PACS Schedule
  • N. Gradmann
  • MPE

2
Schedule Status
  • Current schedule (14-2-01) is based on
    commitments by all consortium members of PACS.
  • There is no negativ margin
  • The schedule is very tight approx 80 of all
    activities are on the critical path

3
PACS instrument key dates
  • 1/01 Start of AVM integration and test
  • 9/02 Start of CQM Instrument tests
  • 7/03 CQM delivery to ESA (delay 3 months)
  • 12/03 Start of PFM Instrument tests
  • 8/04 PFM delivery to ESA (delay 2 months)
  • 4/05 Start of FS Instrument tests
  • 10/05 FS delivery to ESA (delay 4 months)

4
Candidates for further delay
  • Design schedule for all Warm Electronics AVM
    models is very tight AVM test may not start on
    time
  • risk delay of some weeks, no inputs for FM from
    tests
  • still critical development under way CRE,
    Bolometer, Grating, Calibration sources
  • risk delay of some weeks up to months
  • long cryo(!) calibration and test periodes
    without margin
  • risk delay in the order of several months