistivity
Red single sided
Strip lengths 10 cm (innermost) to 20 cm
(outermost) Strip pitches 80mm (innermost) to
200mm (outermost)
4Module Components
Pins
Front-End Hybrid Flex-ceramic laminate
w/integral Kapton cable
Kapton cable
Pitch Adapter
Kapton-bias circuit
Carbon Fiber Frame
Silicon Sensors
5Technology
- Single sided p/n
- Industry standard
- Mass producible at low cost
- Surface radiation damage
- Increases strip capacitance (noise)
- p/n ok after inversion if adequately
over-depleted - High Breakdown Voltages
- Specific design and processing rules for guard
strip geometries - Al strip layer acts as a field plate to remove
high field region from Si bulk to Oxide
6Sensors
Pitch adapter
Frames
Hybrid
Hybrids
factories
Brussels
Brussels
CF carrier
Strasbourg
US in the tracker
CERN
Perugia
Wien
Louvain
RU
Sensor QAC
Karlsruhe
Strasbourg
Module assembly
Lyon
Bari
Perugia
Wien
UCSB
FNAL
Bonding testing
Aachen
Karlsruhe
Strasbourg
Zurich
Wien
UCSB
Bari
Firenze
Torino
Pisa
Padova
Integration into mechanics
ROD INTEGRATION
TIB
-
TID INTEGRATION
PETALS INTEGRATION
Aachen
Louvain
Karlsruhe
Lyon
Strasbourg
Pisa
FNAL
Brussels
UCSB
TOB
assembly
TIB
-
ID
assembly
TEC
assembly
TEC
assembly
Sub-assemblies
At CERN
Pisa
Aachen
Karlsruhe
.
--
gt Lyon
TK ASSEMBLY
At CERN
7Covered in this talk
- Status of Production parts
- For Modules Sensors, Hybrids and Module Frames
- For Rods Rod Frames
- US Readiness
- US Group Evolution past year and upcoming year
- Status of all production equipment and manpower
- Cost Performance and Schedule
8Components Overview
- Stockpiling Parts Now ? but with some caveats
- Sensors (500 mm thick)
- SGS Thomson (ST) ? Many problems. Production
stopped - Hamamatsu (HPK) ? Excellent quality. Deliveries
behind expected - Sensor Frames from Belgium/Pakistan on track
- Problems over the past few years appear to all be
worked out for now - Hybrids from Cicorel/Hybrid SA/CERN ? critical
path - Several design flaws and processing quality
issues uncovered. - Last one now being resolved
- Rod Frames from Helsinki/CERN ? recent mistake
found on some - Various residual problems have mostly been found
and addressed. - One found this week but not expected to cause any
delays - More may arise with experience..
9Timeline of ST Sensor Issue
- August 03
- US uncovered a problem with ST sensors
- December 03 (3 day sensor workshop at CERN)
- Re-probing 1000 sensors in US and EU indicates
quality has degraded from original - US group conclusion degradation in time
possible chemical deterioration. - January 04
- Place orders with HPK for masks and prototypes
- February 04
- ST agrees to significant changes in QC and stable
processing with the aim of being re-qualified at
July 04 tracker week. Also agrees to cut order
from 18,000 to 11,000. CMS places order with HPK
for 7000 sensors - May-July 04
- ST delivers 1000 qualification sensors. US builds
177 modules. Sees time evolution in at least 2
modules. Sensor groups see time evolution in 5
of sensors probed. - Tracker week - July 04
- probing groups together with ST uncover
definitive evidence of corrosion resulting from
large phosphorous content in surface oxide. - ST is not qualified by CMS.
101. Common Mode Noise (CMN)
Situation as of early04
- CMN effect features
- Group of noisy strips with a turn-on voltage at
which all 128 channels show high noise - can appear after thermal cycles
- often accompanied by other types of degradation
such as pinhole development, more CMN - Often correlated with high current
Later a second chip develops a high noise
channel which causes common mode noise Channel
previously only had a slightly higher noise (0.3
ADC)
112. Vacuum effect ? single strips !
with vacuum
As of early04
without vacuum
Strip 420 421 (4µA 15µA). Switching probe chuck
vacuum on and off switches these strips on and
off. Effect is reproducible. No visible defect
seen.
123. Peculiar IV Curves
late 03 early 04
OB2 sensors
Its like no diode Ive ever seen Gromit -
Wallace
134. Long term instability
30211334388607
As of early04
145. Structure in leakage current
Good sensor
As of early04
156."Dots and Stains" development
initial
3 hrs, no hum. nothing more
As of July 04 tracker week
30 min, 40 RH Þ stains on guard first usually
1h30, 40 RH Þ new stains on bias (not always
visible on video, see later)
16"Dots and Stains" origin
Investigation by Strasbourg and Karlsruhe (with
help of the Fraunhofer Institute Chemische
Technologie)
The ratio of elements in white areas of
stains indicates the existence of
Aluminum-oxide Corrosion !
As of July 04
17Confirmation by ST
Aluminum corrosion
Both dots and stains are micro-corrosions of the
aluminum surface. The mechanism that drives this
phenomenon can be the following Humidity reacts
with Phosphorus (present in a 4 concentration
into the passivation oxide) and forms an acid
(probably H3PO4), that corrodes a superficial
layer of Aluminum.
Passivation (1 µm)
Aluminum (2 µm)
Triple oxide layer (1.5 µm)
As of July 04
187a. Long term sensor tests
- 233 sensors tested 72h (room temeperature,
r.h.25-30)
Failure rate of qualification sensors in 72 h
period is 5
As of July 04
197b. Long term TOB module tests
Maxed out ADC Bits at this point
nA
After 7 hours, bias current started to
increase New high noise channels seen in
subsequent tests
sec
- Dark marks on bias ring occur near high noise
channels
207c. Long term TEC module tests
22 modules tested 1 module with current increase
during LT test
As of July 04
21The Current Situation
- Need 18,200 thick sensors installed in CMS
tracker - 20,000 total (10 spares) originally all ST
- Shifted orders to HPK
- Winter 04 7,000
- Summer 04 4,500
- Autumn 04 5,200
- TOTAL of 16,700 (1,500 short of installation
requirement) - Agree to accept 3,000 sensors from ST
- Installation of at least 1,500
- HPK Shipments
- Started on schedule in June 04
- Did not yet reach levels expected
22Original Schedule
 Jan-04 Feb-04  Mar-04 Apr-04 May-04 Jun-04  Jul-04 Aug-04 Sep-04  Oct-04
             Â
Mask Production             Â
Sensor Pre-Production             Â
Sensor Qualification     240        Â
Sensor Production      540 1000  1500 1500 1500  1500
 Cumulative Production      540 1540  3040 4540 6040  7540
Sensor Acceptance       500  1000 1500 1500  1500
- Initial plan showed 1st 7000 sensors delivered by
November - Current 4000 delivered.
- Met with Yamamoto (v.pres.HPK) Oct. 11 at CERN
(JI on video - 3 problems identified (One month lost while
analyzing problems) - Poly Silicon operator error caused over-etching
- Backside SiO2 too thin caused high leakage
currents - Scratches due to a problem with automated
handling devices - Recent batches have 75 yield allowing 1300/mo.
rate - If achieve 85-90 then will deliver 1500/mo.
- Agreed if order placed by Jan. HPK can deliver
all 16,700 by Oct. 2005 - Also discussed option to extend quantity by ?
3,000
23Timeline of Hybrid Issues
- Summer 2003 US finds broken cable traces
- US reviews handling and studies alternative
handling schemes - CERN finds breaks are widespread
- Vendor says design is fatally flawed
- New design implemented after only 2 months delay
- Winter 2004 US finds strange failure mode in
modules - US traces the problem to the hybrid
- CERN responds instantaneously halts all hybrid
production - Find vias are not properly plated, with breaks
occurring at unknown rate - US Halts production of TOB and TEC modules except
for ST qualification - Many TEC TIB modules already done in EU (small
radius HPK thin sensor modules) - EU continues building
- Summer 2004 Vendor bought out.
- Management serious about solving this problem,
with better resources. - 4 variations of design processed
- Autumn 2004 QC Engineer at vendor - all trials
are highly successful! - Week October 15 2004 CMS qualifies substrate
- Week October 22 CMS to qualify fully loaded
hybrids
241.Hybrid Cable Problem
- Flex cable fragility
- Problem was quickly solved
- Good US/CERN relationship
- CERN relationship with vendor
252.Good Vias and Bad Vias
Example of a good via
Cu
26US Hybrids Delivery Schedule
- Oct. 04 200 TB hybrids
- old processing, known via prob. hesitant to use
with HPK sensors - Nov.04 270 TOB hybrids
- not the most recent design but all passed the
testing, and fraction was test with all passing
extreme thermal testing - Jan.05 200 TOB 100 TEC hybrids
- Ramping up to Apr. 05
- Monthly rates 700 TOB, 500 TEC
- Half of the TEC will be sent back to Europe after
they are wire-bonded and tested at FNAL/UCSB/MEX - Each of the 3 North American hybrid processing
centers has a minimum sustainable capacity of gt
24/d ? gt 1600/mo - We can lose a hybrid processing center at any
time without loss of hybrid throughput
27Module and Rod Transportation
- Winter-Spring 03 CERN reports that modules
arriving from US have huge numbers of damaged
wirebonds - US proposes a successful solution (encapsulate
joints) - CERN confirms
- Winter-Spring 04 Rochester studies find
flexible mother cable in rod can damage module
wirebonds in transport - CERN/US engineers study problem and design Al
stabilizers. - Autumn 04 US Discovered error in cross-bar
placement on roughly 50 of rod frames (type-H). - Helsinki developing the repair method.
- US will ship back 40 type H rod frames for
repair - Large numbers of rods will be stockpiled in
advance of full production of modules
28US CMS Tracker Group
- Brown University
- R. Hooper, G. Landsberg, C. Nguyen, H. Nguyen
- University of California, Riverside (UCR)
- P. Gartung, G. Hanson, G.Y. Jeng, G. Pasztor
- University of California, Santa Barbara (UCSB)
- A. Affolder, S. Burke, C. Campagnari, F.
Garberson, D. Hale, J. Incandela, - P. Kalavase, S. Kyre, J. Lamb, R. Taylor, D.
White technicians - University of Illinois, Chicago (UIC)
- E. Chabalina, C. Gerber, L. Nigra, T. Ten
- Fermilab (FNAL)
- M. Demarteau, A. Ronzhin, K. Sogut, L. Spiegel,
S. Tkaczyk technicians - University of Kansas (KU)
- P. Baringer, A. Bean, L. Christofek, D. Coppage
- Mexican Consortium
- Cinvestav H. Castilla, R. Perez, A. Sanchez
- Puebla E. Medel, H. Salazar
- San Luis Potosi A. Morelos
- University of Rochester (UR)
- R.Demina, R. Eusebi, E. Halkiadakis, A. Hocker,
S. Korjenevski, P. Tipton
19 joined group this past year (includes 3 UCSB
technicians) - now adding a few more post-docs
students 9 left the group (includes KSU plus
several from UCSB)
29Preparations
- Good parts in large quantities are coming in
- Deliveries will not be smooth
- Meeting the schedule will require
- Higher than expected peak production rates
- Extremely robust and stable production lines
- Well trained personnel
- Previous proven capacity in US is 15
modules/day/site - Further capacity expansions
- Almost no further fabrication equipment needed
and no expansion in test equipment required - UCSB and FNAL have already completed these
changes - Achieve by extending work day (split shifts)
and/or adding support personnel to major
production tasks - Rates now possible
- FNAL 18/day sustainable and 21-24/d peak
- UCSB 21/d sustainable and 27-30/d peak
30Assembly Plates
UCSB Plates Fabricated (parts made) Commissioned (ready to be used) plates used in module production so far
TOB R-phi 7 7 7
TOB Stereo 3 3 3
TEC R5 R-phi 2 2 2
TEC R5 Stereo 2 2 2
TEC R6 5 5 5
TEC R7 2 2 2
FNAL Plates
TOB R-phi 5 5 5
TOB Stereo 3 3 3
Total 29 29 29
- Total of 29 plates in the US (capacity of 3
modules per plate) - UCSB setup to do TEC.OR.TOB in any given day
- All have been exercised and are ready for use.
31US Production Steps/Status
Task Capacity Manpower issues Software Issues? Hardware Issues
Hybrid Bonding Thermal Cycle 84/d Mexico not yet online No No
Module Assembly gt50/d None No No
Module Bonding gt50/d None No No
ARC Testing gt50/d None No No
LT Testing 200/wk UCR post-doc search No No
ARC LED gt50/d None No No
Module Reinforcing gt50/d None No No
Rod Assembly gt6/d None No No
Single rod test gt6/d UCSB post-doc search Yes Possibly
Multi-rod burn-in 32/wk UCSB post-doc search Yes Possibly
32Module Mechanical Precision
- 97 modules meet the current stringent geometric
specs - Few failures are just outside the relative
angular requirement - US now applies 2nd order corrections
- No new modules outside specs
- Production quality excellent!
- Single Sensor Modules
- 0.20 Faulty strips
- Introduced faults lt 0.1 rate
- Two Sensor Modules
- 0.55 Faulty Strips
- Introduced faults lt 0.1 rate
- Will be much lower w/HPK
Dx(Frame-Sensor) (mm)
Dx(Sensor-Sensor) (mm)
Dq(Frame-Sensor) (mdeg)
Dq(Sensor-Sensor) (mdeg)
33Misalignments and PT Resolution
MC Study of effect of misalignments on pt
resolution single m sample, pT100 GeV
Mean 0.0 RMS 3.5 mm Min -7 mm Max 7 mm
Recent US modules
34Hybrid Thermal Cycler/ARCS Status
- Recently upgraded code
- PLL forcing
- Drifting pedestal check
- Added xml file auto-upload
- UCSB, FNAL and Mexico City test stands are
commissioned and ready
We have all ARCS equipmentspares we need
35DAQ Equipment Status
- 2 fully equipped Vienna boxes at UCSB and FNAL
- UCR Vienna box has enough DAQ equipment for 4
slot stand - TPO needed for 6 slots
- 2 single-rod stands
- Just received enough oMUX cards so re-cabling
between rod types unnecessary - 2 multi-rod thermal cyclers
- Both MUXs have been used to test 5 rods tested
simultaneously - Have enough equipment to fully commission system
- Only 5 MUX cards DAQ spares missing
- To instrument UCR Repair Center have all
critical spare components required in the US we
need - 2 TSC in production?
- 3 TPO in production?
- 2 eMUX boards
- 7 oMUX boards
- 5 VUTRI - in production
- 10 PAACB half are built, half being assembled
now - 10 hybrid-to-utri adaptors in production
36DAQ Equipment Status II
- With current TSC complement
- With 1 failure we lose either
- 1 Vienna box
- 1 single rod stand, or
- 1 rod thermal cycler
- With current TPOs
- With 1 failure we lose either
- 70 capacity of a Vienna box
- 1 single rod system
- 1 multi-rod system
- Cannot run more than 16 APVs in UCR stand
- Without the additional MUX, VUTRI, PAACB,
hybrid-to-utri adapter boards - Cant run UCR LT at full capacity which is
crucial to ops of US Repair center
Component shortages and failures ? potential to
severely limit production testing capacity
37Backup Equipment
- Spare sensor and hybrid tools were produced at
UCSB for UCSB, FNAL and Brussels. - Upgraded OGP computer OS and OGP software
- Automated routine occasionally missed fiducial
marks. The new software fixes this problem. - Set up back-up gantry computers with spare U600
controllers and expansion cards already
installed. - We purchased backup components for every piece of
production equipment or tooling that, if it were
to fail, would cause a reduction in production
rates.
38US Module Types
39First HPK Module Results From UCSB
- 6 R6 modules built using new HPK sensors
- All 6 modules are perfect
- Not a single flaw
- IV profile as expected
- Turn-on at low voltage
- Plateau bias current 600-700 nA
40UCSB TEC Production
- Miscellaneous info
- Have built all required types successfully R5S,
R5N, R6, R7 - 25 shipping boxes (20 modules each) built
- All carrier plates (100 per type) and all
wirebond fixtures complete - Capacity
- Could saturate UCSB production capacity with TEC
modules - Will depend on need and availability of parts as
well as TOB production parts availability and
schedule - Another step higher in production capacity (by
extending work day via overlapped shifts) - Bonding and Testing capacity adequate
- LT testing capacity limit is 100 per week
- Eventually will be mostly TEC (TOB burn-in
shifted to rods) or sampled
41Outstanding problems/issues
- DB stability
- For our production rates, we must automate all DB
queries. - Need to standardize and maintain stable all data
structures - We rely on data to be accurate and complete from
all preceding processing of components and
structures. - Successfully collaborating with our intl
colleagues - Old or un-installable components
- Prefer to remove them physically from our
production sites and to have them properly marked
in DB - Rods
- We have recently achieved major milestones with
rods but we are not out of the woods. See below
42Rods
- Rod assembly understood
- Rod Testing
- Single rod testing is under control
- Multi-rod
- Had many problems with software and hardware
- Recently achieved major milestone at FNAL
- Can now run maximum at capacity (8 SS rods or 6
DS rods i.e. up to 72 modules) for 3 days with
thermal cycles! - Remaining
- Get UCSB multi-rod test stand operational at same
level as FNAL - Had problems with some hardware- now fixed
- To finalize fault finding tests
- Finalize Database info and transfer methods
- Need experience with many rods to determine if
there are issues with components.
43MechanicsTracker Outer Barrel
Rods before/after modules installed
0.9 m
Final Cylinders at CERN
Full Prototype Wheel (for MSGCs)
44Mechanics Tracker Inner Barrel
Support mechanics CF space frames and/or
Honeycomb structures
45MechanicsTracker End Caps
Digital Optical Hybrid
R6
Interconnect Board
Analogue Optical Hybrid
R4
Frontend Hybrid
R2
46Substructures in Test Beams
- May 2003 Beam Test (Bunched 25 ns beams of muons
and pions) - Systems of 6-10 TIB, TEC, TOB modules
- Detector performance as expected!
- May 2004 Beam Test
- Multiple rods, petals, and shells
- Larger system integration tests
- Tracking tests
- Position resolution, hit efficiency
Beam Direction
47The TOB Cosmic rack in the test beamin June 2004
- Michael Eppard (CERN)
- on behalf of TOB CERN
- 23rd July 2004
Michael Eppard
Test General Meeting
23.07.2004
48S/N Module 4 _at_ 300V (PEAK)
S/N gt 32
49ORCA reconstruction of tracks
Ivan Reid
50Cost Performance
- Delays have cost us
- Recently extended production to Jan. 2006
- Net increase of 600k in project
- Other US costs
- Paid for Masks (NRE) at Hamamatsu to be able to
transfer sensor order from ST - 290k
- Misc. equipment for higher/more robust production
- 100K
- Anticipated costs
- US Tech. to work at CERN on hybrids for 6 months
- 50k (?)
- Currently schedule has no contingency
51SST Schedule
Completion Jan. 2006 An aggressive
schedule Will be revised Assumes 500
hybrids/wk Actual 400 hybrids/wk
52Summary
- No longer have a manpower shortage
- In process of adding some personnel at UCSB
- Have studied all possible threats to production
stability - Purchased or manufactured spares
- Further increased capacity to 50 modules/d
- Requires manpower ( 4-5 FTE total)
- Systems
- All stages of production have been exercised and
are near to final except rod testing - Multi-rod stands rapidly converging
53Conclusion
- Strips have been at war with poor components
- ST sensors have too many uncertainties
- Switched to HPK!
- Hybrids problem is solved large deliveries
starting early 05 - US Role has been extremely important
- We are doing everything we can do