Conceptual Plans for Electricity Transmission in the West - PowerPoint PPT Presentation

1 / 38
About This Presentation
Title:

Conceptual Plans for Electricity Transmission in the West

Description:

What Factors Influence the Nature of Inter-regional Transmission Plans. 4 ... Provide definitive actionable construction plan. 18. Method of Study & Results. 19 ... – PowerPoint PPT presentation

Number of Views:28
Avg rating:3.0/5.0
Slides: 39
Provided by: jackdavisl
Category:

less

Transcript and Presenter's Notes

Title: Conceptual Plans for Electricity Transmission in the West


1
Conceptual Plans for Electricity Transmission in
the West
2
Agenda
  • Decision factors
  • Study characteristics
  • Study method/results
  • Policy considerations

3
What Factors Influence the Nature of
Inter-regional Transmission Plans
?
4
Decision Factors
  • Load and load diversity

5
Load and Load Diversity
6
Load and Load Diversity
  • Installed Generation 26,400 MW

7
Load and Load Diversity
2,000 MW
  • Installed Generation 22,400 MW

8
Decision Factors
  • Load and load diversity
  • Reliability

9
Reliability
2,000 MW
  • Installed Generation 26,400 MW

10
Reliability
1,000 MW
1,000 MW
  • Installed Generation 22,400 MW

11
Reliability
1,000 MW
1,000 MW
  • Installed Generation 24,400 MW

12
Decision Factors
  • Load and load diversity
  • Reliability
  • Fuel source location

13
Fuel Source Location
2,000 MW
14
Decision Factors
  • Load and load diversity
  • Reliability
  • Fuel source location
  • Economics

15
Economics
  • Generation Displacement

Usage Factor
16
Study Characteristics
  • What study does
  • Provides broad base conceptual plans
  • Provides insight into issue trade-offs
  • Suggests principles for expansion guidance
  • Suggests financing mechanisms
  • Identifies alternatives to conventional
    transmission expansion

17
Study Characteristics
  • What study does not do
  • Evaluate plans through 2004
  • Study expansion of natural gas pipeline system
  • Consider generation capital costs least cost
    plan
  • Provide definitive actionable construction plan

18
Method of Study Results
19
Base Study Characteristics
  • Two generation expansion scenarios
  • Gas scenario
  • Other than gas scenario OTG

Base Year 2004
20
Base Study Characteristics
  • Simulated 2010
  • 2 per year load growth
  • 25 generation reserve margins
  • Performance analysis
  • Production cost model
  • Spreadsheet
  • Gas price variance
  • Hydro availability

Base Year 2004
21
Gas Scenario New Lines
  • Fig 14A - Estimated Cost 2.1B

22
(No Transcript)
23
Gas Scenario New Capacity
Fig 14B
24
(No Transcript)
25
Other Than Gas New Lines
Fig 15B - Estimated Cost 8B - 12B
26
(No Transcript)
27
Other Than Gas New Capacity
Fig 15C
28
(No Transcript)
29
Next Technical Steps
  • Evaluate alternate load growth scenarios and
    natural gas pricing
  • Incremental transmission analysis including DC
    options
  • Evaluate market power issues
  • Include emerging technology-based transmission
    applications

30
Five Recommended Principles
  • Principle 1
  • Any expansion of the transmission system must
    maintain reliability, support both load and
    resource diversity in the Western
    Interconnection, and enable an efficient
    wholesale electric market.

31
Key policy issues
  • 1. What is the value of increasing diversity in
    the fuels used to generate electricity?
  • 2. What is the value of transmission to mitigate
    generation market power?

32
Principle 2
  • Transmission pricing and cost recovery should
    provide incentives for regionally beneficial
    expansion and system improvement.

33
Transmission financing alternatives
  • Spread the costs of new transmission across all
    users of the transmission system.
  • Provide that a portion of the difference in
    electricity prices between two delivery points
    (congestion costs) is used to pay for new
    transmission to mitigate congestion.
  • Implement an open season model like that used
    for natural gas pipeline expansion.

34
Principle 3
  • A forward-looking Western interconnection-wide
    transmission planning process should be
    established.

35
Key policy issues
  • How can a proactive transmission planning process
    be instituted in the Western Interconnection?
  • How will new transmission technologies and
    non-transmission alternatives (load-based
    generation, energy efficiency and demand
    reduction) alternatives be considered?

36
Principle 4
  • Transmission should enable access to more
    economical and less-polluting resources, thereby
    minimizing environmental impacts on both a local
    and regional basis.

37
Principle 5
  • All siting review processes must be streamlined
    and coordinated. State review processes should
    address both local and interconnection-wide
    needs, and federal agency review processes must
    be coordinated internally as well as with state,
    tribal and local authorities.

38
Questions
?
Write a Comment
User Comments (0)
About PowerShow.com