Title: Net Metering and Embedded Generation
1Net Metering and Embedded Generation
NB Climate Action Change Hub Advisory Committee
Meeting October 1, 2008 Saint John, NB Linda
Berthelot
2Net Metering and Embedded Generation Programs
- Background
- Net Metering Policy
- How Net Metering Works
- Summary of Invoicing
- Embedded Generation Policy
- Purchase Price
- Technical Requirements for Net Metering and
Embedded Generation
3Background
- Electricity from Renewable Resources Regulation
Electricity Act also known as Renewable Portfolio
Standard (RPS) requires an additional 10 of New
Brunswicks electrical energy must come from
renewable sources by 2016 (400 MW) this has
been accelerated to 2010 - NB Power currently has contracts with private
sector developers for 96 MW of wind energy by
2008, and another 213 MW by 2009
4Background
- Changes to the Electricity Act also opened doors
for independent power producers - In 2005 NB Power introduced Net Metering and
Embedded Generation policies which allows
independent power producers to connect their
generation units to the NB Power distribution
system (grid) - Net Metering for renewable generation
- Embedded Generation for renewable and
non-renewable generation - Total aggregate capacity for both programs is 21
MW
5Net Metering Policy
- Net metering projects must use a renewable energy
source (wind, solar, biomass, biogas, small hydro
and tidal) - The maximum size of generator is 100 kilowatts
(kW) - The output of the generation unit offsets the
customers electrical consumption from NB Power - Excess generation is delivered back to NB Powers
distribution system and this is measured with a
bi-directional or net meter
6Net Metering Policy
- The excess kWh are used to further reduce the
customers monthly consumption from NB Power
credited at the retail rate - Customers are billed for the net amount of
electricity used that is the electricity
delivered to the customer by NB Power, minus the
excess that customer sends back to the NB Power
distribution system - Excess credits not required within a billing
period may be carried forward to reduce future
consumption until March 31 of each year
7Cost to Connect
Since net metering is designed to help customers
offset their own electrical requirements, there
is no need for upgrades to NB Powers facilities
NB Power charges a service call fee of 40.47 to
change the meter
8What is Net Metering?
9Invoicing
- NB Powers meter does not measure electricity
generated by customers unit it only measures
kWh delivered to and received from customer - If readings indicate
- NB Power delivers 800 kWh
- NB Power receives 200 kWh
- Difference or Net 600 kWh
- Charged at prevailing NB Power residential retail
rate - HST applied to total supply from NB Power (800
kWh) and not net total
10Invoicing
- What if we receive more electricity from the
customer than what we deliver to them? - Ex
- NB Power delivers - 100 kWh
- NB Power receives - 200 kWh
- Difference - -100 kWh
- Customer is billed for minimum monthly service
fee of 19.73/21.63 and any rental and
applicable fees (LPC), etc - The excess 100 kWh can be carried forward to
future months to offset electricity from NB Power - Any credits remaining at the end of March each
year will be granted to the utility or reduced to
zero
11Embedded Generation
- NB Powers Embedded Generation policy will pay
Non Utility Generators for the useful output of
their generation unit. - Renewable and non-renewable generation units
- Current policy allows generation unit up to 2 MW
- Output of the generation unit is metered
separately from the customers on-site
electricity requirements - No on-site electricity requirements may be served
from the generation unit
12Embedded Generation
- The non-utility generator is responsible for any
and all upgrades resulting from the addition of
their generation unit to the distribution system - The upgrades include transformation, metering,
line extensions, line upgrades, line relocations,
etc - NB Power will complete a system impact study
prior to approval
13Generation Output Purchase Price
- Purchase price is reviewed and determined on a
case-by-case basis. Factors include - Contract term
- Type of generation
- Discos avoided energy cost
- Potential capacity deferral value
- Value for environmental attributes
14Technical Requirements for Net Metering and
Embedded Generation
- Installation requirements are as per NB Power
Technical Specification for Independent Power
Producers - Most net metering projects will be installed via
a certified grid-dependent inverters which
contain all of the technical and safety
requirements - All installations and electrical equipment must
be approved by a certification organization
recognized in the Province of NB - Installations must meet the requirements of NB
Department Public Safety Technical Inspection
Services
15Net Metering and Embedded Generation
NB Climate Action Change Hub Advisory Committee
Meeting October 1, 2008 Saint John, NB Linda
Berthelot