Title: Terms and Conditions of Tariff
1Terms and Conditions of Tariff
- MPERC Comments on CERC Discussion Paper
2In this presentation
- Market Development
- Transmission and wheeling charges for
Transmission Lines - Transmission and wheeling charges for
Inter-regional Lines - Tariff Setting
- Rate of return methodology
- Depreciation
- Development Surcharge
- Rate base
- Interest on working capital
- Operational norms
- Other Discussion Points
3Market Development
4Market DevelopmentTransmission and Wheeling
Charges
- Pan Caking (2.3.3.2)
- Definition Term used to describe stacking up of
charges in a transmission system due to repeated
application of charges for different regions
- Mechanism of charging
- Original Beneficiaries cover full cost
- Reimbursed by income from Open Access Charges and
from Traded Power
- Comments
- Expansion of network should be done on the basis
of a Long-Term Transmission Capacity Demand
Forecast (Example 7-Year Plan in UK) - Commission must regulate the level of investment
by CTU / STU and ensure that it is at a certain
margin above strictly required.
- Implications
- Increase in the landed cost of power
- Discouragement to inter regional exchange of power
- Comments
- Open Access mechanism of Regional Incremental
Postage Stamp
5Market DevelopmentTransmission and Wheeling
Charges for Inter-Regional Lines
- Sharing of Income from Open Access / Traded Power
- Should be adjusted on a monthly basis
- Should be returned to Firm Users in the
proportion of costs paid in that month
Charging of Fixed Costs
- Present system of sharing of costs of
Inter-regional assets is 5050 between Regions. - Method of charging should be changed to allocated
usage basis. - Provisional fixed costs may be charged based on
Allocation of Capacity in Agreement between CTU
and Beneficiaries - Adjustments to be made at the month-end based on
actual allocation. These adjustments may be
billed in next months bill
6Tariff Setting
7Tariff SettingRate of Return
- ROCE, ROE and Return on Debt
- Existing methodology
- Cost-plus approach
- ROE
- Interest rates have reduced
- Escrows and LCs are established
- Suggestion Government Bond Return 5 say 11
- Margin to cover
- Risk premium
- Investment incentive
- Return on Debt _at_ PLR
- Normative Debt Equity Ratio 8020
- ROCE 1180/100 1120/100 11
- Annual revision, retrospective-forward
compensation or through VCA
- Options
- ROE
- Return to equity investment is measured
- ROCE ( ROI)
- Return on total investment is measured
- Measured against WACC
- Incentive for optimization by financial
engineering / refinancing incentive to
investors - No FERV
- Beneficial to consumers
- ROCE may be adopted
8Tariff SettingDepreciation, Development Surcharge
Depreciation
Development Surcharge
- Purpose of depreciation
- Wear and tear
- Repayment of loan
- Comments
- Allow to explicitly charge loan repayment
- After full loan repayment, balance depreciation
may be charged on SLM till useful life of the
plant - Develop norms for loan repayment
- Rate PLR
- Term of loan Moratorium Minimum 10 years
- Buyers must be protected by ensuring term of PPA
is for the fair life of the plant. If such an
assurance is not given, then depreciate at the
current rates
- There should not be any such surcharge on the
beneficiaries for the purpose of creation of
corpus for investment in generation - Reasonable return is being provided
- Instead, a Developmental Charge may be levied for
a "Universal Service Obligation" Fund - USO Fund can be used for improving access to all
- Rural electrification programs
- Promotion to non-conventional sources
- Off-grid generation
9Tariff SettingRate Base, Interest on Working
Capital
- Rate Base
- Asset-side NFA approach
- Interest on Working Capital
- Allow interest portion as pass-through on net
Normative Working Capital - Net of working capital may be derived after
deduction of fuel costs
- Initial Capital Expenditure
- Initial Capex
- In case a prior order exists As per the order
- In case prior order does not exist Should be
determined by competitive bidding. - Norms must be developed by the CERC / CEA for
setting up of projects for quality of equipment,
costs, gestation, competitive bidding processes
for EPC etc - Additional Capex
- Allow subject to prior approval by the CERC
- Or, norms may be developed for this
10Tariff SettingOperating Norms
- Operating Norms
- Define operational norms this should consider
technology in place, inflation, age of the plant
/ equipment
- Generation Gross Calorific Value
- Price of coal is notified based on UHV and coal
consumed is determined based on GCV - There is a need of fixing norms for linking UHV
with GCV. - Norms for stacking and transit losses should also
be fixed based on transport mode and distance
- Operation and Maintenance Expenses
- Pass-through on actuals subject to a limit as a
percentage of capital costs - Allow a portion of the savings to be retained
- Generation Specific Oil Consumption
- Norms should be reduced to 2 ml/kwh from the
current 3.5 ml/kwh if the target PLF is above
normative - At low PLF Specific Oil Consumption is higher to
keep the furnace stable. Higher Sp.oil
consumption can be allowed at low targeted PLF
- Generation SHR
- Should be linked with guaranteed heat rate. A
reasonable margin should be provided above this
which should keep in view the age of the plant
11Other Issues
12Other Issues
- Tariff Period
- MPERC suggestion
- 5-year period, which is a business planning cycle
- May be reviewed before in case of drastic change
- Peak and Off-peak Tariff for Hydel
- MPERC suggestion
- Apply to depreciated hydel plants for peak period
- Off-peak tariff need not be changed
- Surplus income may be paid into a "Universal
Service Obligation" fund for to provide access to
all
- Declared Capacity
- Current Definition / Analysis
- One MWh ex-bus capacity
- Scheduling is on MW basis
- MPERC suggestion
- Change definition to MW basis
- Single Regional Tariff
- MPERCs views
- Promotes generation from lower cost stations,
since they now earn more, but an expensive
generator will not generate - Not recommended
- Individual tariff setting is preferable
13Other Issues
- Auxiliary Consumption
- Current
- MPERC suggestion
- Do not adopt the proposed change. A change will
result in beneficiaries bearing the cost of
losses between switchyard and bus
14MPERC
15Pan caking
Exporting Region
ER
Rourkela
Raipur
Chandrapur
SR
Ramagundam
TNEB
Selling price 200 P/U Landed cost 255
P/U Thus, pan caking is a major disincentive to
inter regional sale
Numbers are purely for the purpose of
illustrating the concept and may not be correct
16Transmission / OA Charges Inter-Regional Lines
17Tariff SettingOperating Norms