Title: Presentation to the Massachusetts DG Collaborative


1
Comparison of State and Federal Standard
Distributed Generation Interconnection Agreements
Presentation to the Massachusetts DG
Collaborative Gene Shlatz
November12, 2002
2
Presentation Overview
  • Summarize Interconnection Standards for States
    Where Enacted or Proposed
  • Includes FERC and NARUC Model Agreement
  • Compare These Standards to Those Proposed by
    Mass. Utilities
  • Identify Potential Best Practices

3
Standards and Procedures Reviewed
  • DG Classification
  • Thresholds
  • Expedited Application Review
  • Radial Network Systems
  • Cost Responsibility
  • Dispute Resolution
  • Interconnection Requirements

4
Interconnection Standards Reviewed
  • Texas PUCT Distributed Generation
    Interconnection Manual (May 2002) Co-Funded by
    DOE Office of Energy Efficiency Renewable
    Energy
  • New York PSC Standardized Interconnection
    Requirements, Application Process . . . For New
    DG 300kVA and Less (November 2000)
  • California PUCT Rulemaking, Rule 21 Model Tariff
    Language (Decision Issued December 2000)
  • FERC ANOPR Standardization of Small Generator
    Interconnection Agreements and Procedures (August
    2002)
  • NARUC Model Distributed Generation
    Interconnection Procedures and Agreement (July
    2002)
  • Specific Ratings and Thresholds Not Provided in
    Model Agreement
  • IEEE P1547 Draft Standard for Interconnecting
    Distributed Resources with Electric Power Systems
    (Draft 10, Issued August 2002)

5
DG Classification
  • Massachusetts 5 Levels
  • Up to 10kW, 10kW to 60kW, 60kW to 300kW, 300kW to
    1 MW, 1MW and Greater
  • Texas PUCT 2 Levels
  • Up to 300kW, 300kW to 10MW
  • No Provision for DG gt 10MW
  • New York PSC 1 Level
  • Up to 300kW
  • Standard Agreement Does Not Address DG gt300kW or
    Networks
  • California PUCT 2 Levels
  • Small Up to 11kVA Large Above 11kVA
  • FERC ANOPR 2 Levels
  • Small Up to 2MW Large 2MW to 20MW

6
Application Fees
  • Application Fees

7
Thresholds and Timeframes for Expedited
Processing of Applications
  • Radial Systems

8
Thresholds and Timeframes for Expedited
Processing of Applications
  • Network Systems

9
Cost Responsibility
  • Application Fees Some States Require Fees
    Others do Not Indicate if Fees Apply (See Prior
    Slides)
  • Study Fees Most States Impose Fees for DGs
    That do Not Meet Fast Track or Expedited Review
    Criteria
  • Texas Waives Fees if Certain Criteria Are Met
  • Several States Waive Fee Where Net Metering
    Applies
  • California Has 3-Level Fee Structure Initial
    Supplemental Detailed.
  • Initial and Supplemental Review Fees (Calif.) Are
    Capped (800 600)
  • Upgrades/Credits Not Addressed in Most States
  • California Cost Allocation Issues Will be
    Addressed in Next Phase Total Cost Borne by
    Applicant should be Reduced by Distribution Cost
    Allocation
  • Texas Utility Must Assess DG Benefits to System
    if Upgrades Required
  • FERC Transmission Rates Includes Credit for
    Reflect Network Upgrades
  • Operation Maintenance Not Addressed in Most
    States
  • California Places Obligation for Future OM on DG
    Customer

10
Dispute Resolution
11
Interconnection Requirements