1 CALTRANS EXPERIENCE WITH WARRANTIES 2 WHY WARRANTY
Shift Responsibility of Quality Control to Contractor
State Responsibility to select good projects for warranty
Failure Avoidance
The Right Strategy at the Right Time 3 Failure Avoidance
Repair work done by State Maintenance crews. Severely Bleeding Pavement 4 Repairs Done By the State after Contract Acceptance
20 projects in last 3 years failed to meet expectations
Over 2.8 million in repairs by the state
Pavement defects include chip seals and overlays
5 HISTORICAL PERSPECTIVE
FIVE-YEAR WARRANTY REHAB PROJECT IN DISTRICT 2 (1993)
THREE-YEAR WARRANTY REHAB PROJECT IN DISTRICT 11 (1994)
SEVERAL FORM 42 MAINTENANCE PROJECTS (1998)
2 1/2-YEAR CAP-M WARRANTY PROJECT IN DISRICT 11 (1999)
6 HISTORICAL PERSPECTIVE
TWO-YEAR WARRANTY MAINTENANCE PROJECT IN DISTRICT 2 (2001)
ONE-YEAR WARRANTY MAINTENANCE PILOT PROGRAM (ON GOING)
FIVE-YEAR WARRANTY REHABILITAION PILOT PROGRAM (ON GOING)
7 DISRICT 2 REHAB PROJECT
Built in 1993
TWO INVOATIONS
Innovative SHRP Mix Design in One Direction
Reduced Thickness Design Over PCC
Asphalt Rubber Hot Mix Gap Graded (RAC-G)
Five-Year Warranty
It is Now 5-Years after Warranty Period Expired
Performing Well
Mtce Cost Data is Limited to Minor Crack Seal
No Major Maintenance is Currently Planned
8 D2-Sha-5 (BUILT IN 1993) ASPHALT RUBBER HOT MIX - GAP GRADED (RAC-G) 5 YEAR WARRANTY - 5 YEARS AFTER WARRANTY PERIOD 9 Imperial-111-PM 38.0-40.8 (3 Year Warranty)
12 FORM-42 (1 year Warranty) San Diego-94-PM 9.9-10.5 Asphalt Rubber (Type G)
Construction Completed 1998
No Maintenance Cost to date
Little to no cracking present
Good Candidate for addition PM Seal coat
13 FORM-42 Los Angeles-138-PM 0.0-2.6 Asphalt Rubber (Type-G)
Project constructed in 1998
Continues to show excellent performance with little to no cracking
14 Form-42 (1-yr Warranty) Imperial-78-PM 34.8-42.8 Asphalt Rubber Chip Seal 15 Form-42 (1-yr Warranty) Imperial-78-PM 34.8-42.8 Asphalt Rubber Chip Seal
Constructed in 1998
Note resistance to reflective cracking
Little to no cracking in the travelway.
Performing well
16 ONE-YEAR WARRANTY PILOT PROGRAM
Purpose
Improve Quality of Surface Treatments Without Significantly Increasing Initial Cost
Shifting QC Responsibility to the Contractor
Preventive Maintenance Projects
Over 30 Projects are Planned
Warranty Pilot began 1998
17 ONE-YEAR WARRANTY PILOT PROGRAM
Preventive Maintenance Strategies
Seals
AR Chip Seal
Slurry Microsurfacing
PME/PMA Chip Seal
Overlays
Conventional AC Dense Graded/Open Graded/PBA
Rubberized AC Open Graded/High Binder
Experimental
Bonded Wearing Course/Various
18 ONE-YEAR WARRANTY PILOT PROGRAM
Developed Specifications Jointly with Industry
Preventative Maintenance Projects
Minimum Exclusions (Less than 15)
Good Performance
No Claims
19 ONE-YEAR WARRANTY PILOT PROGRAM
6 Projects Constructed Out of Warranty Period
4 Projects Constructed Still in the Warranty Period
7 Projects Bid Pre-Construction Rating was Performed
7 Projects Planned for 03/04 FY
20 ONE-YEAR PILOT PROJECT PROGRAM
CONTINUOUS EVALUATION
FIELD PERFORMANCE
COST COMPARISON - WARRANTY PROJECTS VS. NON-WARRANTY PROJECTS
COST DURING CONSTRUCTION - WARRANTY VS. NON-WARRANTY
COST INCURRED BY CONSTRUCTION DURING WARRANTY PERIOD
COST INCURRED BY MAINTENANCE DURING FIRST YEAR AFTER CONSTRUCTION
COST PER LANE MILE - WARRANTY VS. NON-WARRANTY
21 D6-Fre-5 OPEN GRADED ASPHALT RUBBER - HIG BINDER Warranty Started on 12/08/00 22 Lessons LearnedContractor Vs. Dept. of TransportationSBD-5 RAC High Binder (Type-O) Contractors State
Quality Control (New Mix)
Numerous Trial Mix Designs
Aggregate Plant modified to keep up with needed production
Temperature Sensitive and haul time
Contractor Cost
increase material by 3.33 per ton
cost per lane mile 37,000/ln-MI
Risks
State concurrence for exclusions
Mobilize Rubber plant for repairs
Possible demands for multi-repair mobilization
Performance Measures
High Binder
Transfer risk to contractor
Select the right project to warranty
Designers and Engineers need better understanding of specifications
Exclusions shown on the plans
Contractor and Engineer need more time to review project
All projects need Pre and Post Evaluations
Specs needed modification
rut depth specified
exclusion from cracks
Improved Materials and Workmanship
no claims and only minor repairs
23 D8- SBD Route 40 OPEN GRADED ASPHALT RUBBER - HIG BINDER Warranty Started on 7/19/01 24 Lessons LearnedContractor Vs. Dept. of TransportationSBD- Route 40 RAC High Binder (Type-O) Contractors State
Designers and Engineers need better understanding of specifications
Exclusions shown on the plans
Contractor and Engineer need more time to review project
All projects need Pre and Post Evaluations
Specs needed modification
rut depth specified
exclusion from cracks
100 of project benefited from warranty
No claims performing well.
Request for exclusions
Issues over the rut depth specified
Contractor requested exclusion of all ruts. Average (rut depth 8-9mm)
Issue with unknown stability of mix
Existing pavement Crack issue
30 of project was warranted
25 ONE-YEAR PILOT PROJECT PROGRAM
SOME FINDINGS
PERFORMING WELL - NO WARRANTY FAILURES
NO CLAIMS
COST INCREASE (4 TO 14)
CONTRACTORS TOOK EXTRA EFFORT
NO PROBLEMS ENCOUNTERED WITH THE SPECIFICATION
26 ONE-YEAR PILOT PROJECT PROGRAM
SOME FINDINGS
PERFORMING WELL - NO WARRANTY FAILURES
NO CLAIMS
COST INCREDASE (4 TO 14)
CONTRACTORS TOOK EXTRA EFFORT
NO PROBLEMS ENCOUNTERED WITH THE SPECIFICATION
27 Contract Items for Preparatory Work
Need good up-front engineering
Good strategies
Good estimates
Need pay items
Dig outs
Grinding
Etc.
Excluded work and work limits must be clear
28 Performance is a Department Goal
Warranties require performance specifications
Means and methods specifications and warranties arent compatible
As directed by the Engineer is out
As needed to guarantee the work is in
29 Quality Control is the Contractors Business
Cultural shift for contractor and State
Contractors decide the outcome
Chip seal spread rate
Atmospheric temperature during placement
Smoothness
Etc.
How much control is needed to meet minimum quality for warranty period?
30 Work Completion/Warranty Switchover
Need process to switch from completed work to warranty period
Performance bond to warranty bond
Construction to monitoring
Similar to plant establishment period?
31 Performance vs. Warranty Bonds
AB 1745 Public contracts bonds.
Would require a state department to provide the contractor the option of either submitting a separate warranty bond to the department upon completion of the work or permitting the department to retain the contractor's performance and payment bonds until the end of the warranty period.
32 Who decides if warranty repair work is needed?
Resident Engineer (RE)
REs continue to be the States Representative during warranty period.
REs move on to other contracts
Maintenance Supervisor?
Drive the roadway every day
Vested interest
Knowledgeable
33 FIVE-YEAR WARRANTY PILOT PROGRAM
REHABILITAITON PROJECTS (10-YR DESIGN LIFE)
MINIMUM 15 ASPHALT RUBBER
THE SPEC IS OPEN TO ALL PROCESSES
FIVE PROJECTS
ONE PROJECT CONSTRUCTED IN D-7 ON ROUTE 150
FOUR PROJECTS WILL BE CONSTRUCTED IN 03/04
D2 - Route 395
D6 - Route 33
D10 - Route 140
D11 - Route 75
34 How to get quality product by low bid?
Improve up front engineering
Performance specifications
Warranty
Contractors prepare and follow quality control plan
35 ALTERNATIVE ACCEPTANCE DISTRICT 11 CAP-M PROJECT
Built in 1999 on ROUTE 8 - IMPERIAL COUNTY
CAP-M (5-YEAR DESIGN LIFE)
ASPHALT RUBBER HOT MIX - GAP GRADED (RAC-G)
IT WAS NOT BID AS A WARRANTY PROJECT
CONTRACTOR FAILED COMPACTION
2 1/2 WARRANTY PERIOD
CONTRACTOR CHOSE TO WARRANTY PAVEMENT INSTEAD OF PAYING PENALTY
IT WILL BE OUT OF WARRANTY IN OCT 2003
performing Well
36 SUMMARY
LIMITED EXPERIENCE WITH WARRANTIES
LIMITED NUMBER OF PROJECTS
REHAB AND MAINTENANCE PROJECTS
EXPERIMENTAL AND INNOVATIVE PROJECTS
TO ENSURE AGAINST FAILURE WHEN SPECS ARE NOT MET DURING CONSTRUCTION
TO TRY A NEW REPAIR STRATEGY
TWO PILOT PROGRAMS
ONE-YEAR WARANTY ON PREVENTIVE MAINTENANCE PROJECTS
PowerShow.com is a leading presentation sharing website. It has millions of presentations already uploaded and available with 1,000s more being uploaded by its users every day. Whatever your area of interest, here you’ll be able to find and view presentations you’ll love and possibly download. And, best of all, it is completely free and easy to use.
You might even have a presentation you’d like to share with others. If so, just upload it to PowerShow.com. We’ll convert it to an HTML5 slideshow that includes all the media types you’ve already added: audio, video, music, pictures, animations and transition effects. Then you can share it with your target audience as well as PowerShow.com’s millions of monthly visitors. And, again, it’s all free.
About the Developers
PowerShow.com is brought to you by CrystalGraphics, the award-winning developer and market-leading publisher of rich-media enhancement products for presentations. Our product offerings include millions of PowerPoint templates, diagrams, animated 3D characters and more.