Title: Baselining MECO
1Baselining MECO
- Michael Hebert
- UC Irvine
- Feb 6, 2005
- MECO Collaboration Meeting
2The Bottom Line Up Front
- We have eight weeks to develop our understanding
of the project to a point where we are likely to
pass a baseline review. We need - A complete Work Breakdown Structure with its
associated Dictionary in sufficient detail to
make an accurate accounting of the cost and
schedule of events. Typically this is down to
level 7 or more to set the scale - A complete set of Cost Books to accompany the
cost estimate a collection of all of the input
data and calculations used to come up with the
cost numbers. Ideally vendor quotes based upon
detailed drawings from engineering designs. If
this is a strict baseline review, we will need
one or more piece of supporting info for every
cost number at the lowest level, i.e. these
things are tomes - A complete Resource Loaded Schedule (RLS) the
Project file containing all of the schedule links
within each subsystem, between subsystems and
between MECO and AGS pieces. This should have
labor leveled to the extent possible and,
combined with the costs, should match the funding
profile we expect - A completely updated Technical Design Report
- A revised Project Management Plan
3Current MECO Project Organization
JOINT OVERSIGHT GROUP NSF DOE NP
DOE HEP NSERC
RSVP PROJECT DIRECTOR and DEPUTY W. Willis, J.
Kotcher
KOPIO PM WBS 1.2 M. Marx
BNL PM WBS 1.4 P. Pile
MECO PM WBS 1.3 M. Hebert
1.3.11 MECO Project Office
1.3.5 Tracker E. Hungerford
1.3.1 Extinction W. Molzon (acting)
Chief Mechanical Engineer
1.3.9 Integ. Install. MECO CME
1.3.2 Target Shield M. Hebert (acting)
1.3.6 Calorimeter P. Nemethy
1.3.10 Simulations Y. Kolomensky
Chief Electrical Engineer
1.3.3 Solenoids B. Smith
1.3.7 C R Shield J. Kane
Cost Schedule Manager
1.3.8 Trigger DAQ K. Kumar
1.3.4 Muon Beamline W. Morse
4Status of Baseline Info WBS
- For most systems the Work Breakdown Structure is
in reasonable shape in that is appears deep
enough to provide the needed details. There are
exceptions, however - 1.3.2 Heat Shield for lack of someone to take
on this task I have been handling this and have
not dedicated enough time to evolve this to my
satisfaction - 1.3.9 Simulations This would benefit from
another pass and some detailed input from each of
the detector systems on what they need when as
design decisions are made - 1.3.10 Installation and Integration we need to
either migrate installation tasks from each of
the subdetectors to this area, or abandon the
idea for the time being. The original notion was
to unify this effort under the control of the
MECO Chief Mechanical Engineer, a position we
have not yet filled. - One consistent problem is that the WBS Dictionary
is still very sparse below level 3 and in many
cases there appears to be confusion between
definition of the task/object and detailing the
cost calculations. The latter are part of the
Cost Book.
5Status of Baseline Info Costs Cost Books
- We have gone through one, relatively cursory,
round of cost reviewing for the experiment
including the magnets. The results of that
review suggest that the committees did not find
major problems, but they did not have time to
drill deeply into the underlying assumptions and
details. - One point the LOG review made was that we appear
to be very light on Technician labor, at least in
relation to Scientists. Although part of this is
due to AGS work being in a separate WBS, it is
worth a second look - In general all costs need more scrubbing. We
need to get more people looking at each of these
costs (up to now it has been Bill and I and the
subsystem manager). I am looking for volunteers. - Cost Books My preferred approach is to do this
electronically, although AGS and KOPIO will
likely just go with binders. In detail - The basic cost info is dumped to a PDF file from
the Access database (loaded shortly before the
review by RSVP PO) - Additional info (quotes, sketches, calculations
on napkins) get scanned into PDF files and
appended to each subsection
6Status of Baseline Info RLS
- I was asked to come up with a labor profile over
the five year construction project in the LOG
Review. I was pleasantly surprised to find that
there is a substantial amount of schedule
information already in the Project file. - That said, the current file does not have the
latest Magnet schedule info in it, nor has it
undergone any sort of internal vetting. - Last week I learned that RSVP is going to request
a first look at how well our cost profile matches
the expected funding profile, preferably next
week. I have rearranged the baselining schedule
to make an attempt at that. - In particular I would like to get a list of major
milestone dates in each subsystem in the next two
weeks. Details in the baseline plan to follow.
7Status of Baseline Info TDR
- This document has not been updated since
immediately prior to the June 2001 NSF Program
review. - I believe the cost and schedule efforts will
benefit from updating this sooner rather than
later as it will force a rethink of everything in
the system and provide background to anyone
helping in the scrubbing process. - The first step in the process of updating this
information is to produce or revise the Reference
Design Documents for each major piece of MECO, as
these amount to version-controlled parameter
lists and can be plugged directly into the Cost
Book to provide the drawings and channel counts
needed. - Pulling the TDR together is another place where I
could use one or more volunteer editors
8Status of Baseline Info Man. Plan
- This document has remained largely unchanged
since 2003, meaning it does not reflect the
current management structure. - There are numerous aspects of this that remain
unclear as I outlined in the previous talk. - The primary need for the baselining effort is an
RSVP Management Plan and Project Execution Plan
the MECO, KOPIO, and AGS plans are likely to be
appendices. - In short, I am holding off on revising this given
my perception of its relatively low priority.
9A Revised Schedule of Events
- Pre-baseline Review in early April
- Baseline Review in late April
- First look at cost profile in two weeks