Impacts of Mod 244 - PowerPoint PPT Presentation

1 / 10
About This Presentation
Title:

Impacts of Mod 244

Description:

( Highest daily demand between Oct May) ... Co-ordinated end date of MPRN and creation of new one. New values to be applied to new MPRN ... – PowerPoint PPT presentation

Number of Views:26
Avg rating:3.0/5.0
Slides: 11
Provided by: maxpem
Category:

less

Transcript and Presenter's Notes

Title: Impacts of Mod 244


1
Impacts of Mod 244
  • Steve Nunnington
  • xoserve

2
Background
  • 96.5 of transportation charges based on
    capacity.
  • These are dependent on historical throughput.
  • Capacity charges on DM sites are based on-
  • Bottom Stop SOQ. (BSSOQ) applicable to certain
    Interruptible sites.
  • DM SOQ.
  • Interruptible sites still pay 50 of firm costs.
  • BSSOQ can only be amended in the AQ Amendment
    window.
  • BSSOQ is based on the consumption of the Uncapped
    Winter Peak. (Highest daily demand between Oct
    May)
  • Challenges are currently only allowed to those
    meter readings and consequently their derived
    consumption.
  • Number of challenges are very low.

3
Background
  • DM SOQ can only be reduced by shipper from
    October to January each year.
  • DM SOQ cannot fall beneath the value of the
    prevailing bottom stop SOQ.
  • DM SOQs are all passed to Networks for approval
    be they increases or decreases.
  • DM mandatory level is AQ of 58,600,000 Kwh below
    which they become voluntary.
  • Interruptible threshold AQ of 5,860,000 Kwh below
    which sites cannot be interruptible.
  • DM threshold. Site cannot be DM below AQ of
    73,200 Kwh. There are currently 158 of these.
  • AQ needs to be reduced in line with SOQ to ensure
    the supply point falls within the correct
    charging band.
  • Ratchet mechanisms currently apply only Oct
    May.
  • All these processes are fully systematised and
    are robust.

4
Analysis
  • There are 2058 DM supply points on xoserve
    systems.
  • Under Mod 244 there would be the following
    eligible sites-
  • DM Interruptible 1410
  • DM Firm Mandatory 185
  • TOTAL 1595
  • There are also 115 Unique Sites which qualify
    under the terms of the Mod but these could be
    dealt with under current US off line processes.

5
Analysis Comparing Feb 2008 Feb 2009
6
Analysis
  • This would mean under the terms of Mod 244 for
    all DM Mandatories the number of candidate sites
    would be as follows
  • 20 587
  • 30 479
  • 40 400
  • 50 350
  • Additionally 51 US would fall in line with the
    20 rate.
  • Looking ahead
  • Should BSSOQ as a concept be scrapped or the
    definition be changed? (E.G AQ/365)
  • Should we allow DM SOQ appeals throughout the
    year?
  • Should ratchets be applied all year round for
    eligible sites?

7
Possible solutions
  • Rebates on Billing (Off-Line)
  • Bills issued as normal using SOQs
  • Rebate issued at M2 to amended SOQ values
  • Monitoring of usage against various thresholds
    and consumption
  • Ratchet process required
  • Admin charge
  • Re-confirmation of the site under a new MPRN.
    (Off-Line)
  • Co-ordinated end date of MPRN and creation of new
    one
  • New values to be applied to new MPRN
  • Monitoring of usage against various thresholds
    and consumption
  • Ratchet process required
  • Admin charge
  • System solution (On-Line)
  • Investigating availability of a screen to amend
    BSSOQ.
  • Window for reducing DM SOQ may be parameterised.
  • Develop solution to monitor and carry out correct
    solutions when breaches apply.

8
Risks of an Off Line Solution
  • UK Link may not reflect true values
  • Labour Intensive.
  • Unique Sites process handles 115 sites.
  • Very labour intensive
  • Deals with around 20-25 of throughput
  • With 4.75 FTEs
  • Mod 244 currently has 587 candidates
  • Daily monitoring
  • Reads
  • SPA process (Does the Mod span transfers?)
  • Thresholds
  • Ratchets
  • Admin charge

9
Risks 2
  • Demand forecasting for Networks
  • Potential for manual errors in Billing
  • AQ could be out of sync with SOQ.
  • Process required to increase SOQ/AQ when site
    returns to normal production
  • Incorrect information regarding capacity
    availability.
  • Potential emergency impact if interruptible
    values are incorrect.
  • Development of off-line solution may be time
    consuming. Estimates range from 3 6 months from
    Ofgem approval.
  • Where shippers fail to comply there are complex
    activities such as ratchets that will need to be
    undertaken which will be both time consuming and
    labour intensive.
  • If analysis is incorrect and large volumes of
    supply points are submitted through this process
    the developed solution may not be appropriate.
  • DM CSEPS have not been considered along with
    impacts on IGTs.

10
Conclusions
  • Mod 244 should be driven by take up.
  • Small numbers will mean off line system
  • Larger numbers mean that a systematised solution
    is essential.
Write a Comment
User Comments (0)
About PowerShow.com