Title: AMS-02
1AMS-02 Integration Test Plans Status
Trent Martin
24 January, 2007
2Agenda
- Integration Documentation
- AMS Assembly Area/Clean Room 867
- STA Flight Integration Hardware Status
- Pre-integration of STAs in the Flight USS prior
to STA VC/CMR arrival - Pre-integration of Detectors on the STA VC
Flight USS prior to Flight Cryomagnet arrival - Integration discussion items plans for
resolutions - Final Flight Integration
3Integration Documentation
- All NASA developed AMS documentation can be found
at - http//ams-02project.jsc.nasa.gov/html/Documents.h
tm - Includes payload Interface Control Documents and
AMS-02 Assembly and Testing Integration Plan
4AMS 02 Integration at CERN
Assembled AMS 02
Upper Part
Lower Part
AMS 02 Shipping
5KSC
CERN / ESTEC
- Beam Test
- Experiment
- Calibration
- Thermal Vacuum
- Test _at_ ESTEC
AMS-02
KSC Processing
AMS-02
Hurricane Cover SSPF
3 Operational Years
ISS
Launch
6AMS 02 Assembly Sequence for Pre-Integration and
Flight Integration
7Upper USS Magnet
UPS
- Technical Interchange Meeting
- July 23, 2004
- R.Becker (MIT)
Magnet
CAB
USS-02
CVB
1) SCL delivers Magnet (Flight) or NASA delivers
STA Magnet (Pre-Integration) 2) NASA delivers
USS 3) USS main bolted to Vacuum Case (Magnet
must be warm) placed into rotation assembly
stand
8Crate Installation using Jig
Electronics Assembly Jig Installed
Electronics mounted in sequence with detectors
during pre-integration
-
Radiator Mounted Electronics Assembly
Jig replaced with Radiator during flight
integration when all crates are linked and form
a self supporting structure
9ACC
ACC
VC
VC
- Finger brackets bolted to inner lower bore of VC
- 16 Scintilator panels placed in inner bore
resting on finger brackets - 3) Carbon composite cylinder and with
compliant brackets mounted at upper and lower - inner edge of VC securing the paddles
- 4) PMTs, fiber couplers, and optical fibers
mounted to Conical flange
10Tracker, Cooling, Star Tracker
Tracker Electronics Crates
5)
Star Tracker
6)
3)
4)
1)
Tracker
Flange of VC
Tracker Cooling Box
VC
2)
1) Tracker Inner planes and upper conical flange
lowered and secured 2) Lower conical flange
mounted 3) Cooling loops, TTCS, plumbing 4)
Outer planes (1 5) 5) Crates cabling 6)
Star Tracker camera
4)
11TRD Upper TOF
Upper TOF 1) Upper TOF mounted to TRD
TRD MLI
TRD
TRD GAS System
1) TRD with M-structure lowered onto USS
bolted 2) Gas system installed and plumbed to
TRD 3) MLI enclosure 4) Crates Cabling
12Lower USS Integration
(5) Lower TOF 1) Reinforced with Jig, rolled
underneath AMS lifted into position. Struts
adjusted and bolted in place 2) Crates and Cabling
(6) RICH 1) RICH lowered, shimmed and bolted to
lower USS 2) Crates and Cabling
(7) ECAL RICH/Lower USS assembly lifted lowered
onto ECAL then bolted in place Crates
Cabling These steps can be done in parallel
with upper USS integration and only need to be
done once (ie. No pre-integration)
13Upper Lower Parts Integration
Upper Part
Lower Part
- Lower part rolled underneath Upper
- Lifted in place, shimmed, and bolted
- Electrical connections made
14De-integration for Flight Magnet
Temporarily remove mid-brackets and lower struts
15Temporarily Reattach Top Brackets to Upper USS
Move Main Ram Wake Radiators outward to allow
installation of Flight VC Magnet
16- Radiators Electronics
- Zenith radiators with plumbing attached assembled
in quadrants bolted to TRD upper honeycomb and
heat exchangers to Cryocoolers - Plumbing secured and insulated
- Main radiators jigs removed from self supporting
crates and radiators bolted - Tracker Radiators Jigs holding heat exchangers
removed and radiators lowered and bolted to USS
and exchangers
Zenith Radiator
Tracker Radiator
Tracker Radiator
RAM Radiator
WAKE Radiator
RAM Radiator
17AMS Assembly Area
Clean Room 867
Everything in the AMS Assembly Area/Clean Room
867 needed to begin the STA integration will be
ready no later than (NLT) February 2, 2007.
- Operation as a Clean Room (air conditioning,
filters, sealed positive pressure) will be
ready in May, 2007
- Rotation Assembly Stand (RAS) delivered,
assembled, installed, and ready for use
- Scaffolding delivered, assembled, and ready for
use
18AMS Assembly Area
Clean Room 867
- Information provided in the Resource Requirements
checklists has been used to order common use
supplies and to estimate facility requirements - Work area required with without crane access
special access - Crate storage area, volume, and environment
- Tables chairs
- Storage cabinets open shelves
- Air bearing pallet requirements
- Cleaning fluids/supplies vacuum cleaners
- Supply gases (He, CO2, N2, Compressed air, etc.)
- Fans for ventilation/cooling of hardware
personnel - Power requirements
- ???
- If you didnt ask for it on the checklists, do
NOT expect it to be provided!
19AMS Assembly Area
Clean Room 867
Remov-able Ceiling Panels
Airlock
Ceiling Panels are NOT Removable
20AMS STA Integration Hardware
- STA VC integration with the STA Magnet (Cold Mass
Replica - CMR) was completed in December at SM - STA VC Arrived in Terni/INFN for Sine Sweep Tests
on January 10th - Test hardware was previously shipped to Terni and
testing has been completed - Ship STA VC to ESTEC for Acoustic Tests - March
07 - Return to CERN for integration in USS late
March 07 - Depends on results of STA VC/CMR sine sweep
acoustic tests
21AMS Flight Integration Hardware
- Flight USS is complete and has arrived at CERN
with the Primary Support Stand (PSS) and the
Primary Lift Fixture (PLF)
- Flight Vacuum Case is complete and will be
shipped to SCL/SM when they have room in their
facility to accommodate it (after Flight
Cryomagnet tests are completed and the SFHe Tank
is delivered and SFHe leak tested)
22Pre-integration of STAs in the Flight USS Prior
to STA VC Arrival
- STA Hardware Pre-integration in Flight USS
- On-line integration of the STA Crates/Radiators
on the USS will begin the week of February 5,
2007 before the STA VC arrives - This allows work to proceed even if the sine
sweep acoustic tests are delayed - 10T crane installation will be delayed until
after STA Pre-integration is complete at
beginning of March - If necessary, the USS/STAs in PSS will be moved
away from crane installation - There are 3-4 weeks available in March to use
the flight USS STAs for fit checks, cable
plumbing runs, measurements, etc.
23Pre-integration of STAs in the Flight USS Prior
to STA VC Arrival
- STA Hardware assembly in Flight USS (cont)
- Integration of all STAs in USS to be completed by
mid-April 07 - Even though the STA VC delivery to Terni slipped
5 weeks and the RAS readiness at CERN slipped 3
weeks, this is only 2 weeks later than
previously reported at AMS TIM on October 27,
2006 - Ship USS with STAs to Munich/IABG in April 07
- Static Tests
- Modal Tests
- Return USS with STAs to CERN in August 07
- Depends on results of STA VC/CMR sine sweep
acoustic tests and USS/STA modal static tests
24Interference between Flight VC/Magnet
Electronics Crates during Final Flight
Installation
- R. Becker/MIT, J. Kastelic P. Mott/JS, R.
Stafford-Allen/SM to determine how much room is
required to clear the Flight VC/Magnet as well as
how much room is available by Jan 29th. - Provide estimate of additional length required
for lower inter-radiator cables to M. Capell A.
Lebedev - Final cable routing must accommodate additional
length - Be sure theres no interference with hardware
mounted outboard of crate jigs during
pre-integration activities - Upper inter-radiator connections will be
disconnected because the additional length will
be too much additional weight - C. Lauritzen/JS to determine if there is any
problem on the USS if the brackets are
temporarily re-attached at a wider position by
Feb 5th - M. Molina/CGS to determine if Radiator brackets
are OK by Feb 5th - Consider using blocks/spacers under the brackets
and reattaching the lower struts - K. Bollweg J. Heilig will arrange trial test
using STA Crates/radiators in late February
25Pre-integration of Detectors on STA VC USS
prior to Cryomagnet Arrival
- All the detector groups have continued to
evaluate the pre-integration proposal and have
agreed that it should proceed according to the
schedules thoroughly discussed at this TIM - Current estimate of Pre-integration start
August, 2007 - Pre-integration finish December, 2007
- Optical fibers between ACC VC for TAS will be
installed - Constantly monitor the Cryomagnet progress and
decide how much more flight hardware to
pre-integrate - Current estimate of magnet delivery to CERN
February, 2008 - Do as little de-integration as possible just in
time to remove the STA VC and install the Flight
VC Cryomagnet in the USS
26Pre-integration of Detectors on STA VC USS
prior to Cryomagnet Arrival
- Consider removing the STA VC, Tracker, and ACC
from the USS as an assembly so parallel work can
continue during Flight VC/Magnet installation - Use VC rotation fixture and wheels/brackets
developed at SM - This could shorten deintegration by 2-3 weeks
thus allowing combined cosmic ray testing to be
extended
27Final integration of Detectors on Flight VC USS
after Cryomagnet Arrival
- All detectors must be integrated and functionally
tested with the Flight VC and
Cryomagnet at CERN by July, 2008 - Beam tests at CERN (1 month reserved)
- Thermal Vacuum Tests at ESTEC (3 months
reserved) - EMI Tests at ESTEC (1 month reserved)
- Delivery to KSC in December, 2008
28What we have sort of.
29(No Transcript)
30Where we must be by December 2008 at KSC...