Title: Government Office for the North West Objective 2
1Government Office for the North WestObjective 2
- 24/25th February 2003
- APPs Risk Training Workshops
2Introduction
3The need for better risk and programme management
- Imminent continuing threat of decommitment
- Urgent requirement to mitigate risks and
reallocate funding to minimise funds lost - Need for a more proactive approach to programme
management - Opportunity to improve programme management
capability within GONW APPs - Context Reebok event, mid-term review
4Risk management information system
- Focus on spend ultimate importance of outputs
- Shared resource only as good as information
inputted - Co-owned system need feedback from partners to
improve - Realistic forecasts measure of project
management capability - Normal part of project management more
systematic structured approach
5Objectives of workshop
- To establish the basis for inputting to the new
management information - To develop a common understanding of risk
assessment and its role in project management - To provide some good practice benchmarks and
guidance on its use in an APP context
6Agenda
- Richard Caseley
- The risk form
- Heather Heaton
- Risk assessment and its role in project
management - Glyn Roberts
- Risk in the context of APPs
- Working session
7The Risk Form
8Risk Form
- Overview
- Inputs clarification of requirements
- Practical usage issues
- Outputs / benefits for active management
9Overview
Claim profile decommitment risk
Improved project management capability
Clear timely management info
RISK FORM
Claim Form
Risk Register
10Inputting
- Web-based tool using GONW server and linked to
interactive claim form (ICF) to avoid
double-entry - Claims not outputs are main focus
- Inputs to come from projects via APs
- Each AP will have 1 password with which it can
access all of its projects - Each project will have its own password
- Data input by project
- AP reviews data and issues to EPS
11Inputs required
- Data imported from Interactive Claim Form
inputs to Risk Form minimised - Basic input for all projects, more details for
approved projects - informs on delivery and pipeline
- Input level
- P1, P2 - project level
- P3 - claim element
- Monthly input
12(No Transcript)
13(No Transcript)
14(No Transcript)
15(No Transcript)
16Milestones
17Spend profile variability
18Benefits - general
- Reports at AP, county/sub-region, priority and
programme level - Regular management reporting
- Most probable claim
- Minimum and maximum possible spend
- Forecast vs actual
- Focuses on biggest variances
- Claim profile
- Timeline for projects (and claim elements for P3)
- Visibility of pipeline
19Introduction to risk
20The Risk Register
- Decisions about spend variability in the Risk
Form are based on the degree of risk inherent in
a project - A Risk Register is a tool for
- Understanding the nature and level of risk
- Managing risk effectively
21Risk management the basics
- The concept of risk
- Its role and relevance in project management
- Assessment of risk
- Management of risk
22What is risk?
- any potential threat or occurrence which may
prevent objectives being achieved in terms of - - Timescale
- - Cost
- - Quality/benefits
23Risk Management Process for each project
24Risk tools
- Risk register
- Advisory
- Helps to prepare for the risk form
- Useful management review tool
- Can be used at different levels of sophistication
- Risk form
- Required
- Will be used to assess likely spend profile
- Will assist in reallocation decisions
25Brainstorming the risk register
- Think of all the possible risks which the project
faces - Note them down, being careful to define them
clearly - Note the phase of the project they are most
likely to impact
26Assessment of Risk
- IMPACT
- Risks effect on cost/time/quality, if it occurs
- An impact is an effect on or days or
deliverables - PROBABILITY
- Likelihood of the risk occurring
- Expressed as a chance
27Assessments are input to the risk register
- Classify impacts as VL / L / M / H / VH on scale
1-5 - Risks around outcomes outputs should be
considered but are not relevant to the risk form
at this stage
28Combined impact
- A simple sum of the time cost quality effects
29Consider the likelihood of the risk occurring
- Very low
- Low
- Moderate
- High
- Very High
30Impact and likelihood combined are used to rank
risk
31Risk ranking prioritisation
- Impact x probability score
- Higher score higher risk
- Rank and prioritise actions accordingly
32Linking project risk assessment to risk form
inputs
- Take an overview of the projects risk register
- Consider the overall degree of risk around the
projects delivery - In terms of the value of claims
- In terms of timetable
- Greater risk will mean greater variability
- In claim forecasts
- In delays and durations
- eg greater difference between max min claim
forecasts for higher risk projects
33Spend profile variability
34Management of risk
- Identifying mitigation
- Allocating responsibility
- The importance of regular review
35Risk management
- Identify reasonable mitigation action
- Allocate a risk owner
- Set a date for review
36Questions to ask at review
- Each month consider
- Are all risks still relevant?
- Are there any new risks?
- Have they been mitigated as far as possible?
- Has mitigation reduced their likelihood or
impact? - Update risk register
- Update risk form
37Risk review is an essential component of good
project management
- Risk Review Allows
- - Tracking of risk mitigation actions
- - Up-to-date accurate forecasting
- Risk Review May
- - Lead to project modification / re-structuring
- - Lead to project cancellation
38Risk in the context of APPs
39APPLYING RISK ASSESSMENT/MANAGEMENT
- The Task
- Key risk principles
- Other funds risk requirements
- Typical Risks
- Key Stages for Assessment/Management
- Dealing with Common Risks
- Timing extent of process
40Objectives
-
- Delivery of Action Plan contract
- Partnerships responsible for
PROACTIVE management - and report back to EPS if problems
- Does Action Plan need adjustment?
41Key Principles
- Understand risk assessment
- Understand the projects
- Risk Awareness
- Common Sense (not rocket science!)
- Consider risks to
- Claim levels/profile (underspend/overspend
/delays) - Outputs (undershoot)
- Outcomes - quality
42Other Funders Requirements
-
- Match funds require risk assessment in appraisal
- Not much detailed guidance
- Tend not to emphasise risk management
- SRB Appraisal Guidance
- identify consider each component of risk
- take steps to minimise 'downside risks' (that
make project under-perform) - Similar - RDA, Lottery Funds, EP Gap Funding
43Typical Risk Categories
- Generic Risk categories
- Funding e.g. no types of sources
- Political risks/approvals
- Management capacity/capability
- Accommodation equipment
- Cost escalation overruns
- Market risk e.g. insufficient demand
44Typical Risk Categories
- Additional Priority 3 Risk Categories
- - Land acquisition
- - Unanticipated Site Issues
- - Legal Risk
- - Contractual Risk
-
- Other risks - examples
- - 3rd Party actions
- - Underspend
- - Overspend
- - No claim
- - Weather
- - Costs associated with transfer to
private sector
45Project risk process
- - Risk register (guidance approach/other)
- - Identify risks for each element of
project - - Plan of action risk plan
- - Take action
- - Performance review to track results
46Ongoing risk assessment in project management
- Start early for greatest benefit
- Part of project appraisal
- Identify mitigation and allocate clear ownership
within project team - Project Manager to manage risk and review
regularly (monthly) - APs may need to take more of a lead for Priority
2 projects -
47Dealing with Common Risks
- APPs EPS should consider
- - Any pattern of common risks in groups of
projects? - - Ask questions
- - Collaborative or across the board actions to
mitigate common risks? (as started from Reebok)
48Even with good assessment unforeseen risks often
arise therefore
Risk assessment mitigation a continuous
process - To project completion/exit/succ
ession - Not just at development
appraisal Link to monitoring and
evaluation - Feedback experience Build
capability to deal with risk
49Process Outputs
50Pulling it all together
- Risk analysis software combines all the project
level information to provide - An overview at AP level
- An overview at GO level
-
51At Action Plan level
- Report will show profile and variability of total
AP spend - AP will be able to target mitigation actions
appropriately - Overprogramming decisions can be made on the
basis of robust analysis - AP may choose to reallocate funds between
projects - AP may voluntarily decommit funds for
redistribution
52At EPS level
- Level of management intervention will be
proportional to capability displayed - In forecasting
- In delivery
- Programme wide analysis will inform decisions
about - Reallocation of funds between APs
- Decommitment
- Overprogramming
53Next steps
54Risk Analysis Programme
55Outcomes of workshop
- A basis for inputting to the new management
information - A common understanding of risk assessment and
its role in project management - Some good practice benchmarks and guidance on
its use in an APP context
56Conclusion some key points
-
- Co owned system shared benefits
- Partner feedback continuing support from
Scott Wilson and GO-NW - Information system reflects quality
- of risk management
- Immediate need , but long-term capacity
- building