Project Management: A Managerial Approach - PowerPoint PPT Presentation

1 / 26
About This Presentation
Title:

Project Management: A Managerial Approach

Description:

Project Management: A Managerial Approach Chapter 8 Scheduling Overview WBS to Schedule Process PERT Schedule Types CPM Scheduling A schedule is the conversion of ... – PowerPoint PPT presentation

Number of Views:515
Avg rating:3.0/5.0
Slides: 27
Provided by: compengDi
Category:

less

Transcript and Presenter's Notes

Title: Project Management: A Managerial Approach


1
Project Management A Managerial Approach
  • Chapter 8 Scheduling

2
Overview
  • WBS to Schedule Process
  • PERT
  • Schedule Types
  • CPM

3
Scheduling
  • A schedule is the conversion of a project action
    plan into an operating timetable
  • It serves as the basis for monitoring and
    controlling project activity
  • Taken together with the plan and budget, it is
    probably the major tool for the management of
    projects

4
Scheduling
  • In a project environment, the scheduling function
    is more important than it would be in an ongoing
    operation
  • Projects lack the continuity of day-to-day
    operations and often present much more complex
    problems of coordination

5
Scheduling
  • The basic approach of all scheduling techniques
    is to form a network of activity and event
    relationships
  • This network should graphically portray the
    sequential relations between the tasks in a
    project
  • Tasks that must precede or follow other tasks are
    then clearly identified, in time as well as
    function

6
Scheduling
  • Such networks are a powerful tool for planning
    and controlling a project and have the following
    benefits
  • It is a consistent framework for planning,
    scheduling, monitoring, and controlling the
    project
  • It illustrates the interdependence of all tasks,
    work packages, and work elements
  • It denotes the times when specific individuals
    must be available for work on a given task

7
Scheduling
  • Network benefits (cont.)
  • It aids in ensuring that the proper
    communications take place between departments and
    functions
  • It determines an expected project completion date
  • It identifies so-called critical activities that,
    if delayed, will delay the project completion
    time
  • It identifies activities with slack that can be
    delayed for specific periods without penalty

8
Scheduling
  • Network benefits (cont.)
  • It determines the dates on which tasks may be
    started - or must be started if the project is to
    stay on schedule
  • It illustrates which tasks must be coordinated to
    avoid resource timing conflicts
  • It illustrates which tasks may run, or must be
    run, in parallel to achieve the predetermined
    project completion date
  • It relieves some interpersonal conflict by
    clearly showing task dependencies

9
Simple Schedule Gantt Chart
10
Network Techniques PERT and CPM
  • With the exception of Gantt charts, the most
    common approach to scheduling is the use of
    network techniques such as PERT and CPM
  • The Program Evaluation and Review Technique
    (PERT) was developed by the U.S. Navy in 1958
  • The Critical Path Method (CPM) was developed by
    DuPont, Inc during the same time period

11
Network Techniques PERT and CPM
  • PERT has been primarily used for research and
    development projects
  • CPM was designed for construction projects and
    has been generally embraced by the construction
    industry
  • The two methods are quite similar and are often
    combined for educational presentation

12
Scheduling Terminology
  • Activity - A specific task or set of tasks that
    are required by the project, use up resources,
    and take time to complete
  • Event - The result of completing one or more
    activities. An identifiable end state occurring
    at a particular time. Events use no resources.
  • Network - The combination of all activities and
    events define the project and the activity
    precedence relationships

13
Scheduling Terminology
  • Path - The series of connected activities (or
    intermediate events) between any two events in a
    network
  • Critical - Activities, events, or paths which, if
    delayed, will delay the completion of the
    project. A projects critical path is understood
    to mean that sequence of critical activities that
    connect the projects start event to its finish
    event

14
Scheduling Terminology
  • An activity can be in any of these conditions
  • It may have a successor(s) but no predecessor(s)
    - starts a network
  • It may have a predecessor(s) but no successor(s)
    - ends a network
  • It may have both predecessor(s) and successor(s)
    - in the middle of a network
  • Interconnections from horizontal links in
    vertical WBS

15
Hypothetical Network
Calculate t(e) and Z for this network
16
Activity and Project Frequency Distributions
17
PERT Activity Calculation
t(e) a 4m b a Most Optimistic (MO)
6 m Most Likely (ML) b Most
Pessimistic (MP) t(e) Activity Duration
When a single estimate for activity time is not
sufficient!
18
PERT Schedule Probability
Z T(S) T(E) Z Probability of
vSSD(TE)2 Meeting Schedule Z T(S)
T(E) T(S) Scheduled Duration
vSVar(TE) T(E) Critical Path Duration

Z is derived from a table of predetermined
probabilities
19
PERT Activity Times Variances
20
Variance of Activity Estimates
21
Critical Path
TE 30 13 16 5 64 Var(TE) 25 9 1
1 36
22
Possible Project Durations
Z (67 64) / v(25 9 1 1) 0.5 Hence,
the probability of meeting the target schedule
(Ts) is 0.69 (69)
23
Z Table
24
Z-Table Expanded
25
Gantt Charts
  • The Gantt chart shows planned and actual progress
    for a number of tasks displayed against a
    horizontal time scale
  • It is an effective and easy-to-read method of
    indicating the actual current status for each set
    of tasks compared to the planned progress for
    each item of the set
  • It can be helpful in expediting, sequencing, and
    reallocating resources among tasks
  • Gantt charts usually do not show technical
    dependencies

26
Gantt Charts
  • There are several advantages to the use of Gantt
    charts
  • Even though they may contain a great deal of
    information, they are easily understood
  • While they may require frequent updating, they
    are easy to maintain
  • Gantt charts provide a clear picture of the
    current state of a project
  • They are easy to construct

27
Drawing Networks
  • Activity-on-Arrow (AOA) networks use arrows to
    represent activities while nodes stand for events
  • Activity-on-Node (AON) networks use nodes to
    represent activities with arrows to show
    precedence relationships
  • The choice between AOA and AON representation is
    largely a matter of personal preference

28
Drawing Networks

29
Hypothetical Network
3
2
5
6
1
4
30
AOA Network Building Blocks
31
Partial Koll Business Center - AOA
32
Partial AOA Network
33
Partial AOA Network
34
Full AOA Network
Legend
ActivityDuration
35
Activity-on-Node Network Fundamentals
Write a Comment
User Comments (0)
About PowerShow.com