Government Office for the North West Objective 2 - PowerPoint PPT Presentation

1 / 56
About This Presentation
Title:

Government Office for the North West Objective 2

Description:

The need for better risk and programme management. Imminent & continuing threat of ... Data imported from Interactive Claim Form inputs to Risk Form minimised ... – PowerPoint PPT presentation

Number of Views:37
Avg rating:3.0/5.0
Slides: 57
Provided by: scott687
Category:

less

Transcript and Presenter's Notes

Title: Government Office for the North West Objective 2


1
Government Office for the North WestObjective 2
  • 24/25th February 2003
  • APPs Risk Training Workshops

2
Introduction
  • Steve Martin

3
The need for better risk and programme management
  • Imminent continuing threat of decommitment
  • Urgent requirement to mitigate risks and
    reallocate funding to minimise funds lost
  • Need for a more proactive approach to programme
    management
  • Opportunity to improve programme management
    capability within GONW APPs
  • Context Reebok event, mid-term review

4
Risk management information system
  • Focus on spend ultimate importance of outputs
  • Shared resource only as good as information
    inputted
  • Co-owned system need feedback from partners to
    improve
  • Realistic forecasts measure of project
    management capability
  • Normal part of project management more
    systematic structured approach

5
Objectives of workshop
  • To establish the basis for inputting to the new
    management information
  • To develop a common understanding of risk
    assessment and its role in project management
  • To provide some good practice benchmarks and
    guidance on its use in an APP context

6
Agenda
  • Richard Caseley
  • The risk form
  • Heather Heaton
  • Risk assessment and its role in project
    management
  • Glyn Roberts
  • Risk in the context of APPs
  • Working session

7
The Risk Form
  • Richard Caseley

8
Risk Form
  • Overview
  • Inputs clarification of requirements
  • Practical usage issues
  • Outputs / benefits for active management

9
Overview
Claim profile decommitment risk
Improved project management capability
Clear timely management info
RISK FORM
Claim Form
Risk Register
10
Inputting
  • Web-based tool using GONW server and linked to
    interactive claim form (ICF) to avoid
    double-entry
  • Claims not outputs are main focus
  • Inputs to come from projects via APs
  • Each AP will have 1 password with which it can
    access all of its projects
  • Each project will have its own password
  • Data input by project
  • AP reviews data and issues to EPS

11
Inputs required
  • Data imported from Interactive Claim Form
    inputs to Risk Form minimised
  • Basic input for all projects, more details for
    approved projects
  • informs on delivery and pipeline
  • Input level
  • P1, P2 - project level
  • P3 - claim element
  • Monthly input

12
(No Transcript)
13
(No Transcript)
14
(No Transcript)
15
(No Transcript)
16
Milestones
17
Spend profile variability
18
Benefits - general
  • Reports at AP, county/sub-region, priority and
    programme level
  • Regular management reporting
  • Most probable claim
  • Minimum and maximum possible spend
  • Forecast vs actual
  • Focuses on biggest variances
  • Claim profile
  • Timeline for projects (and claim elements for P3)
  • Visibility of pipeline

19
Introduction to risk
  • Heather Heaton

20
The Risk Register
  • Decisions about spend variability in the Risk
    Form are based on the degree of risk inherent in
    a project
  • A Risk Register is a tool for
  • Understanding the nature and level of risk
  • Managing risk effectively

21
Risk management the basics
  • The concept of risk
  • Its role and relevance in project management
  • Assessment of risk
  • Management of risk

22
What is risk?
  • any potential threat or occurrence which may
    prevent objectives being achieved in terms of
  • - Timescale
  • - Cost
  • - Quality/benefits

23
Risk Management Process for each project
24
Risk tools
  • Risk register
  • Advisory
  • Helps to prepare for the risk form
  • Useful management review tool
  • Can be used at different levels of sophistication
  • Risk form
  • Required
  • Will be used to assess likely spend profile
  • Will assist in reallocation decisions

25
Brainstorming the risk register
  • Think of all the possible risks which the project
    faces
  • Note them down, being careful to define them
    clearly
  • Note the phase of the project they are most
    likely to impact

26
Assessment of Risk
  • IMPACT
  • Risks effect on cost/time/quality, if it occurs
  • An impact is an effect on or days or
    deliverables
  • PROBABILITY
  • Likelihood of the risk occurring
  • Expressed as a chance

27
Assessments are input to the risk register
  • Classify impacts as VL / L / M / H / VH on scale
    1-5
  • Risks around outcomes outputs should be
    considered but are not relevant to the risk form
    at this stage

28
Combined impact
  • A simple sum of the time cost quality effects

29
Consider the likelihood of the risk occurring
  • Very low
  • Low
  • Moderate
  • High
  • Very High

30
Impact and likelihood combined are used to rank
risk
31
Risk ranking prioritisation
  • Impact x probability score
  • Higher score higher risk
  • Rank and prioritise actions accordingly

32
Linking project risk assessment to risk form
inputs
  • Take an overview of the projects risk register
  • Consider the overall degree of risk around the
    projects delivery
  • In terms of the value of claims
  • In terms of timetable
  • Greater risk will mean greater variability
  • In claim forecasts
  • In delays and durations
  • eg greater difference between max min claim
    forecasts for higher risk projects

33
Spend profile variability
34
Management of risk
  • Identifying mitigation
  • Allocating responsibility
  • The importance of regular review

35
Risk management
  • Identify reasonable mitigation action
  • Allocate a risk owner
  • Set a date for review

36
Questions to ask at review
  • Each month consider
  • Are all risks still relevant?
  • Are there any new risks?
  • Have they been mitigated as far as possible?
  • Has mitigation reduced their likelihood or
    impact?
  • Update risk register
  • Update risk form

37
Risk review is an essential component of good
project management
  • Risk Review Allows
  • - Tracking of risk mitigation actions
  • - Up-to-date accurate forecasting
  • Risk Review May
  • - Lead to project modification / re-structuring
  • - Lead to project cancellation

38
Risk in the context of APPs
  • Glyn Roberts

39
APPLYING RISK ASSESSMENT/MANAGEMENT
  • The Task
  • Key risk principles
  • Other funds risk requirements
  • Typical Risks
  • Key Stages for Assessment/Management
  • Dealing with Common Risks
  • Timing extent of process

40
Objectives
  •  
  •         Delivery of Action Plan contract
  •         Partnerships responsible for
    PROACTIVE management
  •         and report back to EPS if problems
  •        Does Action Plan need adjustment?

41
Key Principles
  •         Understand risk assessment
  •         Understand the projects
  •         Risk Awareness
  •         Common Sense (not rocket science!)
  • Consider risks to
  •        Claim levels/profile (underspend/overspend
    /delays)
  •        Outputs (undershoot)
  •        Outcomes - quality

42
Other Funders Requirements
  •  
  • Match funds require risk assessment in appraisal
  • Not much detailed guidance
  • Tend not to emphasise risk management
  • SRB Appraisal Guidance
  • identify consider each component of risk
  • take steps to minimise 'downside risks' (that
    make project under-perform)
  • Similar - RDA, Lottery Funds, EP Gap Funding

43

Typical Risk Categories
  • Generic Risk categories
  • Funding e.g. no types of sources
  • Political risks/approvals
  • Management capacity/capability
  • Accommodation equipment
  • Cost escalation overruns
  • Market risk e.g. insufficient demand

44
Typical Risk Categories
  •  Additional Priority 3 Risk Categories
  • -         Land acquisition
  • -         Unanticipated Site Issues
  • -         Legal Risk
  • -         Contractual Risk
  •  
  • Other risks - examples
  • -         3rd Party actions
  • -         Underspend
  • -         Overspend
  • -         No claim
  • -         Weather
  • -         Costs associated with transfer to
    private sector

45
Project risk process
  • -         Risk register (guidance approach/other)
  • -         Identify risks for each element of
    project
  • -         Plan of action risk plan
  • -         Take action
  • -         Performance review to track results

46
Ongoing risk assessment in project management
  • Start early for greatest benefit
  • Part of project appraisal
  • Identify mitigation and allocate clear ownership
    within project team
  • Project Manager to manage risk and review
    regularly (monthly)
  • APs may need to take more of a lead for Priority
    2 projects
  •  

47
Dealing with Common Risks
  •  APPs EPS should consider
  • - Any pattern of common risks in groups of
    projects?
  • - Ask questions
  • - Collaborative or across the board actions to
    mitigate common risks? (as started from Reebok)

48
Even with good assessment unforeseen risks often
arise therefore
Risk assessment mitigation a continuous
process -         To project completion/exit/succ
ession -         Not just at development
appraisal  Link to monitoring and
evaluation -         Feedback experience Build
capability to deal with risk

49
Process Outputs
50
Pulling it all together
  • Risk analysis software combines all the project
    level information to provide
  • An overview at AP level
  • An overview at GO level

51
At Action Plan level
  • Report will show profile and variability of total
    AP spend
  • AP will be able to target mitigation actions
    appropriately
  • Overprogramming decisions can be made on the
    basis of robust analysis
  • AP may choose to reallocate funds between
    projects
  • AP may voluntarily decommit funds for
    redistribution

52
At EPS level
  • Level of management intervention will be
    proportional to capability displayed
  • In forecasting
  • In delivery
  • Programme wide analysis will inform decisions
    about
  • Reallocation of funds between APs
  • Decommitment
  • Overprogramming

53
Next steps
54
Risk Analysis Programme
55
Outcomes of workshop
  • A basis for inputting to the new management
    information
  • A common understanding of risk assessment and
    its role in project management
  • Some good practice benchmarks and guidance on
    its use in an APP context

56
Conclusion some key points
  •  
  •        Co owned system shared benefits
  •        Partner feedback continuing support from
    Scott Wilson and GO-NW
  •        Information system reflects quality
  • of risk management
  •        Immediate need , but long-term capacity
  • building
Write a Comment
User Comments (0)
About PowerShow.com