Title: Matthieu Michel
1INNOVATIVE ASSET MANAGEMENT AND TARGETED
INVESTMENTS USING ONLINEPARTIAL DISCHARGE
MONITORING MAPPING TECHNIQUES
Matthieu Michel May 2007
2What are the problems ?
- EDF Energy underground MV network 38 000Km
- Current replacement rate too low
- We dont know what cable to target
3Technology objectives
- Improve Quality of supply
- Gather real-time information on the condition of
the network - Target replacement/refurbishment programmes
4History latest developments (1/2)
2007
2003
2001
1999
- Automated downloads and analysis
- Web interface
5Some results (1/2)
Lead sheath joint failure
6Some results (2/2)
Cable replacement
Cable replacement and analysis
7What cannot be done ?
- Detect and Locate all the faults
- Faults too far
- Earthing not suitable
- Some faults do not generate partial discharge
- Predict time of failures
8DEPLOYMENT AND BENEFITS
9Methodology
Database / Fault analysis
ANALYSIS
Spot testing
IDENTIFICATION
MONITORING
LOCATION
10Deployment (1/2)
Detection Zone
Network diagram showing the Primary substation
network being monitored
Network to Investigate
Partial Discharge Monitoring Equipment
11Deployment (2/2)
Network diagram showing a remote part of the
network being monitored
Detection Zone
Network to Investigate
12Technology benefits (1/2)
- Financial
- Reduction in operational expenditure Cost
savings of repairing faults - Better control of capital expenditure
Targeted cable replacements - Deferment of capital expenditure Avoiding
premature replacement - Quality of supply
- Reduction of the Customer Interruptions
Avoiding faults - Reduction in multiple interruptions More
accurate first diagnostic
13Technology benefits (2/2)
- Environmental
- Reduction of environmental impact and
disruptions Organised cable replacement
programme rather than emergency opening notices - Operational
- Versatile technology Multiple asset monitoring
(Cable, switchgear, etc) - Development of a robust cable replacement
strategy
14Deployment strategies (1/3) Large-scale
deployment
- Cost 30M (40 of primary substations equipped
and 2 equipment along each feeder)
Estimation on EDF Energy Network UK regulatory
regime
Long Payback period
15Deployment strategies (2/3) Surgical deployment
Estimation on EDF Energy Network UK regulatory
regime
Very limited impact
16Deployment strategies (3/3) Targeted deployment
- Cost 7.5M (10 of primary substations
equipped and 2 equipment along each feeder)
Estimation on EDF Energy Network UK regulatory
regime
Best cost / benefit solution
17Alternatives
- No deployment Increasing number of faults
operational cost - Increase Automation
- Necessary but would not reduce the number of
faults - Does not help the identification of degrading
sections of network - Off-line testing only
- Need for outages ? increases the risks on the
network - 20 years to cover the entire EDF Energy
underground cable network - Large-scale cable replacement impractical and
very expensive
18Conclusions
- Technology can deliver benefits now
- Some faults can be detected and located before
they occur - Target cable replacement
- Distributed equipment can be installed on remote
parts of the network - EDF Energy
- - Trial deployment Validate the impact of
targeted deployment - - Control system integration
- - Developed cable replacement strategy
- - Research Fault identification and estimation
of Time to failure