Title: Risk Assessment: the Generic Concept
1Risk Assessment the Generic Concept
- COMM80 Risk Assessment of Systems Change
- Unit 6
2Objectives of Session Coverage
- To understand the importance of risk assessment.
- To consider some generic techniques e.g.
prioritisation, ranking. - To introduce two specific techniques
(not dealt within in detail here) - To consider the use of software support tools.
3Why Assess Risks?How Assess Risks?
- Why? Because cant monitor all risks in a project
- so need to monitor and control the most
significant ones. - How?
- Quantify assign a value to each risk
- Prioritise use the risk value to assign a
priority typically high, medium, low (or some
numerical scale within a project). - Rank compare risks within a project against
their risk value to determine their relative
importance.
4Risk Quantification
- Risk (probability of occurrence) x (impact).
- Need to measure or estimate probability and
impact. - These are not absolute values but judgements made
by decision makers. - Probability is defined on a scale 0 to 1
(impossible to certain) or 0 to 100 - Impact is defined on a (user defined) scale
- e.g.scale 0 to 10 no impact (0) to catastrophic
(10)
5Generic techniques
- There are many techniques for risk assessment.
- Generic/standard techniques include
- Prioritisation and Ranking,
- Analytical Hierarchy Process,
- Decision Trees,
- Bayesian Belief Networks.
6Quantifying/ Ranking/Prioritising
- This basic approach will be illustrated using the
Risk RadarTM software to provide examples. - Risk RadarTM (V2.02) is a free software product.
- Developed by Integrated Computer Engineering, Inc
(ICE) under a DoD contract - Available from
- www.iceinceUSA.com and
- www.spmn.com (Software Program Managers Network
(SPMN)).
7Risk RadarTM Provides
- standard database functions to add and delete
risks, - specialised functions for prioritising and
retiring project risks. - Including prioritisation of risks through
automatic sorting and risk-specific movement. - the option of a user-defined risk management plan
and a log of historical events for each risk.
8Risk Radar - Initial form
9Set Up Project
10Risk Documentation
11Information About Individual Risks
- For each risk recorded additional information is
held - such as - the area of the project it affects,
- where control resides,
- etc.
12Prioritisation
- Subjective estimates are made
- based on professional judgement of the
- probability that a risk will occur and
- its negative impact on the project if it does.
- risk exposure probability impact value.
- risk exposure probability impact value.
- risk exposure probability impact value.
13Prioritisation
- Risk impact could be broken down and quantified
into all kinds of impacts areas, such as the
schedule impact in terms of days or cost impact
in financial terms, - in reality, it is not possible to quantify these
impacts with any degree of accuracy. - Adding multiple impact areas adds complexity to
the risk management process for little
quantitative benefit. - The impact rating system only suggests the total
impact the risk could have on a specific project.
14Prioritisation
- Risk RadarTM does not assign any meaning to an
impact value. - The project team must define the meanings and
keep to them. - These numbers are, usually based on past
professional experience. - The software uses risk exposure as a means to
rank risks relative to one another within a
project. - It is inappropriate to compare risks across
projects solely based on numerical factors such
as probability, impact, or exposure. -
15Prioritising Risks in Risk Radar
The upper figure shows risks ranked according to
exposure rate. However, if a risk manager felt
that Poor Interface Design should have a higher
ranking than Poor Data Quality they could be
re-arranged them manually as shown below.
16View Risk Impact
17View Risk Impact
18Change in risks profile over time
April
to July