Title: Project Management: A Managerial Approach
1Project Management A Managerial Approach
2Overview
- WBS to Schedule Process
- PERT
- Schedule Types
- CPM
3Scheduling
- A schedule is the conversion of a project action
plan into an operating timetable - It serves as the basis for monitoring and
controlling project activity - Taken together with the plan and budget, it is
probably the major tool for the management of
projects
4Scheduling
- In a project environment, the scheduling function
is more important than it would be in an ongoing
operation - Projects lack the continuity of day-to-day
operations and often present much more complex
problems of coordination
5Scheduling
- The basic approach of all scheduling techniques
is to form a network of activity and event
relationships - This network should graphically portray the
sequential relations between the tasks in a
project - Tasks that must precede or follow other tasks are
then clearly identified, in time as well as
function
6Scheduling
- Such networks are a powerful tool for planning
and controlling a project and have the following
benefits - It is a consistent framework for planning,
scheduling, monitoring, and controlling the
project - It illustrates the interdependence of all tasks,
work packages, and work elements - It denotes the times when specific individuals
must be available for work on a given task
7Scheduling
- Network benefits (cont.)
- It aids in ensuring that the proper
communications take place between departments and
functions - It determines an expected project completion date
- It identifies so-called critical activities that,
if delayed, will delay the project completion
time - It identifies activities with slack that can be
delayed for specific periods without penalty
8Scheduling
- Network benefits (cont.)
- It determines the dates on which tasks may be
started - or must be started if the project is to
stay on schedule - It illustrates which tasks must be coordinated to
avoid resource timing conflicts - It illustrates which tasks may run, or must be
run, in parallel to achieve the predetermined
project completion date - It relieves some interpersonal conflict by
clearly showing task dependencies
9Simple Schedule Gantt Chart
10Network Techniques PERT and CPM
- With the exception of Gantt charts, the most
common approach to scheduling is the use of
network techniques such as PERT and CPM - The Program Evaluation and Review Technique
(PERT) was developed by the U.S. Navy in 1958 - The Critical Path Method (CPM) was developed by
DuPont, Inc during the same time period
11Network Techniques PERT and CPM
- PERT has been primarily used for research and
development projects - CPM was designed for construction projects and
has been generally embraced by the construction
industry - The two methods are quite similar and are often
combined for educational presentation
12Scheduling Terminology
- Activity - A specific task or set of tasks that
are required by the project, use up resources,
and take time to complete - Event - The result of completing one or more
activities. An identifiable end state occurring
at a particular time. Events use no resources. - Network - The combination of all activities and
events define the project and the activity
precedence relationships
13Scheduling Terminology
- Path - The series of connected activities (or
intermediate events) between any two events in a
network - Critical - Activities, events, or paths which, if
delayed, will delay the completion of the
project. A projects critical path is understood
to mean that sequence of critical activities that
connect the projects start event to its finish
event
14 Scheduling Terminology
- An activity can be in any of these conditions
- It may have a successor(s) but no predecessor(s)
- starts a network - It may have a predecessor(s) but no successor(s)
- ends a network - It may have both predecessor(s) and successor(s)
- in the middle of a network - Interconnections from horizontal links in
vertical WBS
15Hypothetical Network
Calculate t(e) and Z for this network
16Activity and Project Frequency Distributions
17PERT Activity Calculation
t(e) a 4m b a Most Optimistic (MO)
6 m Most Likely (ML) b Most
Pessimistic (MP) t(e) Activity Duration
When a single estimate for activity time is not
sufficient!
18PERT Schedule Probability
Z T(S) T(E) Z Probability of
vSSD(TE)2 Meeting Schedule Z T(S)
T(E) T(S) Scheduled Duration
vSVar(TE) T(E) Critical Path Duration
Z is derived from a table of predetermined
probabilities
19PERT Activity Times Variances
20Variance of Activity Estimates
21Critical Path
TE 30 13 16 5 64 Var(TE) 25 9 1
1 36
22Possible Project Durations
Z (67 64) / v(25 9 1 1) 0.5 Hence,
the probability of meeting the target schedule
(Ts) is 0.69 (69)
23Z Table
24Z-Table Expanded
25Gantt Charts
- The Gantt chart shows planned and actual progress
for a number of tasks displayed against a
horizontal time scale - It is an effective and easy-to-read method of
indicating the actual current status for each set
of tasks compared to the planned progress for
each item of the set - It can be helpful in expediting, sequencing, and
reallocating resources among tasks - Gantt charts usually do not show technical
dependencies
26Gantt Charts
- There are several advantages to the use of Gantt
charts - Even though they may contain a great deal of
information, they are easily understood - While they may require frequent updating, they
are easy to maintain - Gantt charts provide a clear picture of the
current state of a project - They are easy to construct
27Drawing Networks
- Activity-on-Arrow (AOA) networks use arrows to
represent activities while nodes stand for events - Activity-on-Node (AON) networks use nodes to
represent activities with arrows to show
precedence relationships - The choice between AOA and AON representation is
largely a matter of personal preference
28Drawing Networks
29Hypothetical Network
3
2
5
6
1
4
30AOA Network Building Blocks
31Partial Koll Business Center - AOA
32Partial AOA Network
33Partial AOA Network
34Full AOA Network
Legend
ActivityDuration
35Activity-on-Node Network Fundamentals