The MRP Heuristic - PowerPoint PPT Presentation

1 / 20
About This Presentation
Title:

The MRP Heuristic

Description:

It is a widely used approach for production planning and scheduling in industry ... the demand for the items that are its immediate predecessors (its input items) ... – PowerPoint PPT presentation

Number of Views:38
Avg rating:3.0/5.0
Slides: 21
Provided by: Hyuns6
Category:

less

Transcript and Presenter's Notes

Title: The MRP Heuristic


1
The MRP Heuristic
  • MRP stands for Materials Requirement Planning
  • It is a widely used approach for production
    planning and scheduling in industry
  • It is the approach embedded in many commercially
    available software applications

2
MRP Assumptions
  • No capacity constraints
  • A task initiated in period t completes in period
    tai
  • Product structure is typically assumed to be of
    the assembly type

3
Formulation
4
The MRP Solution Approach
  • Solve the lot sizing problem for each item
    independently starting with the end-items
    (finished products) and working your way down the
    bill-of-material (BOM)
  • The selected production quantities for an item,
    determine the demand for the items that are its
    immediate predecessors (its input items)

5
Solving the Lot Sizing Problem
  • Solve the problem for each item optimally (e.g.,
    using the Wagner-Whittin algorithm)
  • Solve the problem approximately using a heuristic
    (e.g., using a fixed order period, a fixed order
    period, or a lot for lot heuristic)

6
Example
7
Example (Continued)
8
MRP Terminology
  • Netting determining net requirements against
    projected inventory for each period
  • Lot Sizing determining order quantities
  • Time Phasing determining when production orders
    should be initiated, given the production lead
    time
  • BOM Explosion determining gross requirements
    for components

9
MRP Terminology (Continued)
  • Master Production Schedule (MPS) due dates and
    quantities for all top level items (finished
    products)
  • Bill of Material (BOM) the items that goes into
    each sub-assembly and into the finished product
  • Projected Inventory (on hand plus scheduled
    receipts) for all items
  • Planned Lead times production lead times
  • Level code a number assigned to an item
    depending on the lowest position in the BOM where
    it can be found

10
The Netting Procedure
  • Dt Gross requirements in period t for some item
  • St Quantity currently scheduled to complete in
    period t (i.e., a scheduled receipt)
  • It projected on-hand inventory for the end of
    period t
  • Nt Net requirement for period t
  • Qt Planned orders in period t (production
    quantity initiated in period t)

11
The Basic Steps
  • Step 1 Let t 1
  • Step 2 It It-1 - Dt
  • Step 3 If It ? 0, then let t t 1 and go back
    to step 2, otherwise, let Nt - It and set Nt
    Dt for all t gt t
  • Step 4 Use a lot sizing method to determine Qt
    for t1,, T, taking into account the production
    leadtime
  • Step 5 Use the production quantities Qt in
    determining the gross requirements for all items
    that are used by the item under current
    consideration

12
Example - The Bill of Materials
A
B
100 (2)
200
500
300
300
400
100
600
300
400
13
Example The Input Data
14
Example Part A
15
Example Part B
16
Example Part 500
17
Example Part 100
18
Limitations of MRP
  • Capacity-insensitive
  • Assumes fixed lead times
  • Incentive to inflate lead times

19
The MRP Planning Loop
  • 1. Fixed lead times lead to poor due date
    performance
  • 2. Management decides to increase lead time
  • 3. Longer lead time requires longer forecasting
    horizon
  • 4. Longer forecasting horizon creates errors in
    estimating demand
  • 5. Errors in estimating demand lead to poor due
    date performance.
  • 6. Management decides to increase lead time

20
Enhancements to MRP
  • MRP II The functionality of materials
    requirement planning (MRP) capacity requirement
    planning (CRP)
  • APS Advanced Planning Systems (software
    applications with the ability to solve the
    underlying optimization problem)
  • ERP Enterprise Requirement Planning (MRP or APS
    capabilities integrated into an enterprise-wide
    information system)
Write a Comment
User Comments (0)
About PowerShow.com