KRONOS 3 Project - PowerPoint PPT Presentation

1 / 14
About This Presentation
Title:

KRONOS 3 Project

Description:

... will track the absence occurrences of employees a process currently done by hand. The project ended up being delayed by 18 months due to a snag in the software. ... – PowerPoint PPT presentation

Number of Views:291
Avg rating:3.0/5.0
Slides: 15
Provided by: Informatio297
Category:
Tags: kronos | project | snag

less

Transcript and Presenter's Notes

Title: KRONOS 3 Project


1
KRONOS 3 Project
  • Sherri Hayes
  • Tyler Stott

2
Background
  • Kronos is a time clock software. Perdue uses it
    to track employee time at work.
  • The Kronos 3 project is a software upgrade Perdue
    started in early 2006.
  • The upgrade will track the absence occurrences of
    employees a process currently done by hand.
  • The project ended up being delayed by 18 months
    due to a snag in the software.

3
Background Continued
  • Kronos is used in 60 locations including 18 large
    plants.
  • 22,000 employees rely on the Kronos software to
    ensure they get paid.

4
The Problem
  • Plants running Kronos have Human Resource staff
    manually entering absence information into
    Peoplesoft to track absence history and then
    prepare the appropriate coaching forms. Absence
    information is not readily available for all
    shifts. There is no standardized absence or
    manpower reporting.

5
Stakeholders
  • Executive Sponsor
  • Business Sponsor
  • Business Lead
  • IT Project Manager
  • Customers Plant Kronos locations
  • End Users Kronos Users and HR
  • Additional support required from Kronos

6
Scope What needs to be done
  • Replace current time clocks with the new 4500
    model.
  • Current time clocks are no longer manufactured
    and incompatible with the new software.
  • Upgrade current Kronos software to the Timekeeper
    5.1 version.

7
Project Plan
Baseline
Clocks
V5
Kronos 3
8
Hardware Replacement
  • The clock replacement was successful and was
    completed ahead of schedule.

9
Software Upgrade
  • The software was completed but Perdue soon
    realized that the vendor removed group scheduling
    functionality in the new version.
  • The upgrade was forced to be put on hold until
    Kronos resolved the issue.
  • Kronos agreed to release a new version
  • Perdue agreed to be apart of the Beta program to
    be released April 2007.

10
Cost to the Company
  • The project was delayed 18 months.
  • The company lost 200,000 dollars on licenses they
    purchased for version 5.1.

11
Result
  • The beta was tested through May 2007 and the new
    version 6 is currently being implemented and is
    scheduled to be completed by September 2008.
  • The project as a whole helped to strengthen
    vendor relations between Perdue and Kronos.

12
Lessons Learned
  • Critical to have committed business resources for
    a project.
  • Project team members ended up creating a work
    around for the version 5.1 software until the
    version 6 was released.
  • Develop a strong relationship with vendors.
  • If the vendor knew what Perdue needed maybe the
    delay would have been avoided.

13
Lessons Learned Continued
  • Importance of escalating an issue to all the
    stakeholders so they understand an issue that
    could delay a project.

14
References
  • Stacey Norton Perdue Farms project manager.
  • Kronos www.kronos.com
Write a Comment
User Comments (0)
About PowerShow.com