Biggest Pitfalls and Best Practices: Life Safety - PowerPoint PPT Presentation

1 / 43
About This Presentation
Title:

Biggest Pitfalls and Best Practices: Life Safety

Description:

Biggest Pitfalls and Best Practices: Life Safety What Should I Know About the Life Safety Chapter? Healthcare Engineering Consultants – PowerPoint PPT presentation

Number of Views:202
Avg rating:3.0/5.0
Slides: 44
Provided by: GaryS203
Category:

less

Transcript and Presenter's Notes

Title: Biggest Pitfalls and Best Practices: Life Safety


1
Biggest Pitfalls and Best Practices Life Safety
What Should I Know About the Life Safety
Chapter?
Healthcare Engineering Consultants
2
Life Safety Compartmentation
Life Safety Building Compartmentation Drawings

Blue smoke barrier Green 1 hour fire wall
(hazardous area) Red 2 hour fire wall
Note The 2009 IBC now requires stencils to mark
smoke and fire walls
Healthcare Engineering Consultants
3
Life Safety Compartmentation
  • Smoke Barrier Compartmentation Requirements
  • Extends from floor to deck above
  • Barrier penetrations protected by smoke dampers
  • Smoke dampers not required in ducted
    penetrations where QRS sprinklers are installed
  • All penetrations sealed with appropriate
    materials
  • Doors are labeled 20-minute or 1-3/4 solid core
    type
  • Doors are self-closing
  • Positive latching not required
  • ½-hour smoke compartment must be at least two
    layers of ½ or more sheetrock (existing, one
    sheet on each side)
  • 1-hour compartment for new construction, 5/8 on
    each side


Healthcare Engineering Consultants
4
Life Safety Compartmentation
  • 1-hour Fire Barrier Compartmentation
    Requirements
  • Extends from floor to deck above
  • Transfer air grilles protected by fire dampers
  • All penetrations sealed with appropriate
    materials
  • Doors are labeled 45-minute or 1-hour
  • Doors are self-closing
  • Positive latching is required
  • 1-hour smoke compartment must be at least two
    layers of 5/8 sheetrock (X-type, one layer on
    each side) or equivalent


Healthcare Engineering Consultants
5
Life Safety Compartmentation
  • 2-hour Fire Barrier Compartmentation
    Requirements
  • Extends from floor to deck above
  • All duct penetrations protected by fire dampers
  • All penetrations sealed with appropriate
    materials
  • Doors are labeled 1.5 hour
  • Doors are self-closing
  • Positive latching is required
  • 2-hour smoke compartment must be at least four
    layers of 5/8 sheetrock or equivalent (X-type,
    two layers on each side)

Healthcare Engineering Consultants
6
Life Safety Compartmentation
  • Smoke and Fire Door Requirements
  • Undercut to floor not more than ¾
  • Vertical gap between doors not more than 1/8
  • Warpage to frame less than ½
  • All fire doors and frames must be labeled
  • Smoke doors must be labeled or 1-3/4 solid core
    construction
  • Doors must be self-closing
  • Positive latching is required for fire doors
    not for smoke doors
  • Door tampering is not permitted will alter the
    rating
  • Field installed protective plates gt16 not
    permitted on fire doors
  • (exceptions exist for doors to hazardous
    rooms)


Healthcare Engineering Consultants
7
Interim Life Safety Measures
  • Interim Life Safety Measures Requirement
  • Standard LS.01.02.01 from the Joint Commission
    Accreditation Manual
  • The hospital protects occupants during periods
    when the Life Safety Code is not met or during
    periods of construction

Healthcare Engineering Consultants
8
Interim Life Safety Measures
  • The Interim Life Safety Measures Process
    Includes the Following Steps
  • 1. Is an ILSM evaluation required?
    Y or N
  • If Yes, does the ILSM evaluation require the
    implementation of ILSM?
    Y or N
  • If Yes, which interim measures apply?
  • Implement and document the required measures
  • Note An interim life safety measures policy
    must be written and address each of the four
    steps listed above

Healthcare Engineering Consultants
9
Interim Life Safety Measures
  • Step 1 Is an ILSM evaluation required?
  • The need for an interim life safety measure
    evaluation is normally required whenever there is
    a life safety deficiency that is found, or
    renovation or construction activities create life
    safety deficiencies.
  • Be sure to do an ILSM evaluation for PFIs!
  • Include in the ILSM policy exclusions for
    evaluations, such as routine work orders or
    superficial projects

Healthcare Engineering Consultants
10
Interim Life Safety Measures
Interim life safety measures evaluation exception
for routine work orders or superficial projects
that do not impact life safety
Healthcare Engineering Consultants
11
Interim Life Safety Measures
  • Step 2 Are interim life safety measures
    necessary, based on the evaluation?
  • Interim life safety measure trigger points
    include the following
  • Egress is compromised, and alternative exits are
    necessary
  • Compartmentation is breached,and is considered
    serious
  • Part or all of the fire detection or
    extinguishing system has been taken out of
    service
  • Hot Work is being performed
  • Large quantities of combustible materials are
    present
  • Other conditions determined by the organization

Healthcare Engineering Consultants
12
Interim Life Safety Measures
Check which triggers (if any) apply for the
project Add other triggers, as desired If
none of the triggers are marked Yes, then no
additional action is required
Healthcare Engineering Consultants
13
Interim Life Safety Measures
Step 3 Which interim life safety measures
apply? The use of an ILSM applicability
matrix that helps to determine which interim
measures apply is helpful. The matrix can either
be pre-filled for specific conditions or left
blank until the evaluation process occurs. The
ILSM policy should describe how the interim
measures are selected, based on criteria
developed by the hospital.
Healthcare Engineering Consultants
14
Interim Life Safety Measures
  • Possible Interim Life Safety Measures Include
  • Fire watch
  • Alternative exit signage
  • Daily inspection of exits
  • Temporary, but equivalent fire alarm and
    detection systems
  • Additional fire fighting equipment
  • Temporary, smoke-tight, noncombustible
    partitions
  • Increased surveillance of buildings, grounds and
    equipment
  • Storage, housekeeping and debris removal
    practices
  • Additional staff training for staff who use fire
    equipment

Healthcare Engineering Consultants
15
Interim Life Safety Measures
  • Possible Interim Life Safety Measures Include
    (continued)
  • Additional fire drills
  • Inspect and test temporary systems monthly
  • Additional staff training related to the interim
    measures
  • Additional training to compensate for impaired
    fire or building features
  • Note Implementation of any or all of the interim
    life safety measures noted in the list above are
    based on criteria developed by the hospital and
    should be listed in the hospital interim life
    safety measures policy

Healthcare Engineering Consultants
16
Interim Life Safety Measures (ILSM)
Applicability Grid Example for Interim Life
Safety Measures

Compromise egress X X X X X X
Breach compartmentation X X X X X X X X X
Impair fire detection, alarm, suppression X X X X X X X X
Hot work X X
Large quantities of combustibles X X X X X X X X
Interim Measure
Ensuring Egress
Barriers
Notify Fire Dept
Fire equipment
Fire drills
Operational LS
Reduce combust.
Fire watch
Prohibit smoking
Other
Staff training
Surveillance
Deficiency
Healthcare Engineering Consultants
17
Interim Life Safety Measures
Example for Interim Life Safety Measures Chart

One or more of the interim measures listed on
the chart may be selected, based on the scope of
the project and the type of deficiency that
exists

Healthcare Engineering Consultants
18
Interim Life Safety Measures
Step 4 Implement and document the required
measures Whichever interim measures are
selected must be implemented and documented
Remember Failure to implement or document
interim life safety measures, when required, can
result Conditional Accreditation from the Joint
Commission!
Healthcare Engineering Consultants
19
Interim Life Safety Measures
Healthcare Engineering Consultants
20
Interim Life Safety Measures
Healthcare Engineering Consultants
21
Fire Watch Requirements
  • LS.01.02.01 EP 1
  • The hospital notifies the fire department (or
    other emergency response group) and initiates a
    fire watch when a fire alarm or sprinkler system
    is out of service more than 4 hours in a 24-hour
    period in an occupied building. Notification and
    fire watch times are documented
  • Question What constitutes when a fire alarm or
    sprinkler system is out of service?

Healthcare Engineering Consultants
22
Fire Watch Decision Grid
The requirement for a fire watch is determined by
the hospital staff. NFPA 101, section A.9.6.1.6
states it is not the intent of the Code to
require notification of the AHJ for a single
non-operating device or appliance
Healthcare Engineering Consultants
23
Other Interim Measures
  • What about interim measures for Utility Systems?
  • Interim fire system measures (IFSM)
  • Example Changing out the fire pump (also
    ILSM)
  • Interim emergency power measures (IEPM)
  • Example Changing the oil and filter in an
    emergency
  • generator
  • Interim medical gas system measures (IMGM)
  • Example Installing a new oxygen source
    valve

Healthcare Engineering Consultants
24
Interim Fire System Measures (IFSM)
  • What about interim measures for Fire Systems?
  • Example Replacing the fire pump
  • Possible Interim Measures
  • 1. Notify staff, local fire department and
    insurance company
  • 2. Provide for back-up pump, if possible
  • 3. Implement fire watch throughout affected
    areas
  • 4. Obtain additional portable fire
    extinguishers
  • 5. Perform replacement at non-critical times
  • 6. Other?

Healthcare Engineering Consultants
25
Interim Emergency Power Measures
  • What about interim measures for Emergency Power?
  • Example Changing the generator oil and filter
  • Possible interim measures
  • 1. Obtain back-up generator (not usually
    necessary)
  • 2. Notify staff in critically affected
    areas (ICU, OR, NICU, etc.)
  • 3. Perform service during less critical
    times
  • 4. Verify that back-up, battery-operated
    equipment is functional
  • 5. Remind staff of emergency procedures
    for no power
  • 6. Review procedures for actual normal
    power failure with service personnel

Healthcare Engineering Consultants
26
Interim Medical Gas Measures
  • What about interim measures for Medical Gas and
    Vacuum Systems?
  • Example Installing a new oxygen source valve
  • Possible interim measures
  • 1. Obtain truck with liquid oxygen tank
    and vaporizer to connect to emergency low
    pressure inlet
  • 2. Notify staff in affected areas
  • 3. Obtain additional H cylinders for
    back-feed, if necessary
  • 4. Perform installation during less
    critical time periods
  • 5. Verify that critical patient areas
    have adequate oxygen tanks

Healthcare Engineering Consultants
27
Interim Utility System Measures
Describe what actions the project requires
Be sure to notify the staff and departments that
will be affected, and which special procedures
are necessary
Maintain this and other related documentation in
the project file
Healthcare Engineering Consultants
28
Life Safety Pitfalls
Other Life Safety Deficiencies that are Likely
to be Found
Healthcare Engineering Consultants
29

Life Safety Deficiencies
Additional Note Joint Commission now accepts up
to 6 inch projections above 40 inches from the
floor
Healthcare Engineering Consultants
30
Compartmentation Deficiencies
Whats wrong with this seal?
Healthcare Engineering Consultants
31

Compartmentation Deficiencies
  • Repair of Smoke and Fire Wall Penetrations
  • Polyurethane foam should never be used as a
    sealant!
  • Intumescent materials should not only be
    tested, but pass the tests!
  • Smoke and fire ratings apply to the entire
    assembly
  • Smoke barriers (1/2 hour) need at least 1/2
    sheetrock (each side)
  • 1-hour fire barriers require at least 1-1/4 of
    sheetrock (2 layers)
  • 2-hour fire barriers require at least 2-1/2 of
    sheetrock (4 layers)
  • Insulation or mineral wool requires intumescent
    capping
  • Use the manufacturer applications book for
    proper installation
  • Unusual applications require an engineering
    judgment
  • The use of labels describing the seal is
    recommended

Healthcare Engineering Consultants
32

Egress Corridor Deficiencies
Whats wrong with this picture?
Healthcare Engineering Consultants
33

Egress Corridor Deficiencies
Corridor Interpretations Life Safety Code Means
of egress shall be continuously maintained free
of all obstructions or impediments to full
instant use in the case of fire or other
emergency (7.1.10.1) CMS and Joint Commission An
8-foot clear corridor width must be maintained .
. . CMS permits items to be in the corridor for
temporary use of one half-hour or less . . . Both
agencies agreed that computers on wheels (COWs)
may not be plugged in to recharge while in a
corridor (Mills, Zimmerman) Joint Commission
Carts on wheels permitted in the corridor when in
use COWs permitted when charting being
performed otherwise store in clean utility rooms
or patient rooms (EC News, 2/07)
Healthcare Engineering Consultants
34

Egress Corridor Storage
  • Additional Joint Commission Interpretations
  • Egress corridors greater than 8 feet in width may
    be partitioned to provide alcove storage for
    computers, equipment
  • Small (less than 50 square feet) dead-end
    corridors beyond the exit stairwell doorway may
    be used to store equipment
  • Where only offices exist in an egress corridor
    beyond an exit stairwell door, only 44 inches of
    clearance is required to be maintained in the
    corridor!
  • Important Note Although these
    interpretations were provided by George Mills
    (Joint Commission Senior Engineer) at the 2008
    ASHE Annual Conference, local AHJs may not
    permit these exceptions! Be careful!!

Healthcare Engineering Consultants
35

Egress Corridor Storage
Joint Commission Corridor Interpretations
Staff Office
Permitted Storage Space (if lt50 sq ft)
8 Width Egress Corridor
Exit Stair
Healthcare Engineering Consultants
36

Egress Corridor Storage
Joint Commission Corridor Interpretations
Staff Office
Permitted Storage Space (if lt50 sq ft)
44
8 Width Egress Corridor
Exit Stair
Healthcare Engineering Consultants
37

Request for Life Safety Code Equivalency
  • Traditional Procedure
  • Identify the deficiency (reference the LSC,
    state the intent)
  • Propose an alternate solution (provide
    explanation, drawings, cost, commitment of funds
    and timetable)
  • Get certification from PE, AIA, etc. and submit
    to JCAHO
  • FSES Procedure
  • Survey facility to determine deficiencies
  • Provide BBI for building in which equivalency is
    requested
  • Perform FSES evaluation for fire/ smoke zone in
    question
  • Determine if equivalent condition exists
  • Submit PFI with actions, cost, commitment of
    funds, timetable, and FSES worksheet to the Joint
    Commission

Healthcare Engineering Consultants
38

FSES Occupancy Risk Factors
Healthcare Engineering Consultants
39

FSES Safety Parameter Values
Healthcare Engineering Consultants
40

FSES Individual Safety Evaluations
Healthcare Engineering Consultants
41

FSES Fire Zone Equivalency Evaluation
Healthcare Engineering Consultants
42

FSES Fire Zone Equivalency Evaluation
Healthcare Engineering Consultants
43
Biggest Pitfalls and Best Practices Life Safety
Questions?
Healthcare Engineering Consultants
Write a Comment
User Comments (0)
About PowerShow.com