Baselining MECO - PowerPoint PPT Presentation

1 / 9
About This Presentation
Title:

Baselining MECO

Description:

A complete Work Breakdown Structure with its associated Dictionary in ... We have gone through one, relatively cursory, round of cost reviewing for the ... – PowerPoint PPT presentation

Number of Views:90
Avg rating:3.0/5.0
Slides: 10
Provided by: michael587
Category:

less

Transcript and Presenter's Notes

Title: Baselining MECO


1
Baselining MECO
  • Michael Hebert
  • UC Irvine
  • Feb 6, 2005
  • MECO Collaboration Meeting

2
The Bottom Line Up Front
  • We have eight weeks to develop our understanding
    of the project to a point where we are likely to
    pass a baseline review. We need
  • A complete Work Breakdown Structure with its
    associated Dictionary in sufficient detail to
    make an accurate accounting of the cost and
    schedule of events. Typically this is down to
    level 7 or more to set the scale
  • A complete set of Cost Books to accompany the
    cost estimate a collection of all of the input
    data and calculations used to come up with the
    cost numbers. Ideally vendor quotes based upon
    detailed drawings from engineering designs. If
    this is a strict baseline review, we will need
    one or more piece of supporting info for every
    cost number at the lowest level, i.e. these
    things are tomes
  • A complete Resource Loaded Schedule (RLS) the
    Project file containing all of the schedule links
    within each subsystem, between subsystems and
    between MECO and AGS pieces. This should have
    labor leveled to the extent possible and,
    combined with the costs, should match the funding
    profile we expect
  • A completely updated Technical Design Report
  • A revised Project Management Plan

3
Current MECO Project Organization
JOINT OVERSIGHT GROUP NSF DOE NP
DOE HEP NSERC
RSVP PROJECT DIRECTOR and DEPUTY W. Willis, J.
Kotcher
KOPIO PM WBS 1.2 M. Marx
BNL PM WBS 1.4 P. Pile
MECO PM WBS 1.3 M. Hebert
1.3.11 MECO Project Office
1.3.5 Tracker E. Hungerford
1.3.1 Extinction W. Molzon (acting)
Chief Mechanical Engineer
1.3.9 Integ. Install. MECO CME
1.3.2 Target Shield M. Hebert (acting)
1.3.6 Calorimeter P. Nemethy
1.3.10 Simulations Y. Kolomensky
Chief Electrical Engineer
1.3.3 Solenoids B. Smith
1.3.7 C R Shield J. Kane
Cost Schedule Manager
1.3.8 Trigger DAQ K. Kumar
1.3.4 Muon Beamline W. Morse
4
Status of Baseline Info WBS
  • For most systems the Work Breakdown Structure is
    in reasonable shape in that is appears deep
    enough to provide the needed details. There are
    exceptions, however
  • 1.3.2 Heat Shield for lack of someone to take
    on this task I have been handling this and have
    not dedicated enough time to evolve this to my
    satisfaction
  • 1.3.9 Simulations This would benefit from
    another pass and some detailed input from each of
    the detector systems on what they need when as
    design decisions are made
  • 1.3.10 Installation and Integration we need to
    either migrate installation tasks from each of
    the subdetectors to this area, or abandon the
    idea for the time being. The original notion was
    to unify this effort under the control of the
    MECO Chief Mechanical Engineer, a position we
    have not yet filled.
  • One consistent problem is that the WBS Dictionary
    is still very sparse below level 3 and in many
    cases there appears to be confusion between
    definition of the task/object and detailing the
    cost calculations. The latter are part of the
    Cost Book.

5
Status of Baseline Info Costs Cost Books
  • We have gone through one, relatively cursory,
    round of cost reviewing for the experiment
    including the magnets. The results of that
    review suggest that the committees did not find
    major problems, but they did not have time to
    drill deeply into the underlying assumptions and
    details.
  • One point the LOG review made was that we appear
    to be very light on Technician labor, at least in
    relation to Scientists. Although part of this is
    due to AGS work being in a separate WBS, it is
    worth a second look
  • In general all costs need more scrubbing. We
    need to get more people looking at each of these
    costs (up to now it has been Bill and I and the
    subsystem manager). I am looking for volunteers.
  • Cost Books My preferred approach is to do this
    electronically, although AGS and KOPIO will
    likely just go with binders. In detail
  • The basic cost info is dumped to a PDF file from
    the Access database (loaded shortly before the
    review by RSVP PO)
  • Additional info (quotes, sketches, calculations
    on napkins) get scanned into PDF files and
    appended to each subsection

6
Status of Baseline Info RLS
  • I was asked to come up with a labor profile over
    the five year construction project in the LOG
    Review. I was pleasantly surprised to find that
    there is a substantial amount of schedule
    information already in the Project file.
  • That said, the current file does not have the
    latest Magnet schedule info in it, nor has it
    undergone any sort of internal vetting.
  • Last week I learned that RSVP is going to request
    a first look at how well our cost profile matches
    the expected funding profile, preferably next
    week. I have rearranged the baselining schedule
    to make an attempt at that.
  • In particular I would like to get a list of major
    milestone dates in each subsystem in the next two
    weeks. Details in the baseline plan to follow.

7
Status of Baseline Info TDR
  • This document has not been updated since
    immediately prior to the June 2001 NSF Program
    review.
  • I believe the cost and schedule efforts will
    benefit from updating this sooner rather than
    later as it will force a rethink of everything in
    the system and provide background to anyone
    helping in the scrubbing process.
  • The first step in the process of updating this
    information is to produce or revise the Reference
    Design Documents for each major piece of MECO, as
    these amount to version-controlled parameter
    lists and can be plugged directly into the Cost
    Book to provide the drawings and channel counts
    needed.
  • Pulling the TDR together is another place where I
    could use one or more volunteer editors

8
Status of Baseline Info Man. Plan
  • This document has remained largely unchanged
    since 2003, meaning it does not reflect the
    current management structure.
  • There are numerous aspects of this that remain
    unclear as I outlined in the previous talk.
  • The primary need for the baselining effort is an
    RSVP Management Plan and Project Execution Plan
    the MECO, KOPIO, and AGS plans are likely to be
    appendices.
  • In short, I am holding off on revising this given
    my perception of its relatively low priority.

9
A Revised Schedule of Events
  • Pre-baseline Review in early April
  • Baseline Review in late April
  • First look at cost profile in two weeks
Write a Comment
User Comments (0)
About PowerShow.com